TAYLOR FM 89 (0699-01-065)
Items: 87
County: TAYLOR
Length: 3.3120 MILES
Highway: FM 89
District: ABILENE
Control Number: 0699-01-065
DBE Goal: 0.0%
Project: STP 2026(427)HES
Guaranty: $100,000.00
Time: 234 WORKING DAYS
Engineer's Estimate: $6,239,737.10
Date: 03/04/2026 (3 months ago)
Contract Number: 3263009
Type: WIDEN ROAD - ADD LANES AND SHOULDERS
Project ID: A00193354
Contract Type: Federal
Project Description: ADD CONTINUOUS CENTER TURN LANES AND RIGHT TURN LANES AT INTERSECTION.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
CAL HAYS
TAYLOR FM 89 (0699-01-065)
Project Name: N/A
Project: STP 2026(427)HES
Length: 1.2450 MILES
Project Type: CONSTRUCTION
Limits From: 1.219 MILES SOUTH OF ELM CREEK
Limits To: ELM CREEK
Project Description: ADD CONTINUOUS CENTER TURN LANES AND RIGHT TURN LANES AT INTERSECTION.
TAYLOR FM 89 (0699-01-067)
Project Name: FM 89 ADD TURN LANES ELM CRK TO FM 707
Project: F 2026(428)
Length: 2.0670 MILES
Project Type: INTERSECTION & OPERATIONAL IMPRV
Limits From: ELM CREEK
Limits To: FM 707
Project Description: ADD CONTINUOUS CENTER TURN LANES AND RIGHT TURN LANES AT INTERSECTION. OVERLAY 2" SP-C
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,239,737.10 | |||
| $6,284,525.46 |
0.72%
$44,788.36
|
|||
| $6,362,077.97 |
1.96%
$122,340.87
|
1.23%
$77,552.51
|
||
| $6,941,805.50 |
11.25%
$702,068.40
|
10.46%
$657,280.04
|
-9.11%
-$579,727.53
|
|
| $7,739,939.27 |
24.04%
$1,500,202.17
|
23.16%
$1,455,413.81
|
-11.50%
-$798,133.77
|
|
| $7,942,078.30 |
27.28%
$1,702,341.20
|
26.38%
$1,657,552.84
|
-2.61%
-$202,139.03
|
E
Engineer's Estimate
$6,239,737.10
1
Awarded
$6,284,525.46
Over/Under Est:
0.72%
$44,788.36
$6,362,077.97
Over/Under Est:
1.96%
$122,340.87
Amt Left:
1.23%
$77,552.51
$6,941,805.50
Over/Under Est:
11.25%
$702,068.40
Amt Left:
10.46%
$657,280.04
Delta:
-9.11%
-$579,727.53
$7,739,939.27
Over/Under Est:
24.04%
$1,500,202.17
Amt Left:
23.16%
$1,455,413.81
Delta:
-11.50%
-$798,133.77
$7,942,078.30
Over/Under Est:
27.28%
$1,702,341.20
Amt Left:
26.38%
$1,657,552.84
Delta:
-2.61%
-$202,139.03
Bid Items & Bid Tabulations
87
Total
0 of 87
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $15,000.00 |