Show Job Controls
Bid Cobra

TAYLOR VA (0908-00-103)

Items: 18

County: TAYLOR
Length: N/A
Highway: VA
District: ABILENE
Control Number: 0908-00-103
DBE Goal: N/A
Project: STP 2021(185)
Guaranty: N/A
Time: 58 WORKING DAYS
Engineer's Estimate: $1,003,978.50
Date: 12/03/2020 (5 years ago)
Contract Number: N/A
Type: SPOT REPAIR MILL AND FILL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,003,978.50
$914,854.20
Over/Under Est: -8.88% -$89,124.30
Over/Under Est: -8% -$80,318.28
Amt Left: 0.96% $8,806.02
Over/Under Est: -5.47% -$54,925.71
Amt Left: 3.74% $34,198.59
Delta: -2.75% -$25,392.57
Over/Under Est: 13.47% $135,202.55
Amt Left: 24.52% $224,326.85
Delta: -20.03% -$190,128.26
$1,186,618.73
Over/Under Est: 18.19% $182,640.23
Amt Left: 29.71% $271,764.53
Delta: -4.16% -$47,437.68
$1,371,146.53
Over/Under Est: 36.57% $367,168.03
Amt Left: 49.88% $456,292.33
Delta: -15.55% -$184,527.80
Over/Under Est: 49.88% $500,803.20
Amt Left: 64.48% $589,927.50
Delta: -9.75% -$133,635.17

Bid Items & Bid Tabulations

18 Total 0 of 18
TAYLOR  |  VA  |  ABILENE  |  0908-00-103  |  12/03/2020  |  $1,003,978.50  |  STP 2021(185)  |  SPOT REPAIR MILL AND FILL  |  58 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
BONTKE BROTHERS CONSTRUCTION COMPANY
J. H. STRAIN & SONS, INC.
NOBLES ROAD CONSTRUCTION, INC.
A. L. HELMCAMP, INC.
CONTRACT PAVING CO.
LONE STAR PAVING COMPANY
PLANE ASPH CONC PAV (2")
SY 50,624.000 $2.000 $2.000 $1.500 $2.220 $2.850 $3.400 $3.000 $5.500
PLANE ASPH CONC PAV (6")
SY 800.000 $5.000 $6.000 $3.000 $11.100 $8.000 $9.700 $20.000 $8.000
PLANE ASPH CONC PAV (4")
SY 3,400.000 $5.000 $6.000 $2.000 $4.800 $5.000 $6.900 $14.000 $6.000
MOBILIZATION
LS 1.000 $70,000.000 $1,000.000 $5,700.220 $45,000.000 $91,500.000 $120,000.000 $120,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $250.000 $5,000.000 $14,000.000 $15,500.000 $16,000.000 $9,500.000 $34,700.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,970.000 $1.000 $1.000 $2.000 $2.250 $2.100 $1.000 $0.429 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 700.000 $2.000 $1.200 $4.000 $1.380 $1.050 $1.050 $1.320 $2.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 6,563.000 $0.500 $1.200 $1.000 $0.400 $1.050 $1.050 $0.385 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 24,696.000 $0.500 $0.900 $0.750 $0.370 $0.700 $0.680 $0.352 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 9,306.000 $0.500 $1.200 $1.000 $0.370 $1.050 $1.050 $0.352 $1.000
REFL PAV MRKR TY I-C
EA 20.000 $5.000 $7.000 $15.000 $5.750 $4.000 $4.200 $5.500 $12.000
REFL PAV MRKR TY II-C-R
EA 309.000 $5.000 $5.000 $15.000 $5.750 $4.000 $4.200 $5.500 $12.000
SP MIXES SP-D SAC-A PG76-22
TON 3,755.000 $115.000 $112.000 $110.000 $106.440 $115.000 $115.000 $147.150 $130.000
SP MIXES SP-D SAC-B PG76-22
TON 2,828.000 $110.000 $106.000 $110.000 $97.540 $110.000 $115.000 $137.150 $128.000
TACK COAT
GAL 5,482.000 $4.000 $2.000 $4.000 $3.000 $5.000 $2.800 $6.000 $6.100
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $100.000 $300.000 $250.000 $250.000 $350.000 $140.000 $200.000 $500.000
TMA (STATIONARY)
DAY 14.000 $200.000 $300.000 $300.000 $250.000 $525.000 $220.000 $500.000 $250.000
TMA (MOBILE OPERATION)
DAY 12.000 $200.000 $100.000 $1,500.000 $250.000 $900.000 $25.000 $500.000 $250.000
Totals: $1,003,978.500 $914,854.200 $923,660.220 $949,052.790 $1,139,181.050 $1,186,618.730 $1,371,146.539 $1,504,781.700