Show Job Controls
Bid Cobra

TAYLOR US 277 (0407-06-047)

Items: 36

County: TAYLOR
Length: N/A
Highway: US 277
District: ABILENE
Control Number: 0407-06-047
DBE Goal: N/A
Project: F 2024(302)
Guaranty: N/A
Time: 106 WORKING DAYS
Engineer's Estimate: $3,090,887.33
Date: 11/01/2023 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,090,887.33
$2,639,408.32
Over/Under Est: -14.61% -$451,479.01
$3,173,156.60
Over/Under Est: 2.66% $82,269.27
Amt Left: 20.22% $533,748.28
$3,282,544.06
Over/Under Est: 6.2% $191,656.73
Amt Left: 24.37% $643,135.74
Delta: -3.45% -$109,387.46
$3,672,473.74
Over/Under Est: 18.82% $581,586.41
Amt Left: 39.14% $1,033,065.42
Delta: -11.88% -$389,929.68
$3,888,838.00
Over/Under Est: 25.82% $797,950.67
Amt Left: 47.34% $1,249,429.68
Delta: -5.89% -$216,364.26

Bid Items & Bid Tabulations

36 Total 0 of 36
TAYLOR  |  US 277  |  ABILENE  |  0407-06-047  |  11/01/2023  |  $3,090,887.33  |  F 2024(302)  |  PREVENT MAINT  |  106 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
CK NEWBERRY, LLC
DUININCK, INC.
REECE ALBERT, INC.
FNH CONSTRUCTION, LLC
EXCAVATION (ROADWAY)
CY 218.000 $32.000 $10.000 $65.000 $48.500 $84.570 $50.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 218.000 $55.000 $10.000 $65.000 $97.000 $93.050 $100.000
BACKFILL (TY B)
STA 462.000 $35.000 $100.000 $140.000 $100.000 $325.590 $200.000
PRIME COAT (AE-P)
GAL 1,000.000 $5.000 $0.100 $7.000 $8.250 $7.650 $10.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 5,631.000 $45.050 $30.000 $45.000 $48.000 $65.200 $50.000
PLANE ASPH CONC PAV (1.5")
SY 112,615.000 $3.000 $1.500 $1.500 $2.300 $3.100 $5.000
RC PIPE (CL III)(24 IN)
LF 13.000 $200.000 $360.000 $260.000 $430.000 $338.970 $150.000
SET (TY I) (24 IN) (3: 1) (C)
EA 7.000 $4,196.000 $1,300.000 $10,000.000 $1,600.000 $3,954.710 $3,000.000
SET (TY I)(S= 9 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $5,200.000 $13,000.000 $40,000.000 $16,500.000 $16,383.790 $30,000.000
SET (TY I)(S= 9 FT)(HW= 7 FT)(3:1) (C)
EA 2.000 $13,000.000 $15,000.000 $50,000.000 $19,500.000 $28,247.910 $40,000.000
MOBILIZATION
LS 1.000 $280,989.760 $242,000.000 $300,000.000 $325,000.000 $181,693.690 $365,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $8,000.000 $30,000.000 $4,000.000 $32,500.000 $8,642.170 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 120.000 $44.000 $20.000 $55.000 $48.000 $120.900 $50.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $9.300 $5.000 $12.000 $12.000 $51.310 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 325.000 $4.400 $5.000 $10.000 $9.600 $17.950 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 325.000 $2.150 $1.000 $5.000 $1.200 $8.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 840.000 $5.760 $8.000 $12.000 $9.600 $19.340 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 840.000 $1.210 $1.000 $5.000 $1.200 $6.290 $9.000
CONC CURB & GUTTER (TY II)
LF 26.000 $82.000 $250.000 $75.000 $360.000 $90.390 $200.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 42,236.000 $0.160 $0.200 $0.250 $0.120 $0.240 $0.500
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 21,118.000 $0.140 $0.200 $0.450 $0.140 $0.400 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $30.000 $30.000 $60.000 $33.000 $31.430 $50.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 200.000 $50.000 $30.000 $85.000 $36.000 $34.290 $50.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,934.000 $3,000.000 $4,500.000 $4,000.000 $3,772.180 $3,500.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,712.000 $1.170 $0.100 $2.500 $1.700 $1.970 $6.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 2,200.000 $0.750 $0.490 $0.850 $0.590 $0.790 $2.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 41,468.000 $0.750 $0.490 $0.750 $0.590 $0.770 $2.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 2,460.000 $0.750 $0.490 $0.800 $0.590 $0.790 $2.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 29,810.000 $0.750 $0.490 $0.750 $0.590 $0.770 $2.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 94.000 $22.600 $20.000 $35.000 $24.000 $22.150 $20.000
REFL PAV MRKR TY I-C
EA 115.000 $3.610 $5.000 $10.000 $6.000 $7.340 $6.000
REFL PAV MRKR TY II-A-A
EA 517.000 $3.300 $5.000 $10.000 $6.000 $7.340 $6.000
SP MIXES SP-C SAC-B PG70-22
TON 12,388.000 $150.000 $133.000 $145.000 $145.900 $173.690 $155.000
TACK COAT
GAL 11,262.000 $4.000 $0.100 $5.250 $6.850 $3.200 $8.000
TMA (STATIONARY)
DAY 80.000 $311.000 $1.000 $315.000 $360.000 $323.670 $250.000
TMA (MOBILE OPERATION)
DAY 4.000 $625.000 $1.000 $615.000 $1,200.000 $861.560 $550.000
Totals: $3,090,887.330 $2,639,408.320 $3,173,156.600 $3,282,544.060 $3,672,473.740 $3,888,838.000