TITUS SH 49 (0222-01-063)

Items: 93

County: TITUS
Length: 1.0000 MILES
Highway: SH 49
District: ATLANTA
Control Number: 0222-01-063
DBE Goal: 0.0%
Project: C 222-1-63
Guaranty: $19,000.00
Time: 105 WORKING DAYS
Engineer's Estimate: $984,816.84
Date: 10/08/2025 (8 months ago)
Contract Number: 10253027
Type: INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT T
Project ID: A00196501
Project Description: INSTALL TURN LANE AND IMPROVE TRAFFIC SIGNAL
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
WENDY STARKES
OSCAR FLORES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$984,816.84
$1,096,364.98
Over/Under Est: 11.33% $111,548.14
Over/Under Est: 13.54% $133,340.71
Amt Left: 1.99% $21,792.57
Over/Under Est: 15.59% $153,503.55
Amt Left: 3.83% $41,955.41
Delta: -1.80% -$20,162.84
Over/Under Est: 16.84% $165,813.15
Amt Left: 4.95% $54,265.01
Delta: -1.08% -$12,309.60
Over/Under Est: 24.83% $244,530.38
Amt Left: 12.13% $132,982.24
Delta: -6.84% -$78,717.23

Bid Items & Bid Tabulations

93 Total 0 of 93
TITUS  |  SH 49  |  ATLANTA  |  0222-01-063  |  10/08/2025  |  $984,816.84  |  C 222-1-63  |  INTERS IMPRVS WITH RIGHT AND/OR LEFT...  |  105 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. V. CAVER, INC.
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
TRUE ROADS CONSTRUCTION, LLC
L. S. EQUIPMENT CO., INC.
PREPARING ROW
STA 25.260 $2,000.000 $2,000.000 $3,500.000 $4,500.000 $720.000 $5,000.000
REMOV CONC (CURB & GUTTER)
LF 188.000 $11.000 $15.000 $20.000 $25.000 $23.500 $10.000
SUBGR WIDEN (DC)
STA 6.900 $774.000 $4,000.000 $800.000 $1,500.000 $840.000 $800.000
EMBANK (VEH)(DC)(TY A)
CY 526.000 $91.000 $50.000 $30.000 $33.000 $32.000 $65.000
BACKFILL (TY C)
STA 26.020 $240.000 $350.000 $600.000 $350.000 $525.000 $100.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 3,327.000 $0.750 $0.660 $0.700 $0.720 $0.720 $0.700
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 1,665.000 $0.750 $0.570 $0.650 $0.620 $0.720 $0.700
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 1,665.000 $0.750 $0.630 $0.650 $0.700 $0.720 $0.700
VEGETATIVE WATERING
TGL 53.000 $4.000 $0.010 $20.000 $15.000 $55.000 $0.010
FL BS (CMP IN PLC)(TY A GR 4) (10")
SY 1,189.000 $20.000 $48.760 $33.000 $30.000 $48.000 $75.000
PRIME COAT (MC-30)
GAL 297.000 $6.000 $20.000 $8.000 $8.000 $12.000 $12.000
ASPH (AC-20-5TR)
GAL 430.000 $5.000 $20.000 $18.000 $6.250 $10.000 $10.000
AGGR (TY-PB, GR-4)(SAC-A)
CY 10.000 $168.000 $243.690 $500.000 $450.000 $875.000 $320.000
SP MIXES SP-C SAC-A PG70-22
TON 656.000 $175.000 $271.580 $175.000 $225.000 $190.000 $225.000
TACK COAT
GAL 501.000 $3.190 $6.500 $7.000 $6.000 $9.000 $7.500
PLANE ASPH CONC PAV(0" TO 2")
SY 3,019.000 $2.000 $4.000 $6.500 $4.500 $5.000 $5.000
CUT & RESTORE ASPH PAVING
SY 42.000 $145.000 $300.000 $125.000 $325.000 $100.000 $300.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 80.000 $286.000 $265.000 $300.000 $295.000 $340.000 $285.000
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 11.000 $309.000 $292.500 $330.000 $325.000 $375.000 $310.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 13.000 $392.000 $351.000 $400.000 $390.000 $450.000 $381.000
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 44.000 $1,064.000 $1,375.000 $1,550.000 $1,520.000 $1,750.000 $1,525.000
RIPRAP (CONC)(CL B)
CY 3.000 $570.000 $600.000 $700.000 $700.000 $1,360.000 $662.500
RC PIPE (CL III)(18 IN)
LF 98.000 $54.000 $63.350 $65.000 $65.000 $78.000 $98.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 6.000 $770.000 $940.000 $1,000.000 $1,150.000 $1,800.000 $2,200.000
