TAYLOR FM 382 (1070-02-010)

Items: 61

County: TAYLOR
Length: 0.0000 MILES
Highway: FM 382
District: ABILENE
Control Number: 1070-02-010
DBE Goal: 4.0%
Project: STP 2025(547)HES
Guaranty: $52,000.00
Time: 192 WORKING DAYS
Engineer's Estimate: $2,358,683.10
Date: 03/05/2025 (1 year ago)
Contract Number: 3253220
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00193322
Contract Type: Federal
Project Description: WIDEN ROADWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,358,683.10
$1,784,682.40
Over/Under Est: -24.34% -$574,000.70
$2,156,894.40
Over/Under Est: -8.56% -$201,788.70
Amt Left: 20.86% $372,212.00
Over/Under Est: 6.52% $153,818.90
Amt Left: 40.78% $727,819.60
Delta: -16.49% -$355,607.60
$2,596,954.00
Over/Under Est: 10.1% $238,270.90
Amt Left: 45.51% $812,271.60
Delta: -3.36% -$84,452.00
$2,844,005.78
Over/Under Est: 20.58% $485,322.68
Amt Left: 59.36% $1,059,323.38
Delta: -9.51% -$247,051.78
Over/Under Est: 20.75% $489,357.15
Amt Left: 59.58% $1,063,357.85
Delta: -0.14% -$4,034.47
Subcontractor Percentage Amount
DIIBS SPECIALISTS, LLC 2.99% $53,362.00
FLAT LINE, INC. 2.28% $40,690.76
DK CONTRACTING, LLC 1.68% $29,982.66
CONTRACTORS SERVICE, LTD. 1.57% $28,019.51
Total: 8.52% $152,054.93

