Show Job Controls
Bid Cobra

TAYLOR VARIOUS (0908-00-122)

Items: 12

County: TAYLOR
Length: 0.0000 MILES
Highway: VARIOUS
District: ABILENE
Control Number: 0908-00-122
DBE Goal: 0.0%
Project: C 908-00-122
Guaranty: $41,000.00
Time: 86 WORKING DAYS
Engineer's Estimate: $2,033,924.00
Date: 07/02/2025 (11 months ago)
Contract Number: 7253222
Type: INSTALL/REPLACE SIGNS
Project ID: A00194162
Project Description: REPLACE/INSTALL LARGE SIGNS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RANDEE SHIELDS
DAVID KRAUSE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,033,924.00
$1,507,937.50
Over/Under Est: -25.86% -$525,986.50
Over/Under Est: -24.33% -$494,846.50
Amt Left: 2.07% $31,140.00
$1,620,023.90
Over/Under Est: -20.35% -$413,900.10
Amt Left: 7.43% $112,086.40
Delta: -5.26% -$80,946.40
Over/Under Est: -16.89% -$343,588.00
Amt Left: 12.1% $182,398.50
Delta: -4.34% -$70,312.10
Over/Under Est: 17.92% $364,436.40
Amt Left: 59.05% $890,422.90
Delta: -41.89% -$708,024.40

Bid Items & Bid Tabulations

12 Total 0 of 12
TAYLOR  |  VARIOUS  |  ABILENE  |  0908-00-122  |  07/02/2025  |  $2,033,924.00  |  C 908-00-122  |  INSTL/REPLACE SIGNS  |  86 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HJC FARMS, INC.
VACA UNDERGROUND UTILITIES INC
RHINO EQUITY, LLC
CENTERLINE TECHNOLOGIES, LLC
WG ENGINEERING & CONSTRUCTION, LLC
REMOV CONC (RIPRAP)
SY 9.000 $30.000 $36.500 $650.000 $35.000 $100.000 $550.600
FLOWABLE BACKFILL
CY 4.000 $500.000 $1,000.000 $400.000 $1,000.000 $500.000 $576.800
DRILL SHAFT (12 IN)
LF 12.000 $90.000 $175.000 $115.000 $100.000 $150.000 $295.000
DRILL SHAFT (24 IN)
LF 2,793.000 $150.000 $175.000 $175.000 $235.000 $200.000 $389.400
RIPRAP (CONC)(4 IN)
CY 1.000 $715.000 $1,000.000 $1,000.000 $600.000 $1,000.000 $2,136.700
MOBILIZATION
LS 1.000 $182,923.000 $51,000.000 $145,000.000 $20,000.000 $6,000.000 $133,152.700
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $15,000.000 $3,000.000 $2,000.000 $2,500.000 $600.000 $10,564.400
TMA (STATIONARY)
DAY 80.000 $300.000 $150.000 $50.000 $1.000 $65.000 $326.400
ALUMINUM SIGNS (TY G)
SF 11,209.000 $30.000 $25.000 $35.000 $25.000 $32.000 $39.400
ALUMINUM SIGNS (TY O)
SF 1,182.000 $35.000 $25.000 $33.000 $40.000 $30.000 $48.000
INSTALL LRSS (STRUCT STEEL)
LB 75,686.000 $11.000 $6.500 $5.250 $6.150 $8.000 $5.200
REMOVE LRSA
EA 132.000 $900.000 $1,000.000 $400.000 $1,000.000 $850.000 $1,468.200
Totals: $2,033,924.000 $1,507,937.500 $1,539,077.500 $1,620,023.900 $1,690,336.000 $2,398,360.400
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $15,000.00