TOM GREEN US 67 (0077-06-095)

Items: 63

County: TOM GREEN
Length: N/A
Highway: US 67
District: SAN ANGELO
Control Number: 0077-06-095
DBE Goal: N/A
Project: NH 1602(524)
Guaranty: N/A
Time: 175 WORKING DAYS
Engineer's Estimate: $10,034,798.45
Date: 11/04/2016 (9 years ago)
Contract Number: N/A
Type: ACP OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$10,034,798.45
$6,339,169.41
Over/Under Est: -36.83% -$3,695,629.04
Over/Under Est: -22.05% -$2,213,005.25
Amt Left: 23.39% $1,482,623.79
Over/Under Est: -18.61% -$1,867,530.19
Amt Left: 28.84% $1,828,098.85
Delta: -4.42% -$345,475.06

Bid Items & Bid Tabulations

63 Total 0 of 63
TOM GREEN  |  US 67  |  SAN ANGELO  |  0077-06-095  |  11/04/2016  |  $10,034,798.45  |  NH 1602(524)  |  ACP OVERLAY  |  175 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
REECE ALBERT, INC.
PRICE CONSTRUCTION, LTD.
AUSTIN BRIDGE & ROAD SERVICES, LP
REMOVING CONC (CURB AND GUTTER)
LF 69.000 $12.000 $6.850 $14.370 $50.000
REMOVING CONC (MISC)
SY 54.000 $30.000 $11.220 $44.860 $50.000
REMOVING CONCRETE(MOW STRIP)
LF 175.000 $12.000 $5.900 $120.000 $50.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 304.000 $12.000 $4.660 $18.430 $10.000
REMOVING STAB BASE AND ASPH PAV(15")
SY 14,550.000 $20.000 $6.540 $9.580 $10.000
BACKFILL (TY A OR B)
STA 439.400 $190.000 $160.040 $130.300 $184.260
EMULS ASPH (PRIME)(MULTI)
GAL 6,170.000 $5.600 $2.870 $2.630 $5.000
ASPH (MULTI OPTION)
GAL 26,927.000 $4.000 $3.370 $3.500 $3.250
AGGR(TY-PD GR-4 SAC-B)
CY 1,259.000 $120.000 $98.370 $114.170 $210.000
AGGR(TY-PD GR-5 SAC-B)
CY 874.000 $130.000 $124.070 $164.640 $204.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 53,373.000 $4.000 $2.380 $2.470 $2.500
SUPERPAVE MIXTURES SP-C SAC-B PG70-22
TON 45,185.000 $110.000 $69.140 $88.090 $84.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(9")
SY 1,285.000 $80.000 $60.550 $67.770 $70.000
PLANE ASPH CONC PAV(2" TO 4")
SY 8,596.000 $4.000 $2.130 $2.370 $4.000
PLANE ASPH CONC PAV (1")
SY 124,059.000 $2.000 $0.810 $0.540 $1.350
PLANE ASPH CONC PAV (2")
SY 107,458.000 $3.000 $0.940 $0.880 $1.500
PLANE ASPH CONC PAV (1" TO 3")
SY 177.000 $3.000 $4.830 $11.100 $27.400
PLANE ASPH CONC PAV (2 1/2")
SY 3,280.000 $3.500 $1.900 $2.930 $6.000
PLANE ASPH CONC PAV(1" TO 2")
SY 1,485.000 $3.500 $2.120 $5.430 $13.070
PLAN ASPH CONC PAV (1" TO 2 1/2")
SY 17,491.000 $3.500 $1.720 $1.530 $3.000
PLANE ASPH CONC PAV (2" TO 6")
SY 3,923.000 $4.000 $2.830 $2.370 $5.000
CONC PVMT (CONT REINF - CRCP) (10.5")
SY 12,815.000 $105.000 $97.140 $103.950 $84.000
CONC PVMT (CONT REINF)(FAST TRK)(10.5")
SY 1,735.000 $150.000 $100.330 $121.800 $110.000
RIPRAP (MOW STRIP)(4 IN)
CY 24.000 $550.000 $810.380 $1,100.000 $500.000
CLEANING AND SEALING EXISTING JOINTS
LF 190.000 $40.000 $41.440 $115.500 $57.320
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 1.000 $600.000 $1,530.270 $525.000 $1,000.000
MOBILIZATION
LS 1.000 $734,000.000 $142,358.330 $530,700.000 $816,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $16,000.000 $17,353.210 $10,000.000 $26,400.000