Bid Items & Bid Tabulations

61 Total 0 of 61
TAYLOR  |  FM 382  |  ABILENE  |  1070-02-010  |  03/05/2025  |  $2,358,683.10  |  STP 2025(547)HES  |  WIDEN ROAD - ADD SHOULDERS  |  192 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
CK NEWBERRY, LLC
BONTKE BROTHERS CONSTRUCTION COMPANY
LAKEY, INC.
GILVIN-TERRILL, LTD.
GREY SKY CONSTRUCTION LLC
RMV (6") TRT/UNTRT BASE & ASPH PAV
SY 556.000 $10.000 $10.000 $15.000 $22.000 $16.500 $30.000 $20.000
OBLITERATING ABANDONED ROAD
SY 2,384.000 $25.000 $7.000 $6.000 $22.000 $6.250 $25.000 $60.000
EXCAV (ROADWAY)
CY 6,566.000 $15.000 $14.000 $25.000 $18.000 $23.797 $35.000 $30.000
EMBANK (FNL)(DC)(TY A)
CY 5,248.000 $35.000 $17.000 $25.000 $12.000 $13.000 $35.000 $40.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 9,332.000 $2.000 $0.450 $0.500 $2.000 $1.000 $0.500 $1.000
VEGETATIVE WATERING
TGL 75.000 $10.000 $75.000 $30.000 $500.000 $38.270 $50.000 $50.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 3,747.000 $90.000 $58.000 $95.000 $65.000 $100.000 $50.000 $80.000
CEMENT
TON 44.000 $400.000 $325.000 $325.000 $300.000 $262.500 $250.000 $350.000
CEMENT TRT (NEW BASE)(12")
SY 2,556.000 $3.000 $10.000 $10.000 $14.000 $20.000 $20.000 $10.000
PRIME COAT (MC-30)
GAL 3,352.000 $9.000 $10.000 $8.000 $10.000 $8.000 $10.000 $6.000
ASPH (AC-20-5TR)
GAL 23,162.000 $6.000 $8.000 $5.000 $9.000 $5.040 $6.000 $6.000
ASPH (RC-250)
GAL 639.000 $10.000 $10.000 $8.000 $10.000 $11.000 $20.000 $6.000
ASPH (AC-20-5TR OR CRS-2P)
GAL 8,181.000 $5.000 $8.000 $6.000 $10.000 $6.250 $6.000 $6.000
AGGR (TY-B, GR-5)(SAC-B)
CY 21.000 $160.000 $300.000 $300.000 $275.000 $645.000 $265.000 $300.000
AGGR (TY-PB, GR-3)(SAC-B)
CY 183.000 $140.000 $200.000 $325.000 $275.000 $136.000 $315.000 $300.000
AGGR (TY-PB, GR-4)(SAC-B)
CY 467.000 $180.000 $200.000 $150.000 $275.000 $145.750 $315.000 $300.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 4,455.000 $70.000 $38.000 $45.000 $55.000 $70.000 $64.900 $45.000
CEM STABIL BKFL
CY 31.000 $350.000 $275.000 $250.000 $150.000 $225.000 $350.000 $350.000
RAIL (TY T631)
LF 100.000 $130.000 $100.000 $110.000 $175.000 $160.000 $100.000 $250.000
CONC BOX CULV (4 FT X 2 FT)
LF 44.000 $900.000 $550.000 $1,000.000 $1,100.000 $650.000 $400.000 $1,000.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 43.000 $1,100.000 $680.000 $1,500.000 $1,200.000 $1,050.000 $1,000.000 $1,250.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 16.000 $1,200.000 $725.000 $1,750.000 $1,500.000 $1,200.000 $1,100.000 $1,250.000
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 8.000 $1,300.000 $975.000 $2,000.000 $1,800.000 $1,159.300 $1,250.000 $1,500.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1)(C)
EA 2.000 $8,500.000 $8,650.000 $10,000.000 $8,000.000 $15,000.000 $7,500.000 $15,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1)(C)
EA 8.000 $9,200.000 $8,875.000 $10,000.000 $9,500.000 $18,500.000 $8,500.000 $20,000.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1)(C)
EA 6.000 $10,000.000 $10,200.000 $10,000.000 $15,000.000 $25,000.000 $10,000.000 $25,000.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1)(C)
EA 2.000 $11,000.000 $13,000.000 $12,000.000 $17,500.000 $22,000.000 $13,500.000 $45,000.000
REMOV STR (WINGWALL)
EA 10.000 $3,000.000 $1,900.000 $5,000.000 $2,000.000 $2,500.000 $1,000.000 $2,500.000
MOBILIZATION
LS 1.000 $220,365.000 $125,000.000 $200,000.000 $250,000.000 $400,000.000 $280,000.000 $275,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $15,000.000 $10,000.000 $2,500.000 $7,500.000 $7,100.000 $50,000.000 $12,500.000
TMA (STATIONARY)
DAY 77.000 $250.000 $175.000 $350.000 $250.000 $400.000 $715.000 $250.000
TMA (MOBILE OPERATION)
DAY 16.000 $500.000 $175.000 $350.000 $500.000 $350.000 $715.000 $550.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 140.000 $100.000 $100.000 $100.000 $8.000 $67.560 $90.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 140.000 $15.000 $6.000 $30.000 $4.000 $17.030 $25.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $6.000 $6.500 $7.000 $5.000 $6.120 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $2.000 $2.000 $3.000 $4.000 $1.850 $1.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 980.000 $8.000 $8.000 $8.000 $8.000 $6.625 $5.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 980.000 $2.500 $2.000 $2.000 $4.000 $2.000 $1.000 $9.000
DRIVEWAYS (BASE)
SY 421.000 $40.000 $20.000 $50.000 $65.000 $90.000 $30.000 $40.000
TURNOUTS (RAP)
SY 161.000 $10.000 $25.000 $50.000 $25.000 $20.000 $30.000 $45.000
MTL W-BEAM GD FEN (TIM POST)
LF 725.000 $30.000 $28.000 $28.000 $35.000 $31.110 $26.000 $30.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $3.500 $3.000 $3.000 $10.000 $3.450 $4.000 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,245.000 $3,500.000 $4,000.000 $3,648.800 $3,300.000 $3,520.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $330.000 $275.000 $225.000 $1,000.000 $360.120 $400.000 $1,500.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 6.000 $350.000 $270.000 $250.000 $800.000 $379.760 $250.000 $1,150.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 1.000 $500.000 $460.000 $425.000 $800.000 $420.000 $450.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $800.000 $725.000 $700.000 $975.000 $731.000 $700.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 4.000 $900.000 $940.000 $900.000 $1,500.000 $990.000 $900.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $950.000 $960.000 $900.000 $1,600.000 $924.000 $900.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $1,000.000 $1,100.000 $1,000.000 $1,625.000 $875.000 $1,000.000 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(T-EXAL)
EA 1.000 $1,350.000 $1,500.000 $1,400.000 $800.000 $1,000.000 $1,400.000 $1,150.000
REMOVE SM RD SN SUP&AM
EA 32.000 $125.000 $75.000 $200.000 $150.000 $115.000 $125.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 15.000 $50.000 $55.000 $50.000 $800.000 $42.000 $60.000 $100.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 24.000 $100.000 $65.000 $130.000 $800.000 $500.000 $55.000 $100.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 160.000 $17.000 $5.500 $25.000 $800.000 $25.000 $15.000 $20.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,594.000 $2.000 $2.250 $1.000 $1.000 $2.500 $1.500 $6.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 36,656.000 $1.300 $0.700 $1.200 $1.000 $0.930 $0.640 $1.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 18,517.000 $1.300 $0.700 $1.200 $1.000 $1.000 $0.640 $1.250
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 3,054.000 $1.300 $0.700 $1.200 $1.000 $0.850 $0.640 $1.000
PREFAB PM TY C (W)(24")(SLD)
LF 112.000 $20.000 $19.800 $17.000 $18.000 $20.000 $18.000 $20.000
REFL PAV MRKR TY II-A-A
EA 414.000 $7.000 $5.500 $5.000 $15.000 $12.000 $5.000 $6.000
Totals: $2,358,683.100 $1,784,682.400 $2,156,894.400 $2,512,502.000 $2,596,954.002 $2,844,005.780 $2,848,040.250
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $11,000.00