TITUS IH 30 (0610-03-090)

Items: 21

County: TITUS
Length: N/A
Highway: IH 30
District: ATLANTA
Control Number: 0610-03-090
DBE Goal: N/A
Project: STP 2017(239)HES
Guaranty: N/A
Time: 236 WORKING DAYS
Engineer's Estimate: $1,832,095.26
Date: 11/04/2016 (9 years ago)
Contract Number: N/A
Type: SAFETY LIGHTING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,832,095.26
$1,841,758.65
Over/Under Est: 0.53% $9,663.39
$1,844,754.65
Over/Under Est: 0.69% $12,659.39
Amt Left: 0.16% $2,996.00
Over/Under Est: 1.55% $28,428.45
Amt Left: 1.02% $18,765.06
Delta: -0.85% -$15,769.06
$2,149,087.50
Over/Under Est: 17.3% $316,992.24
Amt Left: 16.69% $307,328.85
Delta: -15.51% -$288,563.79

Bid Items & Bid Tabulations

21 Total 0 of 21
TITUS  |  IH 30  |  ATLANTA  |  0610-03-090  |  11/04/2016  |  $1,832,095.26  |  STP 2017(239)HES  |  SAFETY LIGHTING  |  236 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SOUTH TEXAS ILLUMINATION, LLC
MICA CORPORATION
AMERICAN LIGHTING AND SIGNALIZATION, INC.
LUDCO, INC.
PREPARING ROW
AC 0.250 $5,236.000 $24,000.000 $12,100.000 $108,100.000 $20,000.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 375.000 $548.000 $561.800 $447.000 $772.560 $600.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 200.000 $165.000 $182.500 $168.000 $187.100 $200.000
RIPRAP (CONC)(CL B)
CY 48.000 $340.000 $333.900 $720.000 $621.030 $500.000
MOBILIZATION
LS 1.000 $135,710.760 $167,110.000 $141,400.000 $197,791.410 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $4,000.000 $8,869.000 $9,950.000 $3,717.230 $7,500.000
REMOVE RD IL ASM (TRANS-BASE)
EA 54.000 $570.000 $313.000 $305.000 $660.190 $700.000
REPLACE LUMINAIRE W/LED (250W EQ)
EA 16.000 $694.000 $1,211.650 $690.000 $601.880 $800.000
REPLACE LUMINAIRE W/LED (400W EQ)
EA 8.000 $880.000 $1,342.450 $840.000 $741.080 $1,100.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 20.000 $3,089.000 $3,339.200 $2,880.000 $3,069.020 $3,200.000
HI MST IL POLE (150 FT)( 80 MPH)
EA 15.000 $24,888.000 $21,683.600 $19,650.000 $21,141.860 $30,000.000
CONDT (PVC) (SCH 40) (2")
LF 24,360.000 $6.500 $5.250 $9.070 $5.610 $9.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 3,890.000 $20.000 $8.800 $22.300 $13.930 $25.000
ELEC CONDR (NO.6) BARE
LF 29,065.000 $1.300 $1.650 $1.330 $0.970 $1.500
ELEC CONDR (NO.6) INSULATED
LF 61,300.000 $1.500 $1.650 $1.420 $1.000 $2.000
GROUND BOX TY A (122311)
EA 15.000 $628.000 $713.400 $780.000 $651.330 $900.000
GROUND BOX TY A (122311)W/APRON
EA 56.000 $894.000 $779.400 $1,030.000 $789.690 $1,000.000
REMOVE ELECTRICAL SERVICES
EA 7.000 $300.000 $626.000 $305.000 $1,054.310 $1,500.000
ELC SRV TY A 240/480 060(NS)AL(E)SP(O)
EA 4.000 $5,600.000 $5,295.400 $6,895.000 $5,901.090 $5,000.000
ELC SRV TY A 240/480 060(SS)SS(E)SP(O)
EA 3.000 $5,291.000 $5,355.400 $7,325.000 $5,798.620 $5,500.000
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
EA 15.000 $28,700.000 $28,409.600 $24,950.000 $27,371.920 $30,000.000
Totals: $1,832,095.260 $1,841,758.650 $1,844,754.650 $1,860,523.710 $2,149,087.500