Show Job Controls
Bid Cobra

TOM GREEN US 87 (0070-02-099)

Items: 13

County: TOM GREEN
Length: N/A
Highway: US 87
District: SAN ANGELO
Control Number: 0070-02-099
DBE Goal: 0.0%
Project: STP 2024(659)HES
Guaranty: N/A
Time: 302 WORKING DAYS
Engineer's Estimate: $5,033,299.75
Date: 01/04/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
JORDAN SEFCIK
THOMAS GATLIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$5,033,299.75
$4,084,306.03
Over/Under Est: -18.85% -$948,993.72
Over/Under Est: -17.4% -$876,026.75
Amt Left: 1.79% $72,966.97
Over/Under Est: -13.39% -$673,873.35
Amt Left: 6.74% $275,120.37
Delta: -4.86% -$202,153.40
$4,714,452.23
Over/Under Est: -6.33% -$318,847.52
Amt Left: 15.43% $630,146.20
Delta: -8.14% -$355,025.83
Over/Under Est: -5.66% -$284,774.83
Amt Left: 16.26% $664,218.89
Delta: -0.72% -$34,072.69
$4,971,782.50
Over/Under Est: -1.22% -$61,517.25
Amt Left: 21.73% $887,476.47
Delta: -4.70% -$223,257.58

Bid Items & Bid Tabulations

13 Total 0 of 13
TOM GREEN  |  US 87  |  SAN ANGELO  |  0070-02-099  |  01/04/2024  |  $5,033,299.75  |  STP 2024(659)HES  |  HAZARD ELIM & SAFETY  |  302 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCOUT 5 CONSTRUCTION LLC
MASSANA CONSTRUCTION INC.
SCR CIVIL CONSTRUCTION, LLC
HJC FARMS, INC.
GRATIOT CONSTRUCTION, LTD.
3LW CIVIL LLC
BLADING
HR 289.000 $165.000 $0.010 $85.000 $215.000 $150.000 $113.640 $65.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 24.000 $850.000 $0.010 $950.000 $1,086.000 $1,241.770 $1,136.360 $50.000
RIPRAP (CONC) (CL A )
CY 5,103.000 $500.000 $550.000 $360.000 $476.000 $500.000 $454.060 $445.000
REMOV STR (SMALL FENCE)
LF 3,675.000 $4.500 $8.800 $5.000 $6.850 $5.000 $2.270 $37.000
MOBILIZATION
LS 1.000 $457,573.000 $200,000.000 $472,833.000 $127,100.000 $225,000.000 $440,909.090 $438,925.890
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $8,000.000 $0.100 $6,100.000 $2,000.000 $1,725.000 $8,117.050 $4,854.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 810.000 $6.000 $0.010 $7.500 $8.600 $8.000 $8.520 $2.590
BIODEG EROSN CONT LOGS (REMOVE)
LF 810.000 $2.000 $0.010 $1.500 $1.750 $1.000 $1.700 $1.290
CABLE BARRIER SYSTEM (TL-4)
LF 86,829.000 $13.250 $8.530 $13.000 $13.350 $12.000 $12.900 $15.590
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 8,549.000 $20.000 $11.830 $17.000 $15.000 $10.750 $16.930 $19.500
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 148.000 $2,500.000 $1,375.000 $2,500.000 $1,915.000 $3,870.000 $3,438.920 $3,165.730
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 604.000 $100.000 $0.010 $12.000 $40.000 $50.000 $2.270 $5.220
TMA (STATIONARY)
DAY 292.000 $155.000 $0.010 $66.000 $180.000 $250.000 $2.270 $97.090
Totals: $5,033,299.750 $4,084,306.030 $4,157,273.000 $4,359,426.400 $4,714,452.230 $4,748,524.920 $4,971,782.500