TAYLOR IH0020 (6478-99-001)

Items: 15

County: TAYLOR
Length: 0.0100 MILES
Highway: IH0020
District: ABILENE
Control Number: 6478-99-001
DBE Goal: N/A
Project: BPM - A00213687
Guaranty: $19,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $956,650.00
Date: 04/01/2025 (1 year ago)
Contract Number: 3250802
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00213687
Project Description: CONCRETE REPAIR ON BRIDGES, BRIDGE CLASS CULVERTS, AND OTHER CONCRETE STRUCTURES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
4250 N CLACK, ABILENE, TX 79601
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (12)
E
Engineer's Estimate
$956,650.00
$643,004.00
Over/Under Est: -32.79% -$313,646.00
$716,500.00
Over/Under Est: -25.1% -$240,150.00
Amt Left: 11.43% $73,496.00
Over/Under Est: -22.21% -$212,480.00
Amt Left: 15.73% $101,166.00
Delta: -3.86% -$27,670.00
Over/Under Est: -20.21% -$193,330.00
Amt Left: 18.71% $120,316.00
Delta: -2.57% -$19,150.00
Over/Under Est: -20.03% -$191,626.00
Amt Left: 18.98% $122,020.00
Delta: -0.22% -$1,704.00
Over/Under Est: -19.62% -$187,700.00
Amt Left: 19.59% $125,946.00
Delta: -0.51% -$3,926.00
Over/Under Est: -16.67% -$159,449.80
Amt Left: 23.98% $154,196.20
Delta: -3.67% -$28,250.20
Over/Under Est: -15.76% -$150,800.00
Amt Left: 25.33% $162,846.00
Delta: -1.09% -$8,649.80
Over/Under Est: -13.34% -$127,626.00
Amt Left: 28.93% $186,020.00
Delta: -2.88% -$23,174.00
Over/Under Est: -12.72% -$121,650.00
Amt Left: 29.86% $191,996.00
Delta: -0.72% -$5,976.00
$887,700.00
Over/Under Est: -7.21% -$68,950.00
Amt Left: 38.06% $244,696.00
Delta: -6.31% -$52,700.00
Over/Under Est: 35.69% $341,450.00
Amt Left: 101.88% $655,096.00
Delta: -46.23% -$410,400.00

Bid Items & Bid Tabulations

15 Total 0 of 15
TAYLOR  |  IH0020  |  ABILENE  |  6478-99-001  |  04/01/2025  |  $956,650.00  |  BPM - A00213687  |  BRIDGE PREVENT MAINT  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BLACKSMITH VENTURES LLC
ROAD DOCTORS LLC
PREMIER CONTRACTORS LLC
BK FIELD OPERATIONS LLC
PATHFIELD INVESTMENTS LLC
ICOS MANAGEMENT, LLC
SHALOM SERVICES CORPORATION
BECK-REIT & SONS, LTD.
STRUCTURAL INTEGRITY GROUP LLC
GARRET SHIELDS INFRASTRUCTURE
RHINO EQUITY, LLC
SCR CIVIL CONSTRUCTION, LLC
REMOV CONC (RIPRAP)
SY 30.000 $105.000 $50.000 $250.000 $70.000 $100.000 $65.000 $220.000 $75.000 $40.000 $215.000 $50.000 $40.000 $100.000
REMOV CONC (MISC)
CY 50.000 $230.000 $50.000 $250.000 $340.000 $175.000 $350.000 $110.000 $500.000 $60.000 $400.000 $200.000 $40.000 $300.000
FLOWABLE BACKFILL
CY 25.000 $400.000 $500.000 $500.000 $340.000 $400.000 $350.000 $550.000 $750.000 $300.000 $740.000 $500.000 $200.000 $500.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 300.000 $175.000 $100.000 $250.000 $190.000 $400.000 $200.000 $275.000 $200.000 $220.000 $185.000 $200.000 $280.000 $191.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 200.000 $250.000 $150.000 $250.000 $200.000 $450.000 $200.000 $330.000 $225.000 $355.000 $243.000 $300.000 $390.000 $390.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 2,400.000 $250.000 $150.000 $120.000 $200.000 $140.000 $200.000 $110.000 $125.000 $162.000 $200.000 $220.000 $190.000 $300.000
CONC STR REPAIR (STANDARD)
SF 300.000 $230.000 $200.000 $120.000 $150.000 $200.000 $200.000 $132.000 $150.000 $162.000 $225.000 $150.000 $220.000 $200.000
RIPRAP (CONC)(4 IN)
CY 30.000 $750.000 $500.000 $1,000.000 $700.000 $600.000 $800.000 $825.000 $750.000 $800.000 $1,450.000 $500.000 $900.000 $900.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 500.000 $55.000 $45.000 $80.000 $60.000 $58.000 $60.000 $55.000 $51.000 $55.000 $37.000 $50.000 $80.000 $45.000
JOINT SEALANT
LF 100.000 $50.000 $45.000 $80.000 $40.000 $60.000 $40.000 $55.000 $51.000 $55.000 $100.000 $50.000 $55.000 $108.000
MOBILIZATION (CALLOUT)
EA 4.000 $3,000.000 $1.000 $20,000.000 $500.000 $10,000.000 $1.000 $15,000.000 $20,000.000 $9,800.000 $1.000 $1,000.000 $15,000.000 $12,000.000
TMA (STATIONARY)
DAY 70.000 $300.000 $350.000 $100.000 $1.000 $1.000 $1.000 $275.000 $222.860 $100.000 $1.000 $400.000 $150.000 $400.000
PERM CONC TRF BARR REPAIR(SINGLE SLOPE)
LF 100.000 $250.000 $400.000 $300.000 $190.000 $100.000 $200.000 $770.000 $500.000 $333.000 $205.000 $100.000 $230.000 $830.000
PERM CONC TRF BARR REPL(SINGLE SLOPE)
LF 50.000 $700.000 $400.000 $500.000 $220.000 $100.000 $200.000 $880.000 $1,750.000 $888.000 $483.000 $120.000 $390.000 $1,800.000
CONCRETE RAIL REPAIR (MISC)
LF 50.000 $250.000 $400.000 $300.000 $150.000 $550.000 $175.000 $660.000 $300.000 $777.000 $315.000 $500.000 $200.000 $860.000
Totals: $956,650.000 $643,004.000 $716,500.000 $744,170.000 $763,320.000 $765,024.000 $768,950.000 $797,200.200 $805,850.000 $829,024.000 $835,000.000 $887,700.000 $1,298,100.000