Show Job Controls
Bid Cobra

THROCKMORTON SH 79 (0284-02-027)

Items: 60

County: THROCKMORTON
Length: N/A
Highway: SH 79
District: WICHITA FALLS
Control Number: 0284-02-027
DBE Goal: 0.0%
Project: C 284-2-27
Guaranty: N/A
Time: 178 WORKING DAYS
Engineer's Estimate: $6,978,676.15
Date: 01/04/2024 (2 years ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD SHOULDERS
Mail/Deliver Bids To: N/A
ZACHARY HUSEN
ANTHONY BOUCHER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$6,978,676.15
$7,882,206.69
Over/Under Est: 12.95% $903,530.54
$8,012,951.19
Over/Under Est: 14.82% $1,034,275.04
Amt Left: 1.66% $130,744.50
$9,036,989.11
Over/Under Est: 29.49% $2,058,312.96
Amt Left: 14.65% $1,154,782.42
Delta: -12.78% -$1,024,037.92
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 2.10% $165,878.17
HJC FARMS, INC. 1.33% $105,056.17
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.75% $59,242.20
FLAT LINE, INC. 0.74% $58,452.31
MARCOMS CONSTRUCTION LLC 0.41% $32,385.74
FC TRAFFIC CONTROL, INC. 0.23% $18,167.61
PROFESSIONAL TRAFFIC CONTROL LLC 0.17% $13,428.23
MOBILE ENTERPRISES, INC. 0.11% $8,688.86
Total: 5.84% $461,299.29

Bid Items & Bid Tabulations

60 Total 0 of 60
THROCKMORTON  |  SH 79  |  WICHITA FALLS  |  0284-02-027  |  01/04/2024  |  $6,978,676.15  |  C 284-2-27  |  WIDEN ROAD - ADD SHOULDERS  |  178 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
DUININCK, INC.
ZACK BURKETT CO.
EXCAVATION (ROADWAY)
CY 6,392.000 $20.000 $30.000 $26.000 $28.700
EXCAVATION (CHANNEL)
CY 36.000 $50.000 $100.000 $54.500 $250.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 6,491.000 $38.000 $65.000 $51.000 $62.700
BACKFILL (TY A OR B)
STA 10.000 $445.000 $550.000 $485.000 $750.000
BROADCAST SEED (TEMP) (WARM)
SY 57,501.000 $0.120 $0.120 $0.130 $0.140
BROADCAST SEED (TEMP) (COOL)
SY 57,501.000 $0.120 $0.120 $0.140 $0.150
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 115,000.000 $0.140 $0.110 $0.120 $0.130
VEGETATIVE WATERING
MG 924.000 $30.000 $20.000 $27.000 $35.000
CEMENT
TON 831.000 $277.500 $290.000 $315.000 $354.000
CEMENT TREAT (SUBGRADE)(6")
SY 76,467.000 $5.000 $3.400 $5.400 $9.860
PRIME COAT (MC-30)
GAL 18,080.000 $5.000 $6.000 $5.150 $6.600
EMULS ASPH (EROSN CONT)(SS-1)
GAL 23,000.000 $4.500 $4.500 $4.050 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 5,000.000 $80.000 $75.000 $83.000 $80.000
PLANE ASPH CONC PAV(0" TO 2")
SY 3,361.000 $5.000 $7.000 $8.850 $7.500
PLANE ASPH CONC PAV(0" TO 8")
SY 1,493.000 $8.000 $10.000 $13.500 $12.000
RIPRAP (MOW STRIP)(4 IN)
CY 64.000 $700.000 $800.000 $925.000 $1,053.000
CLEANING AND SEALING JOINTS (CL 3)
LF 200.000 $54.000 $76.000 $48.000 $120.500
RETROFIT RAIL (TY T631)
LF 212.000 $120.000 $152.000 $160.000 $169.650
CMP (GAL STL 18 IN)
LF 552.000 $100.000 $94.000 $110.000 $87.750
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 32.000 $1,700.000 $1,250.000 $1,600.000 $1,872.000
CLEAN EXIST CULVERTS
EA 6.000 $2,500.000 $1,650.000 $2,700.000 $5,000.000
REMOV STR (SET)
EA 4.000 $1,000.000 $650.000 $1,100.000 $351.000
REMOV STR (PIPE)
LF 552.000 $15.000 $30.000 $13.000 $15.250
MOBILIZATION
LS 1.000 $629,949.880 $590,000.000 $775,000.000 $705,335.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $4,500.000 $10,500.000 $28,500.000 $24,979.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,100.000 $3.500 $3.100 $3.250 $3.510
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,100.000 $1.250 $0.920 $0.980 $1.050
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 5,400.000 $4.750 $3.100 $3.250 $3.510
BIODEG EROSN CONT LOGS (REMOVE)
LF 5,400.000 $1.000 $0.820 $0.870 $1.000
DRIVEWAYS (ACP)
SY 957.000 $50.000 $69.000 $42.500 $94.150
DRIVEWAYS (BASE)
SY 2,526.000 $25.000 $25.000 $23.000 $40.000
RUMBLE STRIPS (SHOULDER)
LF 69,400.000 $0.150 $0.210 $0.100 $0.270
RUMBLE STRIPS (CENTERLINE)
LF 34,700.000 $0.300 $0.320 $0.140 $0.270
MTL W-BEAM GD FEN (TIM POST)
LF 462.500 $25.000 $29.000 $30.500 $32.760
SHORT RADIUS
LF 25.000 $55.330 $38.000 $38.500 $41.540
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,093.670 $1,400.000 $1,400.000 $1,521.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 100.000 $101.000 $75.000 $76.000 $81.900
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,200.000 $1,800.000 $1,800.000 $1,959.750
REMOVE METAL BEAM GUARD FENCE
LF 411.000 $5.000 $3.200 $3.250 $3.510
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $261.200 $320.000 $325.000 $351.000
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $3,100.000 $3,500.000 $3,600.000 $3,890.250
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $450.000 $290.000 $300.000 $409.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $500.000 $690.000 $705.000 $965.250
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $685.000 $750.000 $780.000 $1,140.750
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $785.000 $890.000 $925.000 $1,316.250
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 36.000 $350.000 $520.000 $535.000 $760.500
REMOVE SM RD SN SUP&AM
EA 49.000 $183.000 $110.000 $110.000 $117.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 27.000 $50.830 $39.000 $40.500 $43.290
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,726.000 $2.000 $1.900 $1.550 $1.200
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 71,112.000 $0.500 $0.550 $0.570 $0.810
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 7,790.000 $0.500 $0.550 $0.570 $0.810
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 23,439.000 $0.500 $0.550 $0.570 $0.810
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 84.000 $20.000 $21.000 $22.000 $23.400
REFL PAV MRKR TY II-A-A
EA 668.000 $4.000 $5.250 $5.450 $5.850
D-GR HMA TY-B PG64-22
TON 19,985.000 $100.000 $120.000 $109.200 $120.000
D-GR HMA TY-D SAC-B PG70-28
TON 17,447.000 $108.000 $125.000 $120.000 $130.000
D-GR HMA TY-D PG70-28 (LEVEL-UP)
TON 250.000 $135.000 $210.000 $210.000 $178.500
BONDING COURSE
GAL 18,380.000 $4.000 $4.500 $1.000 $5.500
TMA (STATIONARY)
DAY 330.000 $204.000 $260.000 $325.000 $367.000
TMA (MOBILE OPERATION)
DAY 20.000 $850.000 $260.000 $1,200.000 $1.000
Totals: $6,978,676.150 $7,882,206.690 $8,012,951.190 $9,036,989.110