Show Job Controls
Bid Cobra

TAYLOR SL 322 (2398-01-064)

Items: 69

County: TAYLOR
Length: 0.0000 MILES
Highway: SL 322
District: ABILENE
Control Number: 2398-01-064
DBE Goal: 0.0%
Project: F 2026(342)
Guaranty: $100,000.00
Time: 126 WORKING DAYS
Engineer's Estimate: $10,040,718.56
Date: 02/05/2026 (4 months ago)
Contract Number: 2263205
Type: PREVENTIVE MAINTENANCE
Project ID: A00206930
Contract Type: Federal
Project Description: OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$10,040,718.56
$8,968,076.23
Over/Under Est: -10.68% -$1,072,642.33
$9,274,102.25
Over/Under Est: -7.64% -$766,616.31
Amt Left: 3.41% $306,026.02
$10,097,096.46
Over/Under Est: 0.56% $56,377.90
Amt Left: 12.59% $1,129,020.23
Delta: -8.87% -$822,994.21
Over/Under Est: 0.66% $66,336.78
Amt Left: 12.7% $1,138,979.11
Delta: -0.10% -$9,958.88
$11,572,486.71
Over/Under Est: 15.26% $1,531,768.15
Amt Left: 29.04% $2,604,410.48
Delta: -14.50% -$1,465,431.37
$11,613,776.45
Over/Under Est: 15.67% $1,573,057.89
Amt Left: 29.5% $2,645,700.22
Delta: -0.36% -$41,289.74