CONC CURB (TY II)
LF 254.000 $25.000 $29.200 $63.000 $75.000
CONC CURB & GUTTER(VALLEY GUTTER)(36")
LF 92.000 $35.000 $35.130 $60.480 $75.000
INTERSECTIONS (ACP)
SY 294.000 $40.000 $51.460 $49.660 $59.720
RUMBLE STRIPS (SHOULDER)
LF 81,694.000 $0.200 $0.130 $0.080 $0.160
MTL W-BEAM GD FEN (STEEL POST)
LF 5,250.000 $25.000 $20.830 $19.950 $19.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 21.000 $2,350.000 $1,869.390 $1,449.000 $1,380.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 7.000 $1,350.000 $1,014.810 $892.500 $850.000
MTL BM GD FEN TRANS (NON - SYM)
EA 6.000 $1,200.000 $1,014.810 $682.500 $650.000
REMOVE METAL BEAM GUARD FENCE
LF 5,250.000 $5.000 $3.200 $1.260 $1.200
REMOVE TERMINAL ANCHOR SECTION
EA 7.000 $400.000 $213.640 $84.000 $80.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 22.000 $350.000 $213.650 $94.500 $90.000
GUARDRAIL END TREATMENT (INSTALL)
EA 25.000 $3,000.000 $2,002.920 $1,916.250 $1,825.000
GUARDRAIL END TREATMENT (REMOVE)
EA 25.000 $410.000 $213.640 $105.000 $100.000
REMOVE SM RD SN SUP&AM
EA 1.000 $150.000 $73.920 $21.000 $20.000
REMOVE BRDG MNT CLEARANCE SIGN ASSM
EA 1.000 $1,000.000 $649.300 $525.000 $500.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BR)
EA 97.000 $22.000 $26.710 $26.250 $25.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1 (BR)
EA 200.000 $22.000 $26.710 $26.250 $25.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 12,950.000 $0.250 $0.320 $0.320 $0.700
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 487.000 $5.000 $3.200 $3.150 $5.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 31,305.000 $1.000 $0.720 $0.700 $0.950
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 31,305.000 $1.000 $0.720 $0.700 $0.950
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,876.000 $1.600 $1.480 $1.970 $2.020
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 84.000 $1.000 $1.280 $1.260 $0.270
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 14,742.000 $0.850 $0.750 $0.740 $0.560
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 1,097.000 $3.000 $2.460 $2.420 $3.500
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 44.000 $4.000 $8.550 $8.400 $10.000
PAVEMENT SEALER 4"
LF 1,092.000 $0.500 $0.170 $0.170 $0.250
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 14,240.000 $0.350 $0.380 $0.380 $0.270
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 59,979.000 $0.350 $0.380 $0.380 $0.270
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 62,466.000 $0.350 $0.380 $0.380 $0.270
REFL PAV MRK TY I (W)12"(DOT)(090MIL)
LF 230.000 $3.500 $2.560 $2.520 $2.000
REFL PAV MRKR TY II-C-R
EA 1,932.000 $3.550 $3.630 $3.570 $4.750
SPOT DIAMOND GRINDING ASPH PVMT
SY 6,571.000 $21.500 $11.570 $11.760 $9.180
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 698.000 $100.000 $6.100 $100.000 $80.000
TMSP RADAR SPEED CONTROL MONITOR
EA 4.000 $12,000.000 $1,068.080 $5,725.810 $7,750.700
Totals: $10,034,798.450 $6,339,169.416 $7,821,793.200 $8,167,268.264