TOM GREEN VA (0907-00-186)

Items: 24

County: TOM GREEN
Length: N/A
Highway: VA
District: SAN ANGELO
Control Number: 0907-00-186
DBE Goal: N/A
Project: STP 2020(480)
Guaranty: N/A
Time: 61 WORKING DAYS
Engineer's Estimate: $1,833,018.40
Date: 01/10/2020 (6 years ago)
Contract Number: N/A
Type: PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$1,833,018.40
$1,506,526.80
Over/Under Est: -17.81% -$326,491.60
$1,523,627.70
Over/Under Est: -16.88% -$309,390.70
Amt Left: 1.14% $17,100.90
$1,549,727.16
Over/Under Est: -15.45% -$283,291.24
Amt Left: 2.87% $43,200.36
Delta: -1.71% -$26,099.46
Over/Under Est: -12.93% -$237,081.95
Amt Left: 5.93% $89,409.65
Delta: -2.98% -$46,209.29
Over/Under Est: -5.3% -$97,072.35
Amt Left: 15.23% $229,419.25
Delta: -8.77% -$140,009.60
Over/Under Est: -0.49% -$9,026.65
Amt Left: 21.07% $317,464.95
Delta: -5.07% -$88,045.70
Over/Under Est: 3.12% $57,135.85
Amt Left: 25.46% $383,627.45
Delta: -3.63% -$66,162.50
$2,060,786.25
Over/Under Est: 12.43% $227,767.85
Amt Left: 36.79% $554,259.45
Delta: -9.03% -$170,632.00

Bid Items & Bid Tabulations

24 Total 0 of 24
TOM GREEN  |  VA  |  SAN ANGELO  |  0907-00-186  |  01/10/2020  |  $1,833,018.40  |  STP 2020(480)  |  PAVMT MRK  |  61 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VIZCAINO, L.P.
L&L COMPANY
STRIPE-A-ZONE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
D. I. J. CONSTRUCTION, INC.
TRP CONSTRUCTION GROUP, LLC
CENTERLINE TECHNOLOGIES, LLC
BARRICADES UNLIMITED
MOBILIZATION
LS 1.000 $160,000.000 $3,000.000 $1.000 $4,500.000 $38,000.000 $25,500.000 $25,000.000 $1.000 $1.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,500.000 $1,000.000 $1.000 $0.010 $3,500.000 $100.000 $1,500.000 $1.000 $1.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,710.000 $0.850 $1.000 $0.500 $1.500 $2.000 $0.750 $1.000 $0.300 $0.270
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 78.000 $1.600 $1.000 $1.000 $1.800 $2.000 $2.000 $1.500 $1.000 $0.550
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,621.000 $0.600 $0.500 $0.600 $0.900 $1.000 $0.600 $1.000 $0.550 $0.550
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 5,003.000 $5.500 $3.000 $4.000 $4.950 $4.850 $6.750 $7.000 $5.000 $5.500
PAVEMENT SEALER 24"
LF 448.000 $1.200 $1.000 $1.000 $1.000 $1.350 $1.500 $1.000 $1.000 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 41,860.000 $0.240 $0.260 $0.270 $0.305 $0.360 $0.300 $0.350 $0.310 $0.270
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 130,301.000 $0.240 $0.260 $0.260 $0.305 $0.320 $0.280 $0.350 $0.300 $0.270
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,860.000 $0.240 $0.260 $0.270 $0.305 $0.360 $0.300 $0.350 $0.310 $0.270
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 140,094.000 $0.240 $0.260 $0.260 $0.305 $0.320 $0.280 $0.350 $0.300 $0.270
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 1,550,760.000 $0.530 $0.490 $0.500 $0.490 $0.500 $0.530 $0.580 $0.600 $0.700
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 167,270.000 $0.530 $0.500 $0.500 $0.500 $0.550 $0.580 $0.600 $0.610 $0.700
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 733,630.000 $0.530 $0.500 $0.500 $0.510 $0.500 $0.540 $0.590 $0.610 $0.700
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $210.000 $320.000 $250.000 $250.000 $265.000 $310.000 $250.000 $300.000 $250.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $255.000 $320.000 $300.000 $335.000 $365.000 $315.000 $300.000 $300.000 $350.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 36.000 $30.000 $35.000 $20.000 $55.350 $50.000 $40.000 $45.000 $30.000 $35.000
REFL PAV MRKR TY I-C
EA 133.000 $5.000 $10.000 $3.000 $4.000 $4.000 $10.000 $5.000 $5.000 $5.000
REFL PAV MRKR TY II-C-R
EA 58.000 $5.000 $10.000 $3.000 $4.000 $4.000 $10.000 $5.000 $10.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 90.000 $0.500 $10.000 $1.000 $1.250 $1.000 $1.000 $5.000 $8.000 $1.530
ELIM EXT PAV MRK & MRKS (24")
LF 509.000 $4.000 $1.000 $3.000 $3.000 $2.000 $3.000 $5.000 $8.000 $9.150
ELIM EXT PAV MRK & MRKS (36")(YLD TRI)
EA 37.000 $30.000 $10.000 $20.000 $24.500 $12.000 $11.000 $30.000 $20.000 $10.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 46,050.000 $5.000 $3.800 $4.000 $4.150 $3.500 $5.250 $4.200 $6.000 $4.750
TMA (MOBILE OPERATION)
DAY 110.000 $200.000 $50.000 $10.000 $0.010 $50.000 $160.000 $45.000 $1.000 $1.000
Totals: $1,833,018.400 $1,506,526.800 $1,523,627.700 $1,549,727.165 $1,595,936.450 $1,735,946.050 $1,823,991.750 $1,890,154.250 $2,060,786.250