THROCKMORTON FM 923 (0982-05-011)
Items: 36
County: THROCKMORTON
Length: 0.0000 MILES
Highway: FM 923
District: WICHITA FALLS
Control Number: 0982-05-011
DBE Goal: 2.0%
Project: BR 2025(836)
Guaranty: $14,000.00
Time: 102 WORKING DAYS
Engineer's Estimate: $707,816.50
Date: 07/02/2025 (11 months ago)
Contract Number: 7253233
Type: BRIDGE REPLACEMENT
Project ID: A00183414
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ZACHARY HUSEN
CHRISTIAN SIERRA
THROCKMORTON FM 923 (0982-05-011)
Project Name: N/A
Project: BR 2025(836)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT BUSH KNOB CREEK
Limits To: .
Project Description: REPLACE BRIDGE AND APPROACHES
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$707,816.50 | |||
| $728,607.05 |
2.94%
$20,790.55
|
|||
| $737,257.57 |
4.16%
$29,441.07
|
1.19%
$8,650.52
|
||
| $747,184.10 |
5.56%
$39,367.60
|
2.55%
$18,577.05
|
-1.35%
-$9,926.53
|
|
| $751,775.10 |
6.21%
$43,958.60
|
3.18%
$23,168.05
|
-0.61%
-$4,591.00
|
|
| $756,248.00 |
6.84%
$48,431.50
|
3.79%
$27,640.95
|
-0.59%
-$4,472.90
|
|
| $873,923.13 |
23.47%
$166,106.63
|
19.94%
$145,316.08
|
-15.56%
-$117,675.13
|
|
| $887,640.05 |
25.41%
$179,823.55
|
21.83%
$159,033.00
|
-1.57%
-$13,716.92
|
|
| $1,040,958.00 |
47.07%
$333,141.50
|
42.87%
$312,350.95
|
-17.27%
-$153,317.95
|
E
Engineer's Estimate
$707,816.50
1
Awarded
$728,607.05
Over/Under Est:
2.94%
$20,790.55
$737,257.57
Over/Under Est:
4.16%
$29,441.07
Amt Left:
1.19%
$8,650.52
$747,184.10
Over/Under Est:
5.56%
$39,367.60
Amt Left:
2.55%
$18,577.05
Delta:
-1.35%
-$9,926.53
$751,775.10
Over/Under Est:
6.21%
$43,958.60
Amt Left:
3.18%
$23,168.05
Delta:
-0.61%
-$4,591.00
$756,248.00
Over/Under Est:
6.84%
$48,431.50
Amt Left:
3.79%
$27,640.95
Delta:
-0.59%
-$4,472.90
$873,923.13
Over/Under Est:
23.47%
$166,106.63
Amt Left:
19.94%
$145,316.08
Delta:
-15.56%
-$117,675.13
$887,640.05
Over/Under Est:
25.41%
$179,823.55
Amt Left:
21.83%
$159,033.00
Delta:
-1.57%
-$13,716.92
$1,040,958.00
Over/Under Est:
47.07%
$333,141.50
Amt Left:
42.87%
$312,350.95
Delta:
-17.27%
-$153,317.95
| Subcontractor | Percentage | Amount |
|---|---|---|
| HODGES AND SON CONSTRUCTION COMPANY, INC. | 7.17% | $52,241.13 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 4.31% | $31,402.96 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 1.09% | $7,941.82 |
| FC TRAFFIC CONTROL, INC. | 0.92% | $6,703.18 |
| TORO BRAVO CONSTRUCTION, LLC | 0.37% | $2,695.85 |
| Total: | 13.86% | $100,984.94 |
Bid Items & Bid Tabulations
36
Total
0 of 36
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| Total: | $4,000.00 |