TAYLOR VA (0908-33-100)
Items: 15
County: TAYLOR
Length: N/A
Highway: VA
District: ABILENE
Control Number: 0908-33-100
DBE Goal: N/A
Project: C 908-33-100
Guaranty: N/A
Time: 48 WORKING DAYS
Engineer's Estimate: $197,805.00
Date: 05/06/2021 (5 years ago)
Contract Number: N/A
Type: DRAINAGE IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$197,805.00 | |||
| $174,853.00 |
-11.6%
-$22,952.00
|
|||
| $182,330.00 |
-7.82%
-$15,475.00
|
4.28%
$7,477.00
|
||
| $189,981.00 |
-3.96%
-$7,824.00
|
8.65%
$15,128.00
|
-4.20%
-$7,651.00
|
|
| $192,488.37 |
-2.69%
-$5,316.63
|
10.09%
$17,635.37
|
-1.32%
-$2,507.37
|
|
| $207,906.00 |
5.11%
$10,101.00
|
18.9%
$33,053.00
|
-8.01%
-$15,417.63
|
|
| $207,910.00 |
5.11%
$10,105.00
|
18.91%
$33,057.00
|
0.00%
-$4.00
|
|
| $259,810.00 |
31.35%
$62,005.00
|
48.59%
$84,957.00
|
-24.96%
-$51,900.00
|
|
| $279,470.00 |
41.29%
$81,665.00
|
59.83%
$104,617.00
|
-7.57%
-$19,660.00
|
E
Engineer's Estimate
$197,805.00
1
Awarded
$174,853.00
Over/Under Est:
-11.6%
-$22,952.00
$182,330.00
Over/Under Est:
-7.82%
-$15,475.00
Amt Left:
4.28%
$7,477.00
$189,981.00
Over/Under Est:
-3.96%
-$7,824.00
Amt Left:
8.65%
$15,128.00
Delta:
-4.20%
-$7,651.00
$192,488.37
Over/Under Est:
-2.69%
-$5,316.63
Amt Left:
10.09%
$17,635.37
Delta:
-1.32%
-$2,507.37
$207,906.00
Over/Under Est:
5.11%
$10,101.00
Amt Left:
18.9%
$33,053.00
Delta:
-8.01%
-$15,417.63
$207,910.00
Over/Under Est:
5.11%
$10,105.00
Amt Left:
18.91%
$33,057.00
Delta:
0.00%
-$4.00
$259,810.00
Over/Under Est:
31.35%
$62,005.00
Amt Left:
48.59%
$84,957.00
Delta:
-24.96%
-$51,900.00
$279,470.00
Over/Under Est:
41.29%
$81,665.00
Amt Left:
59.83%
$104,617.00
Delta:
-7.57%
-$19,660.00