TITUS FM 71 (0546-01-040)
Items: 56
County: TITUS
Length: 0.3990 MILES
Highway: FM 71
District: ATLANTA
Control Number: 0546-01-040
DBE Goal: 0.0%
Project: BR 2026(072)
Guaranty: $24,000.00
Time: 132 WORKING DAYS
Engineer's Estimate: $1,390,645.70
Date: 10/09/2025 (8 months ago)
Contract Number: 10253230
Type: BRIDGE REPLACEMENT
Project ID: A00196394
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
WENDY STARKES
OSCAR FLORES
TITUS FM 71 (0546-01-040)
Project Name: N/A
Project: BR 2026(072)
Length: 0.3990 MILES
Project Type: CONSTRUCTION
Limits From: AT LACY CREEK
Limits To: .
Project Description: REPLACE BRIDGE AND APPROACHES
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,390,645.70 | |||
| $1,331,902.88 |
-4.22%
-$58,742.82
|
|||
| $1,411,903.00 |
1.53%
$21,257.30
|
6.01%
$80,000.12
|
||
| $1,456,226.84 |
4.72%
$65,581.14
|
9.33%
$124,323.96
|
-3.14%
-$44,323.84
|
|
| $1,456,287.90 |
4.72%
$65,642.20
|
9.34%
$124,385.02
|
0.00%
-$61.06
|
|
| $1,503,897.15 |
8.14%
$113,251.45
|
12.91%
$171,994.27
|
-3.27%
-$47,609.25
|
|
| $1,515,331.60 |
8.97%
$124,685.90
|
13.77%
$183,428.72
|
-0.76%
-$11,434.45
|
|
| $1,571,257.50 |
12.99%
$180,611.80
|
17.97%
$239,354.62
|
-3.69%
-$55,925.90
|
E
Engineer's Estimate
$1,390,645.70
1
Awarded
$1,331,902.88
Over/Under Est:
-4.22%
-$58,742.82
$1,411,903.00
Over/Under Est:
1.53%
$21,257.30
Amt Left:
6.01%
$80,000.12
$1,456,226.84
Over/Under Est:
4.72%
$65,581.14
Amt Left:
9.33%
$124,323.96
Delta:
-3.14%
-$44,323.84
$1,456,287.90
Over/Under Est:
4.72%
$65,642.20
Amt Left:
9.34%
$124,385.02
Delta:
0.00%
-$61.06
$1,503,897.15
Over/Under Est:
8.14%
$113,251.45
Amt Left:
12.91%
$171,994.27
Delta:
-3.27%
-$47,609.25
$1,515,331.60
Over/Under Est:
8.97%
$124,685.90
Amt Left:
13.77%
$183,428.72
Delta:
-0.76%
-$11,434.45
$1,571,257.50
Over/Under Est:
12.99%
$180,611.80
Amt Left:
17.97%
$239,354.62
Delta:
-3.69%
-$55,925.90
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRUE ROADS CONSTRUCTION LLC | 10.64% | $141,674.30 |
| R & G CONSTRUCTION, LLC | 3.76% | $50,065.36 |
| DUSTIN ALLEN, INC. | 2.16% | $28,760.95 |
| J. H. ODEN CONTRACTING COMPANY | 2.01% | $26,763.66 |
| STRIPING TECHNOLOGY, L.P. | 0.96% | $12,782.64 |
| DIAMOND ELITE BARRICADES, LLC | 0.58% | $7,722.85 |
| Total: | 20.11% | $267,769.76 |
Bid Items & Bid Tabulations
56
Total
0 of 56
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $18,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $28,000.00 |