REMOV STR (PIPE)
LF 60.000 $18.000 $25.000 $25.000 $15.000 $44.000 $100.000
MOBILIZATION
LS 1.000 $90,000.000 $112,000.000 $100,000.000 $115,000.000 $75,000.000 $92,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $5,000.000 $5,000.000 $10,000.000 $5,500.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $13,000.000 $7,000.000 $15,000.000 $1,800.000 $20,000.000 $5,000.000
TMA (STATIONARY)
DAY 60.000 $99.000 $250.000 $300.000 $275.000 $150.000 $300.000
TMA (MOBILE OPERATION)
DAY 30.000 $99.000 $275.000 $300.000 $395.000 $150.000 $300.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $40.000 $60.000 $45.000 $65.000 $48.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $11.000 $18.000 $13.000 $20.000 $14.000 $17.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $4.000 $13.000 $6.000 $15.000 $6.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $1.000 $1.000 $1.000 $2.000 $1.200 $1.500
REMOVE RD IL ASM (TRANS-BASE)
EA 2.000 $750.000 $855.000 $950.000 $950.000 $1,100.000 $975.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 8.000 $7,250.000 $5,895.000 $6,500.000 $6,500.000 $7,500.000 $6,250.000
CONDT (PVC) (SCH 40) (2")
LF 2,101.000 $11.000 $8.100 $9.000 $9.000 $10.000 $9.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 292.000 $27.000 $18.250 $20.000 $20.000 $23.000 $25.500
CONDT (PVC) (SCH 40) (4")
LF 169.000 $13.000 $23.500 $26.000 $26.000 $30.000 $25.750
CONDT (PVC) (SCH 40) (4") (BORE)
LF 447.000 $34.000 $27.250 $30.000 $30.000 $35.000 $29.670
ELEC CONDR (NO.12) INSULATED
LF 160.000 $2.000 $2.350 $2.600 $2.600 $3.000 $2.950
ELEC CONDR (NO.8) INSULATED
LF 4,892.000 $3.000 $2.350 $2.600 $2.600 $3.000 $2.950
ELEC CONDR (NO.6) BARE
LF 3,256.000 $3.000 $2.350 $2.600 $2.600 $3.000 $2.950
ELEC CONDR (NO.6) INSULATED
LF 5,016.000 $3.000 $2.850 $3.200 $3.200 $3.650 $3.100
ELEC CONDR (NO.2) INSULATED
LF 39.000 $5.000 $6.000 $6.600 $6.600 $7.500 $6.450
GROUND BOX TY A (122311)W/APRON
EA 10.000 $1,154.000 $1,200.000 $1,350.000 $1,350.000 $1,500.000 $1,400.000
GROUND BOX TY D (162922)
EA 2.000 $1,857.000 $1,100.000 $1,250.000 $1,250.000 $1,400.000 $1,400.000
GROUND BOX TY D (162922)W/APRON
EA 6.000 $2,677.000 $1,525.000 $1,700.000 $1,675.000 $1,955.000 $1,650.000
REMOVE GROUND BOX
EA 4.000 $441.000 $485.000 $535.000 $535.000 $620.000 $495.000
ELC SRV TY D 120/240 100(NS)AL(E)PS(U)
EA 1.000 $9,524.000 $8,950.000 $10,000.000 $10,000.000 $11,500.000 $9,100.000
ALUMINUM SIGNS (TY G)
SF 72.000 $16.000 $65.500 $75.000 $72.000 $84.000 $72.250
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 3.000 $473.000 $981.270 $1,425.000 $1,415.000 $1,000.000 $1,300.000
REMOVE SM RD SN SUP&AM
EA 5.000 $105.000 $200.000 $150.000 $150.000 $120.000 $250.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 12.000 $0.600 $5.000 $3.000 $2.500 $5.000 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 138.000 $0.600 $3.000 $3.000 $2.500 $5.000 $1.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 125.000 $1.500 $2.500 $2.750 $2.750 $3.000 $3.000
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 3,509.000 $1.000 $1.250 $1.400 $1.400 $1.500 $1.750
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 2,760.000 $1.000 $1.250 $1.400 $1.400 $1.500 $1.750
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 276.000 $3.500 $10.000 $11.000 $11.000 $12.000 $15.000
PREFAB PM TY C (W)(24")(SLD)
LF 170.000 $3.000 $15.000 $16.500 $16.500 $18.000 $250.000
PREFAB PM TY C (W)(ARROW)
