Show Job Controls
Bid Cobra

TOM GREEN VARIOUS (0907-00-232)

Items: 6

County: TOM GREEN
Length: 0.0000 MILES
Highway: VARIOUS
District: SAN ANGELO
Control Number: 0907-00-232
DBE Goal: 0.0%
Project: C 907-00-232
Guaranty: $7,000.00
Time: 38 WORKING DAYS
Engineer's Estimate: $363,785.00
Date: 06/05/2025 (1 year ago)
Contract Number: 6253229
Type: BRIDGE MAINTENANCE
Project ID: A00196848
Project Description: CLEAN AND SEAL EXISTING BRIDGE JOINTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
THOMAS GATLIN
NATHANIEL MOORE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$363,785.00
$274,353.00
Over/Under Est: -24.58% -$89,432.00
$274,477.00
Over/Under Est: -24.55% -$89,308.00
Amt Left: 0.05% $124.00
Over/Under Est: 0.15% $540.50
Amt Left: 32.79% $89,972.50
Delta: -32.73% -$89,848.50
Over/Under Est: 2.26% $8,221.00
Amt Left: 35.59% $97,653.00
Delta: -2.11% -$7,680.50
Over/Under Est: 6% $21,838.00
Amt Left: 40.56% $111,270.00
Delta: -3.66% -$13,617.00
Over/Under Est: 8.94% $32,510.00
Amt Left: 44.45% $121,942.00
Delta: -2.77% -$10,672.00

Bid Items & Bid Tabulations

6 Total 0 of 6
TOM GREEN  |  VARIOUS  |  SAN ANGELO  |  0907-00-232  |  06/05/2025  |  $363,785.00  |  C 907-00-232  |  BRIDGE MAINT  |  38 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PATHFIELD INVESTMENTS LLC
MPB, INC.
SCR CIVIL CONSTRUCTION, LLC
12TWELVE ROAD AND BRIDGE LLC
O. TREVINO CONSTRUCTION, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 2,029.000 $45.000 $35.000 $55.000 $61.000 $60.000 $49.000 $65.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 3,234.000 $60.000 $50.000 $42.000 $47.250 $65.000 $45.000 $65.000
MOBILIZATION
LS 1.000 $55,000.000 $20,000.000 $24,000.000 $36,200.000 $20,000.000 $80,872.000 $38,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $8,000.000 $10,000.000 $1,500.000 $18,000.000 $10,001.000 $18,000.000 $3,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 16.000 $180.000 $100.000 $1.000 $200.000 $1.000 $300.000 $100.000
TMA (STATIONARY)
DAY 38.000 $120.000 $1.000 $1.000 $325.000 $1.000 $500.000 $200.000
Totals: $363,785.000 $274,353.000 $274,477.000 $364,325.500 $372,006.000 $385,623.000 $396,295.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
Total: $5,000.00