TITUS FM 899 (1176-02-019)
Items: 66
County: TITUS
Length: N/A
Highway: FM 899
District: ATLANTA
Control Number: 1176-02-019
DBE Goal: N/A
Project: BR 2019(691)
Guaranty: N/A
Time: 115 WORKING DAYS
Engineer's Estimate: $1,260,463.65
Date: 03/05/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,260,463.65 | |||
| $1,121,133.28 |
-11.05%
-$139,330.37
|
|||
| $1,235,811.88 |
-1.96%
-$24,651.77
|
10.23%
$114,678.60
|
||
| $1,254,555.20 |
-0.47%
-$5,908.45
|
11.9%
$133,421.92
|
-1.52%
-$18,743.32
|
|
| $1,262,447.20 |
0.16%
$1,983.55
|
12.6%
$141,313.92
|
-0.63%
-$7,892.00
|
|
| $1,266,078.41 |
0.45%
$5,614.76
|
12.93%
$144,945.13
|
-0.29%
-$3,631.21
|
|
| $1,394,744.01 |
10.65%
$134,280.36
|
24.4%
$273,610.73
|
-10.16%
-$128,665.60
|
|
| $1,403,741.43 |
11.37%
$143,277.78
|
25.21%
$282,608.15
|
-0.65%
-$8,997.42
|
|
| $1,418,429.71 |
12.53%
$157,966.06
|
26.52%
$297,296.43
|
-1.05%
-$14,688.28
|
|
| $1,861,999.70 |
47.72%
$601,536.05
|
66.08%
$740,866.42
|
-31.27%
-$443,569.99
|
|
| $2,484,828.60 |
97.14%
$1,224,364.95
|
121.64%
$1,363,695.32
|
-33.45%
-$622,828.90
|
E
Engineer's Estimate
$1,260,463.65
1
Awarded
$1,121,133.28
Over/Under Est:
-11.05%
-$139,330.37
$1,235,811.88
Over/Under Est:
-1.96%
-$24,651.77
Amt Left:
10.23%
$114,678.60
$1,254,555.20
Over/Under Est:
-0.47%
-$5,908.45
Amt Left:
11.9%
$133,421.92
Delta:
-1.52%
-$18,743.32
$1,262,447.20
Over/Under Est:
0.16%
$1,983.55
Amt Left:
12.6%
$141,313.92
Delta:
-0.63%
-$7,892.00
$1,266,078.41
Over/Under Est:
0.45%
$5,614.76
Amt Left:
12.93%
$144,945.13
Delta:
-0.29%
-$3,631.21
$1,394,744.01
Over/Under Est:
10.65%
$134,280.36
Amt Left:
24.4%
$273,610.73
Delta:
-10.16%
-$128,665.60
$1,403,741.43
Over/Under Est:
11.37%
$143,277.78
Amt Left:
25.21%
$282,608.15
Delta:
-0.65%
-$8,997.42
$1,418,429.71
Over/Under Est:
12.53%
$157,966.06
Amt Left:
26.52%
$297,296.43
Delta:
-1.05%
-$14,688.28
$1,861,999.70
Over/Under Est:
47.72%
$601,536.05
Amt Left:
66.08%
$740,866.42
Delta:
-31.27%
-$443,569.99
$2,484,828.60
Over/Under Est:
97.14%
$1,224,364.95
Amt Left:
121.64%
$1,363,695.32
Delta:
-33.45%
-$622,828.90
Bid Items & Bid Tabulations
66
Total
0 of 66