EA 6.000 $213.000 $225.000 $250.000 $250.000 $270.000 $275.000
PREFAB PM TY C (W)(WORD)
EA 6.000 $264.000 $265.000 $295.000 $295.000 $320.000 $12.000
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 258.000 $3.500 $10.000 $11.000 $11.000 $12.000 $10.000
REFL PAV MRKR TY I-C
EA 7.000 $5.000 $8.000 $8.800 $9.000 $10.000 $10.000
REFL PAV MRKR TY II-A-A
EA 138.000 $4.000 $6.000 $6.600 $7.000 $8.000 $7.000
ELIM EXT PM & MRKS (24")
LF 146.000 $4.000 $5.000 $5.500 $5.500 $6.000 $6.000
PAV SURF PREP FOR MRK (6")
LF 4,140.000 $0.100 $0.500 $0.550 $0.600 $0.600 $1.000
PAV SURF PREP FOR MRK (24")
LF 170.000 $3.000 $3.500 $3.850 $4.000 $4.200 $3.750
PAV SURF PREP FOR MRK (ARROW)
EA 6.000 $65.000 $100.000 $110.000 $110.000 $120.000 $125.000
PAV SURF PREP FOR MRK (WORD)
EA 6.000 $65.000 $100.000 $110.000 $110.000 $120.000 $125.000
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $13,774.000 $11,950.000 $13,500.000 $13,200.000 $15,000.000 $15,000.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $2,500.000 $6,300.000 $7,000.000 $7,000.000 $8,000.000 $7,000.000
VEH SIG SEC (12")LED(GRN)
EA 8.000 $359.000 $305.000 $335.000 $335.000 $390.000 $335.000
VEH SIG SEC (12")LED(GRN ARW)
EA 4.000 $353.000 $315.000 $350.000 $350.000 $400.000 $345.000
VEH SIG SEC (12")LED(YEL)
EA 12.000 $364.000 $305.000 $335.000 $336.000 $390.000 $335.000
VEH SIG SEC (12")LED(YEL ARW)
EA 8.000 $359.000 $315.000 $350.000 $350.000 $400.000 $345.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $418.000 $305.000 $335.000 $336.000 $390.000 $335.000
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $349.000 $315.000 $350.000 $350.000 $400.000 $345.000
BACK PLATE (12")(1 SEC)
EA 4.000 $150.000 $156.000 $175.000 $175.000 $200.000 $165.000
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 8.000 $239.000 $221.000 $250.000 $250.000 $285.000 $241.000
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
EA 4.000 $232.000 $256.750 $285.000 $285.000 $330.000 $265.000
TRF SIG CBL (TY A)(12 AWG)(3 CONDR)
LF 70.000 $3.000 $2.600 $2.900 $3.000 $3.350 $2.800
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 1,311.000 $4.000 $3.000 $3.300 $3.300 $3.850 $3.150
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 1,156.000 $4.000 $3.500 $3.850 $4.000 $4.500 $3.650
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 2.000 $2,500.000 $6,534.000 $7,000.000 $7,000.000 $8,150.000 $6,800.000
INS TRF SIG PL AM(S)1 ARM(32')
EA 1.000 $16,216.000 $12,500.000 $14,000.000 $14,000.000 $16,000.000 $15,000.000
INS TRF SIG PL AM(S)1 ARM(36')
EA 1.000 $13,938.000 $13,500.000 $15,000.000 $15,000.000 $17,300.000 $16,500.000
INS TRF SIG PL AM(S)1 ARM(60')LUM
EA 2.000 $46,000.000 $38,650.000 $42,500.000 $43,000.000 $50,000.000 $41,000.000
PED POLE ASSEMBLY
EA 2.000 $2,413.000 $3,800.000 $4,200.000 $4,200.000 $4,800.000 $4,100.000
REMOVAL OF SIGNAL POLE ASSM
EA 2.000 $900.000 $1,900.000 $2,100.000 $2,100.000 $2,400.000 $2,100.000
VIVDS CAM ASSY (INSTALL ONLY)
EA 4.000 $985.000 $1,000.000 $1,100.000 $1,100.000 $1,200.000 $1,100.000
VIVDS CABLE (CAT 6)
LF 1,126.000 $6.000 $3.500 $3.850 $3.850 $4.500 $3.750
BBU SYSTEM (EXTERNAL BATTERY CABINET)
EA 1.000 $9,500.000 $8,450.000 $9,500.000 $9,300.000 $10,000.000 $9,000.000
Totals: $984,816.840 $1,096,364.980 $1,118,157.550 $1,138,320.390 $1,150,629.990 $1,229,347.220
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $11,000.00
STATE FORCE ACCOUNT WORK (NON-PART) $38,250.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,500.00
Total: $54,750.00