TAYLOR SL 322 (2398-01-057)
Items: 28
County: TAYLOR
Length: 0.0000 MILES
Highway: SL 322
District: ABILENE
Control Number: 2398-01-057
DBE Goal: 0.0%
Project: BR 2025(716)
Guaranty: $28,000.00
Time: 101 WORKING DAYS
Engineer's Estimate: $1,390,494.33
Date: 05/01/2025 (1 year ago)
Contract Number: 5253029
Type: BRIDGE MAINTENANCE
Project ID: A00190971
Contract Type: Federal
Project Description: BMIP
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
CAL HAYS
TAYLOR SL 322 (2398-01-057)
Project Name: N/A
Project: BR 2025(716)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT UPRR
Limits To: NB
Project Description: BMIP
JONES FM 2404 (2474-01-012)
Project Name: BRIDGE BMIP FM 2404 @ MULBERRY CRK
Project: BR 2025(717)
Length: 0.0000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: FM 2404
Limits To: @ MULBERRY CREEK
Project Description: BMIP
TAYLOR US 84 (0006-18-067)
Project Name: BRIDGE BMIP US 84 WB @ IH 20
Project: BR 2025(718)
Length: 0.0000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: US 84
Limits To: @ IH 20
Project Description: BMIP
TAYLOR SL 322 (2398-01-058)
Project Name: BMIP SL 322 SB AT UPRR TAYLOR CO
Project: BR 2025(716)
Length: 0.0000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: AT UPRR
Limits To: SB
Project Description: BMIP
MITCHELL BI 20J (0005-12-016)
Project Name: BRIDGE BMIP BI 20J @ IH 20 C-CITY
Project: BR 2025(717)
Length: 0.0000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: BI 20J WB
Limits To: @ IH 20
Project Description: BMIP
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,390,494.33 | |||
| $1,338,126.80 |
-3.77%
-$52,367.53
|
|||
| $1,350,387.00 |
-2.88%
-$40,107.33
|
0.92%
$12,260.20
|
||
| $1,396,564.00 |
0.44%
$6,069.67
|
4.37%
$58,437.20
|
-3.42%
-$46,177.00
|
|
| $1,443,546.00 |
3.82%
$53,051.67
|
7.88%
$105,419.20
|
-3.36%
-$46,982.00
|
|
| $1,589,670.00 |
14.32%
$199,175.67
|
18.8%
$251,543.20
|
-10.12%
-$146,124.00
|
|
| $1,608,923.00 |
15.71%
$218,428.67
|
20.24%
$270,796.20
|
-1.21%
-$19,253.00
|
|
| $1,685,335.60 |
21.2%
$294,841.27
|
25.95%
$347,208.80
|
-4.75%
-$76,412.60
|
|
| $1,734,381.00 |
24.73%
$343,886.67
|
29.61%
$396,254.20
|
-2.91%
-$49,045.40
|
|
| $1,883,360.00 |
35.45%
$492,865.67
|
40.75%
$545,233.20
|
-8.59%
-$148,979.00
|
E
Engineer's Estimate
$1,390,494.33
1
Awarded
$1,338,126.80
Over/Under Est:
-3.77%
-$52,367.53
$1,350,387.00
Over/Under Est:
-2.88%
-$40,107.33
Amt Left:
0.92%
$12,260.20
$1,396,564.00
Over/Under Est:
0.44%
$6,069.67
Amt Left:
4.37%
$58,437.20
Delta:
-3.42%
-$46,177.00
$1,443,546.00
Over/Under Est:
3.82%
$53,051.67
Amt Left:
7.88%
$105,419.20
Delta:
-3.36%
-$46,982.00
$1,589,670.00
Over/Under Est:
14.32%
$199,175.67
Amt Left:
18.8%
$251,543.20
Delta:
-10.12%
-$146,124.00
$1,608,923.00
Over/Under Est:
15.71%
$218,428.67
Amt Left:
20.24%
$270,796.20
Delta:
-1.21%
-$19,253.00
$1,685,335.60
Over/Under Est:
21.2%
$294,841.27
Amt Left:
25.95%
$347,208.80
Delta:
-4.75%
-$76,412.60
$1,734,381.00
Over/Under Est:
24.73%
$343,886.67
Amt Left:
29.61%
$396,254.20
Delta:
-2.91%
-$49,045.40
$1,883,360.00
Over/Under Est:
35.45%
$492,865.67
Amt Left:
40.75%
$545,233.20
Delta:
-8.59%
-$148,979.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| ONE WAY CONCRETE CONSTRUCTION, LLC | 30.86% | $412,945.93 |
| 1 PRIORITY ENVIRONMENTAL SERVICES, LLC | 16.26% | $217,579.42 |
| DUSTROL, INC. | 1.49% | $19,938.09 |
| FC TRAFFIC CONTROL, INC. | 1.10% | $14,719.39 |
| ERWIN STEEL WORKS, LLC | 0.90% | $12,043.14 |
| TRP CONSTRUCTION GROUP, LLC | 0.76% | $10,169.76 |
| SKIDABRADER GROUP LLC | 0.56% | $7,493.51 |
| Total: | 51.93% | $694,889.24 |
Bid Items & Bid Tabulations
28
Total
0 of 28
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) | $90,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $96,000.00 |