Bid Items & Bid Tabulations

69 Total 0 of 69
TAYLOR  |  SL 322  |  ABILENE  |  2398-01-064  |  02/05/2026  |  $10,040,718.56  |  F 2026(342)  |  PREVENT MAINT  |  126 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
CK NEWBERRY, LLC
RK HALL, LLC
FOUTSCO PAVING COMPANY, LLC
A. L. HELMCAMP, INC.
REECE ALBERT, INC.
REMOV CONC (MOWSTRIP)
SY 107.000 $17.000 $45.000 $50.000 $44.940 $35.000 $65.000 $44.290
REMOV CONC (CURB & GUTTER)
LF 4,038.000 $10.000 $11.500 $10.000 $5.810 $20.000 $28.000 $11.070
EMBANK (FNL)(OC)(TY A)
CY 651.000 $80.000 $40.000 $25.000 $101.120 $55.000 $90.000 $105.910
BACKFILL (TY A)
STA 707.000 $225.000 $175.000 $150.000 $207.040 $150.000 $300.000 $271.160
SP MIXES SP-C SAC-B PG70-22
TON 50,151.000 $110.550 $108.510 $105.000 $118.880 $125.750 $145.000 $147.650
TACK COAT
GAL 37,868.000 $3.200 $4.000 $2.250 $4.640 $6.000 $4.500 $2.340
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 10,520.000 $40.660 $30.000 $37.000 $40.370 $36.000 $56.000 $46.780
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,645.000 $52.000 $44.000 $58.000 $55.790 $56.000 $94.000 $73.230
PLANE ASPH CONC PAV (0" TO 2-1/2")
SY 90,166.000 $3.000 $1.500 $2.250 $4.350 $1.000 $1.750 $4.820
RIPRAP (MOW STRIP)(4 IN)
CY 593.000 $584.000 $635.000 $625.000 $646.010 $560.000 $600.000 $636.640
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 275.000 $54.560 $51.500 $45.000 $54.600 $25.000 $45.000 $47.610
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 1,861.000 $45.000 $46.000 $30.000 $67.200 $40.000 $31.000 $32.110
RETROFIT RAIL (ADD HSS)
LF 4,253.000 $145.000 $115.000 $115.000 $109.200 $105.000 $110.000 $116.260
MOBILIZATION
LS 1.000 $827,319.020 $495,000.000 $900,000.000 $527,796.760 $625,000.000 $700,000.000 $432,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $30,000.000 $11,000.000 $20,000.000 $26,346.080 $60,000.000 $7,400.000 $12,600.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $7,000.000 $10,000.000 $14,830.770 $5,000.000 $15,000.000 $10,905.390
TMA (STATIONARY)
DAY 199.000 $236.000 $150.000 $25.000 $221.000 $1.000 $200.000 $288.320
TMA (MOBILE OPERATION)
DAY 30.000 $247.000 $300.000 $25.000 $307.000 $1.000 $150.000 $667.100
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 17,800.000 $5.470 $5.250 $5.000 $5.240 $0.500 $5.300 $4.980
BIODEG EROSN CONT LOGS (REMOVE)
LF 17,800.000 $1.340 $1.200 $1.000 $1.050 $0.250 $1.000 $1.110
INTERSECTIONS (ACP) (TY 1)
SY 698.000 $65.000 $37.000 $25.000 $45.780 $25.000 $50.000 $37.670
DRIVEWAYS (ACP) (TY 1)
SY 567.000 $35.000 $37.000 $30.000 $49.890 $40.000 $61.000 $41.910
DRIVEWAYS (BASE)
SY 234.000 $38.000 $25.000 $35.000 $40.880 $40.000 $50.000 $44.360
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 115,079.000 $0.200 $0.180 $0.150 $0.170 $0.150 $0.250 $0.180
MTL W-BEAM GD FEN (TIM POST)
LF 7,787.500 $26.000 $27.780 $26.000 $22.050 $26.000 $22.000 $27.960
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 26.000 $2,228.000 $2,640.000 $2,400.000 $1,601.250 $2,450.000 $1,900.000 $2,657.300
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 13.000 $1,167.000 $1,725.000 $1,600.000 $1,233.750 $1,450.000 $1,300.000 $1,732.780
MTL BM GD FEN TRANS (NON - SYM)
EA 12.000 $792.000 $1,285.000 $1,200.000 $840.000 $1,450.000 $850.000 $1,289.900
CONNECTOR PLATE FOR THRIE BEAM
EA 38.000 $471.000 $115.000 $100.000 $966.000 $785.000 $1,000.000 $110.720
REMOVE METAL BEAM GUARD FENCE
LF 8,425.000 $3.000 $2.200 $2.000 $2.100 $2.000 $2.200 $2.210
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 16.000 $270.000 $250.000 $250.000 $210.000 $100.000 $220.000 $249.120
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 26.000 $344.000 $250.000 $250.000 $893.830 $100.000 $500.000 $249.120
RM MTL BM GD FENCE TRANS (TL-2)
EA 14.000 $340.000 $250.000 $250.000 $210.000 $175.000 $220.000 $249.120
GUARDRAIL END TREATMENT (INSTALL)
EA 27.000 $3,100.000 $3,910.000 $3,500.000 $3,045.000 $3,450.000 $3,100.000 $3,930.590
