TAYLOR CS (0908-33-106)

Items: 66

County: TAYLOR
Length: N/A
Highway: CS
District: ABILENE
Control Number: 0908-33-106
DBE Goal: N/A
Project: BR 2022(944)
Guaranty: N/A
Time: 133 WORKING DAYS
Engineer's Estimate: $1,216,522.25
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,216,522.25
$1,316,532.40
Over/Under Est: 8.22% $100,010.15
Over/Under Est: 24.74% $300,971.65
Amt Left: 15.26% $200,961.50
Over/Under Est: 35.07% $426,693.90
Amt Left: 24.81% $326,683.75
Delta: -8.28% -$125,722.25
Subcontractor Percentage Amount
WYLIE DRILLING & DRAINAGE, INC. 5.46% $71,882.67
HJC FARMS, INC. 1.67% $21,986.09
CONTRACTORS SERVICE, LTD. 0.73% $9,610.69
D. I. J. CONSTRUCTION, INC. 0.69% $9,084.07
DK CONTRACTING, LLC 0.66% $8,689.11
TORO BRAVO CONSTRUCTION, LLC 0.32% $4,212.90
Total: 9.53% $125,465.53

Bid Items & Bid Tabulations

66 Total 0 of 66
TAYLOR  |  CS  |  ABILENE  |  0908-33-106  |  05/04/2023  |  $1,216,522.25  |  BR 2022(944)  |  BRIDGE REPL  |  133 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
DELGADO'S CONTRACTORS, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
AC 0.250 $55,000.000 $50,000.000 $20,000.000 $200,000.000
REMOVING CONC (RIPRAP)
SY 224.000 $35.000 $25.000 $30.000 $90.000
REMOVING CONC (SIDEWALKS)
SY 120.000 $20.000 $25.000 $30.000 $90.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 1,162.000 $15.000 $13.500 $20.000 $15.000
EXCAVATION (ROADWAY)
CY 307.200 $15.000 $35.000 $40.000 $40.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 114.800 $25.000 $35.000 $50.000 $60.000
BROADCAST SEED (PERM) (URBAN) (CLAY)
SY 1,184.000 $1.250 $2.000 $5.000 $4.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 238.000 $80.000 $100.000 $130.000 $100.000
PRIME COAT (MC-30)
GAL 132.000 $20.000 $15.000 $30.000 $40.000
CURB (TYPE II)
LF 10.000 $40.000 $40.000 $50.000 $500.000
CEM STABIL BKFL
CY 42.000 $320.000 $250.000 $250.000 $350.000
TEMPORARY SPL SHORING
SF 660.000 $35.000 $120.000 $45.000 $5.000
DRILL SHAFT (24 IN)
LF 380.000 $250.000 $210.000 $300.000 $250.000
CL C CONC (ABUT)(HPC)
CY 23.800 $2,000.000 $1,650.000 $2,000.000 $2,000.000
CL C CONC (CAP)(HPC)
CY 18.800 $2,000.000 $1,900.000 $2,000.000 $2,200.000
CL C CONC (COLUMN)(HPC)
CY 4.500 $2,300.000 $1,800.000 $2,000.000 $3,000.000
REINF CONC SLAB (SLAB BEAM)(HPC)
SF 3,600.000 $30.000 $30.500 $50.000 $60.000
BRIDGE SIDEWALK (HPC)
SF 1,100.000 $25.000 $28.000 $35.000 $50.000
APPROACH SLAB (HPC)
CY 76.300 $1,030.000 $1,050.000 $1,500.000 $1,200.000
PRESTR CONC SLAB BEAM (5SB12)
LF 689.390 $275.000 $264.750 $310.000 $385.000
SILICONE RESIN PAINT FINISH
SF 410.000 $12.000 $18.000 $30.000 $10.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 3.000 $250.000 $500.000 $250.000 $500.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 578.200 $175.000 $125.000 $300.000 $220.000
RIPRAP (MOW STRIP)(4 IN)
CY 6.000 $700.000 $750.000 $625.000 $800.000
STR STEEL (MISC NON - BRIDGE)
LB 283.000 $20.000 $112.000 $35.000 $45.000
RAIL (TY T223)(HPC)
LF 112.000 $205.000 $185.000 $200.000 $200.000
RAIL (TY C223)(HPC)
LF 112.000 $225.000 $185.000 $200.000 $200.000
TYPE A JOINT
LF 74.000 $100.000 $32.000 $150.000 $75.000
RC PIPE (CL IV)(18 IN)
LF 50.000 $125.000 $250.000 $110.000 $150.000
SET (TY II) (18 IN) (RCP) (3: 1) (P)
EA 2.000 $1,500.000 $3,000.000 $1,300.000 $5,000.000
REMOV STR (PIPE)
LF 150.000 $30.000 $35.000 $20.000 $30.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $50,000.000 $135,000.000 $40,000.000 $60,000.000
REMOV STR (PIPE GATE)
LF 26.000 $100.000 $35.000 $50.000 $40.000
MOBILIZATION
LS 1.000 $105,000.000 $100,000.000 $170,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $10,000.000 $6,000.000 $4,000.000 $14,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 120.000 $30.000 $80.000 $40.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 120.000 $10.000 $25.000 $20.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 110.000 $5.000 $10.000 $7.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 110.000 $2.000 $2.000 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 372.000 $12.000 $10.000 $10.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 372.000 $2.000 $2.000 $2.000 $1.000
CONC SIDEWALKS (4")
SY 110.000 $85.000 $98.000 $100.000 $150.000
CURB RAMPS (SPECIAL)
SY 8.000 $560.000 $325.000 $400.000 $750.000
MTL W-BEAM GD FEN (TIM POST)
LF 25.000 $35.000 $44.000 $45.000 $40.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $1,500.000 $1,650.000 $1,750.000 $3,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $4,000.000 $6,050.000 $4,000.000 $4,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $30,000.000 $33,000.000 $30,000.000 $30,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $1,025.000 $962.000 $1,050.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $600.000 $500.000 $600.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 4.000 $600.000 $640.000 $650.000 $2,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $750.000 $770.000 $800.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 2.000 $130.000 $100.000 $200.000 $200.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 9.000 $77.000 $46.000 $50.000 $50.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
EA 2.000 $51.000 $47.000 $65.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 9.000 $45.000 $50.000 $60.000 $50.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 1.000 $86.000 $53.000 $60.000 $50.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 1.000 $350.000 $620.000 $700.000 $500.000
INSTL OM ASSM (OM-3R)(TWT)GND
EA 1.000 $350.000 $620.000 $700.000 $500.000
PAVEMENT SEALER 4"
LF 682.000 $1.000 $1.000 $4.000 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 718.000 $1.000 $4.700 $9.000 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 804.000 $1.000 $4.700 $9.000 $3.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 60.000 $25.000 $22.000 $22.000 $20.000
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 10.000 $75.000 $44.000 $170.000 $40.000
REFL PAV MRKR TY II-A-A
EA 9.000 $5.000 $17.000 $45.000 $20.000
SP MIXES SP-C SAC-B PG70-22
TON 72.000 $200.000 $250.000 $250.000 $400.000
TMA (MOBILE OPERATION)
DAY 1.000 $400.000 $1,000.000 $2,000.000 $200.000
Totals: $1,216,522.250 $1,316,532.402 $1,517,493.900 $1,643,216.150