Show Job Controls
Bid Cobra

TOM GREEN US 67 (0077-06-105)

Items: 37

County: TOM GREEN
Length: 0.0000 MILES
Highway: US 67
District: SAN ANGELO
Control Number: 0077-06-105
DBE Goal: 0.0%
Project: F 2026(139)
Guaranty: $100,000.00
Time: 69 WORKING DAYS
Engineer's Estimate: $13,517,647.99
Date: 12/02/2025 (6 months ago)
Contract Number: 12253013
Type: SEAL COAT
Project ID: A00195568
Contract Type: Federal
Project Description: SEAL COAT AND TY II PAVEMENT MARKINGS FY2026
Mail/Deliver Bids To: N/A
JESUS GARCIA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$13,517,647.99
$11,201,011.49
Over/Under Est: -17.14% -$2,316,636.50
$12,203,145.99
Over/Under Est: -9.72% -$1,314,502.00
Amt Left: 8.95% $1,002,134.50

Bid Items & Bid Tabulations

37 Total 0 of 37
TOM GREEN  |  US 67  |  SAN ANGELO  |  0077-06-105  |  12/02/2025  |  $13,517,647.99  |  F 2026(139)  |  SEAL COAT  |  69 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
CK NEWBERRY, LLC
ASPH (AC-20-5TR OR AC-20XP)
GAL 1,907,792.000 $3.500 $2.758 $2.500
AGGR (TY-PD, GR-4)(SAC-A)
CY 9,238.000 $128.000 $110.690 $130.000
AGGR (TY-PD, GR-3)(SAC-B)
CY 28,953.000 $102.000 $93.220 $118.000
MOBILIZATION
LS 1.000 $1,383,136.810 $1,203,623.110 $1,100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $8,000.000 $0.010 $95,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 72.000 $100.000 $0.010 $1.000
TMA (MOBILE OPERATION)
DAY 84.000 $200.000 $0.010 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,503.000 $1.000 $0.010 $0.600
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 32,048.000 $1.000 $0.010 $0.600
RE PV MRK TY I(BLACK)4"(SHADOW)(100MIL)
LF 600.000 $0.250 $2.000 $5.000
RE PM TY II (W) 6" (BRK)
LF 42,097.000 $0.170 $0.140 $0.150
RE PM TY II (W) 6" (DOT)
LF 1,350.000 $0.630 $0.300 $0.500
RE PM TY II (W) 6" (SLD)
LF 2,492,284.000 $0.160 $0.120 $0.130
RE PM TY II (W) 8" (DOT)
LF 259.000 $0.630 $1.000 $1.000
RE PM TY II (W) 8" (SLD)
LF 22,754.000 $0.250 $0.350 $0.450
RE PM TY II (W) 12" (DOT)
LF 364.000 $0.750 $5.000 $3.000
RE PM TY II (W) 24" (SLD)
LF 10,735.000 $2.600 $4.500 $3.500
RE PM TY II (Y) 6" (BRK)
LF 225,670.000 $0.180 $0.140 $0.140
RE PM TY II (Y) 6" (SLD)
LF 1,158,934.000 $0.170 $0.120 $0.130
RE PM TY II (Y) 8" (SLD)
LF 10,469.000 $0.500 $0.350 $0.450
PAVEMENT SLER 10"
LF 300.000 $1.000 $2.000 $3.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 600.000 $0.750 $2.000 $5.000
PREFAB PM TY C (W)(ARROW)
EA 42.000 $242.000 $220.000 $219.000
PREFAB PM TY C (W)(DBL ARROW)
EA 8.000 $335.000 $300.000 $278.000
PREFAB PM TY C (W)(UTURN ARROW)
EA 13.000 $325.000 $300.000 $318.000
PREFAB PM TY C (W)(LN REDUCT ARROW)
EA 16.000 $350.000 $350.000 $328.000
PREFAB PM TY C (W)(WORD)
EA 57.000 $300.000 $220.000 $242.000
PREFAB PM TY C (W)(RR XING)
EA 5.000 $560.000 $350.000 $625.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 226.000 $35.000 $18.000 $32.000
PREFAB PM TY C (W)(BIKE ARROW)
EA 6.000 $120.000 $200.000 $200.000
PREFAB PM TY C (W)(BIKE SYMBOL)
EA 3.000 $195.000 $200.000 $250.000
REFL PAV MRKR TY I-C
EA 1,130.000 $3.500 $4.000 $4.000
REFL PAV MRKR TY II-A-A
EA 27,124.000 $3.500 $4.000 $3.700
REFL PAV MRKR TY II-C-R
EA 2,242.000 $3.500 $4.000 $4.000
ELIM EXT PM & MRKS (6")
LF 130.000 $1.250 $5.000 $5.000
ELIM EXT PM & MRKS (8")
LF 50.000 $1.500 $5.000 $5.000
ELIM EXT PM & MRKS (RUMBLE STRIP)
LF 3,856,787.000 $0.100 $0.080 $0.150
Totals: $13,517,647.990 $11,201,011.486 $12,203,145.990