GUARDRAIL END TREATMENT (REMOVE)
EA 28.000 $280.000 $250.000 $250.000 $210.000 $200.000 $220.000 $249.120
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $1,200.000 $1,100.000 $1,100.000 $1,027.950 $2,000.000 $1,000.000 $1,162.570
REMOVE SM RD SN SUP&AM
EA 1.000 $204.000 $250.000 $500.000 $115.500 $300.000 $120.000 $249.120
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BR)
EA 139.000 $30.000 $66.000 $60.000 $46.200 $25.000 $46.000 $66.430
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 159.000 $30.000 $66.000 $60.000 $46.200 $25.000 $46.000 $66.430
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BR)
EA 88.000 $30.000 $66.000 $60.000 $46.200 $25.000 $46.000 $66.430
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BR)
EA 54.000 $30.000 $66.000 $60.000 $46.200 $25.000 $46.000 $66.430
INST DEL ASSM (D-SW)SZ 1(WFLX)GNDLL(BR)
EA 399.000 $91.000 $54.000 $150.000 $50.400 $48.000 $78.000 $166.080
INST DEL ASSM (D-SY)SZ 1(YFLX)GNDLL(BR)
EA 268.000 $91.000 $54.000 $150.000 $50.400 $48.000 $78.000 $166.080
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 7,415.000 $1.300 $1.500 $1.000 $2.450 $0.100 $1.000 $1.870
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4.000 $15.000 $25.000 $1.000 $3.530 $5.000 $1.000 $1.850
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 204.000 $5.000 $2.200 $1.000 $0.630 $1.000 $1.050 $0.660
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 14,999.000 $1.000 $1.050 $0.750 $0.680 $0.780 $0.850 $0.720
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 2,292.000 $3.600 $4.680 $4.000 $4.310 $2.400 $2.500 $4.540
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 343.000 $7.500 $13.200 $8.000 $8.610 $6.750 $7.100 $9.080
RE PM TY II (W) 6" (BRK)
LF 17,690.000 $0.230 $0.180 $0.150 $0.160 $0.140 $0.180 $0.170
RE PM TY II (W) 6" (DOT)
LF 204.000 $5.000 $1.100 $0.150 $0.160 $0.250 $0.260 $0.170
RE PM TY II (W) 6" (SLD)
LF 91,361.000 $0.200 $0.180 $0.150 $0.160 $0.130 $0.180 $0.170
RE PM TY II (W) 8" (SLD)
LF 14,999.000 $0.480 $0.500 $0.200 $0.200 $0.170 $0.180 $0.210
RE PM TY II (W) 12" (DOT)
LF 231.000 $5.000 $2.200 $0.250 $0.260 $1.000 $1.050 $0.280
RE PM TY II (W) 12" (SLD)
LF 2,292.000 $1.660 $1.920 $0.250 $0.260 $0.500 $0.530 $0.280
RE PM TY II (W) 24" (SLD)
LF 343.000 $3.000 $4.400 $4.000 $4.200 $0.720 $0.760 $4.430
RE PM TY II (Y) 6" (SLD)
LF 92,245.000 $0.250 $0.180 $0.150 $0.160 $0.170 $0.180 $0.170
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 17,690.000 $0.700 $0.570 $0.600 $0.590 $0.500 $0.530 $0.620
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 92,361.000 $0.800 $0.570 $0.600 $0.590 $0.500 $0.530 $0.620
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 92,245.000 $0.900 $0.570 $0.600 $0.590 $0.500 $0.530 $0.620
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 231.000 $5.000 $5.500 $2.500 $2.630 $2.500 $2.800 $2.770
PRFB RUMBLE STRIP (BLK)(4')(TRANSVERSE)
LF 320.000 $10.000 $16.500 $15.000 $15.750 $4.000 $4.200 $16.610
PREFAB PM TY C (W)(24")(SLD)
LF 37.000 $30.000 $18.700 $15.000 $15.750 $14.000 $15.000 $16.610
PREFAB PM TY C (W)(ARROW)
EA 4.000 $500.000 $242.000 $225.000 $236.250 $190.000 $200.000 $249.120
PREFAB PM TY C (W)(NUMBER)
EA 2.000 $500.000 $242.000 $250.000 $262.500 $200.000 $220.000 $276.800
PREFAB PM TY C (W)(WORD)
EA 10.000 $500.000 $358.000 $325.000 $341.250 $255.000 $270.000 $359.840
PREFAB PM TY C (W)(36")(YLD TRI)
EA 3.000 $500.000 $17.000 $50.000 $52.500 $50.000 $53.000 $55.360
REFL PAV MRKR TY II-A-A
EA 4.000 $60.000 $11.000 $10.000 $10.500 $4.000 $5.000 $11.070
REFL PAV MRKR TY II-C-R
EA 1,926.000 $4.500 $5.500 $4.500 $4.730 $3.500 $4.000 $4.980
Totals: $10,040,718.560 $8,968,076.230 $9,274,102.250 $10,097,096.455 $10,107,055.340 $11,572,486.710 $11,613,776.450
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $15,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $10,000.00
CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $40,000.00