Show Job Controls
Bid Cobra

TITUS US 67 (0010-06-042)

Items: 21

County: TITUS
Length: N/A
Highway: US 67
District: ATLANTA
Control Number: 0010-06-042
DBE Goal: N/A
Project: STP 2019(634)HES
Guaranty: N/A
Time: 240 WORKING DAYS
Engineer's Estimate: $3,219,831.20
Date: 03/05/2019 (7 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$3,219,831.20
$2,498,030.22
Over/Under Est: -22.42% -$721,800.98
$2,526,922.30
Over/Under Est: -21.52% -$692,908.90
Amt Left: 1.16% $28,892.08
$2,531,620.69
Over/Under Est: -21.37% -$688,210.51
Amt Left: 1.34% $33,590.47
Delta: -0.19% -$4,698.39
Over/Under Est: -19.93% -$641,677.70
Amt Left: 3.21% $80,123.28
Delta: -1.84% -$46,532.81
Over/Under Est: -16.64% -$535,665.30
Amt Left: 7.45% $186,135.68
Delta: -4.11% -$106,012.40
Over/Under Est: -13.99% -$450,305.00
Amt Left: 10.87% $271,495.98
Delta: -3.18% -$85,360.30
$2,894,716.50
Over/Under Est: -10.1% -$325,114.70
Amt Left: 15.88% $396,686.28
Delta: -4.52% -$125,190.30
Over/Under Est: -6.75% -$217,408.02
Amt Left: 20.19% $504,392.96
Delta: -3.72% -$107,706.68
Over/Under Est: -3.97% -$127,978.70
Amt Left: 23.77% $593,822.28
Delta: -2.98% -$89,429.32
$3,302,472.40
Over/Under Est: 2.57% $82,641.20
Amt Left: 32.2% $804,442.18
Delta: -6.81% -$210,619.90

Bid Items & Bid Tabulations

21 Total 0 of 21
TITUS  |  US 67  |  ATLANTA  |  0010-06-042  |  03/05/2019  |  $3,219,831.20  |  STP 2019(634)HES  |  SAFETY TREAT FIXED OBJECTS  |  240 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONGVIEW BRIDGE AND ROAD, LTD.
CDM HOLDINGS, LLC
H. V. CAVER, INC.
STATELINE CONSTRUCTION, LLC
RAYFORD'S TRUCK & TRACTOR
EAST TEXAS BRIDGE, INC.
PIERCE R & B LLC
HIGHWAY 19 CONSTRUCTION LLC
TALBRAN ENTERPRISES LLC
KWEST GROUP LLC
PREPARING ROW
STA 146.020 $3,000.000 $2,000.000 $800.000 $1,500.000 $1,200.000 $1,000.000 $2,500.000 $700.000 $1,000.000 $600.000 $1,240.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 1,804.000 $30.000 $20.000 $12.000 $22.000 $20.000 $30.000 $20.000 $30.000 $30.000 $40.000 $45.000
BLADING
STA 457.300 $100.000 $225.000 $100.000 $75.000 $75.000 $150.000 $300.000 $225.000 $500.000 $250.000 $229.500
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 111,422.000 $0.350 $0.210 $0.100 $0.190 $0.250 $0.050 $0.250 $0.500 $0.190 $0.500 $0.700
VEGETATIVE WATERING
MG 1,768.100 $35.000 $1.000 $1.000 $5.000 $5.000 $8.000 $7.000 $10.000 $30.000 $45.000 $8.500
CUT & RESTORE CONC PAVING
SY 301.000 $180.000 $135.000 $140.000 $169.500 $135.000 $150.000 $80.000 $175.000 $125.000 $165.000 $215.000
CUT & RESTORE ASPH PAVING
SY 1,328.000 $120.000 $70.000 $99.000 $108.500 $85.000 $50.000 $55.000 $95.000 $150.000 $150.000 $120.000
CUT AND RESTORE PAV (FLEX BASE)
SY 3,932.000 $50.000 $30.000 $53.000 $45.500 $37.500 $25.000 $30.000 $50.000 $45.000 $80.000 $91.000
RIPRAP (CONC)(4 IN)
CY 120.000 $350.000 $765.000 $380.000 $275.000 $450.000 $400.000 $400.000 $550.000 $500.000 $400.000 $600.000
RC PIPE (CL III)(18 IN)
LF 9,958.000 $45.000 $33.500 $44.000 $32.720 $38.000 $40.000 $38.000 $40.000 $35.000 $40.000 $45.500
RC PIPE (CL III)(24 IN)
LF 1,516.000 $50.000 $48.000 $54.000 $49.180 $70.000 $75.000 $50.000 $58.000 $45.000 $68.000 $68.000
RC PIPE (CL III)(36 IN)
LF 99.000 $100.000 $80.000 $105.000 $112.130 $128.000 $200.000 $90.000 $125.000 $85.000 $125.000 $150.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1,536.000 $550.000 $500.000 $500.000 $540.000 $525.000 $675.000 $570.000 $575.000 $525.000 $600.000 $488.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 202.000 $850.000 $800.000 $825.000 $885.000 $930.000 $850.000 $935.000 $1,000.000 $875.000 $1,050.000 $812.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 4.000 $2,640.000 $3,250.000 $3,350.000 $3,875.000 $3,673.000 $12,000.000 $4,000.000 $5,500.000 $3,500.000 $4,700.000 $3,196.000
REMOV STR (HEADWALL)
EA 37.000 $1,000.000 $275.000 $600.000 $825.000 $635.000 $750.000 $400.000 $750.000 $250.000 $800.000 $657.000
REMOV STR (PIPE)
LF 9,359.000 $20.000 $10.000 $11.000 $12.500 $7.000 $5.000 $10.000 $10.000 $10.000 $8.000 $26.000
MOBILIZATION
LS 1.000 $291,000.000 $200,000.000 $200,000.000 $179,000.000 $250,000.000 $240,000.000 $200,000.000 $285,000.000 $400,000.000 $250,000.000 $225,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $2,500.000 $2,000.000 $5,000.000 $2,200.000 $3,000.000 $1,500.000 $4,000.000 $6,000.000 $5,000.000 $2,000.000 $8,198.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 1.000 $350.000 $350.000 $600.000 $375.000 $735.000 $500.000 $1,000.000 $1,000.000 $500.000 $300.000 $350.000
TMA (STATIONARY)
EA 1.000 $15,000.000 $7,500.000 $23,000.000 $6,500.000 $50,000.000 $12,000.000 $15,000.000 $17,500.000 $25,000.000 $20,000.000 $75,000.000
Totals: $3,219,831.200 $2,498,030.220 $2,526,922.300 $2,531,620.690 $2,578,153.500 $2,684,165.900 $2,769,526.200 $2,894,716.500 $3,002,423.180 $3,091,852.500 $3,302,472.400