Show Job Controls
Bid Cobra

TAYLOR US 83 (0033-06-129)

Items: 31

County: TAYLOR
Length: 0.0000 MILES
Highway: US 83
District: ABILENE
Control Number: 0033-06-129
DBE Goal: 0.0%
Project: BR 2026(587)
Guaranty: $100,000.00
Time: 114 WORKING DAYS
Engineer's Estimate: $5,992,792.40
Date: 05/07/2026 (4 weeks ago)
Contract Number: 5263212
Type: BRIDGE MAINTENANCE
Project ID: A00207724
Contract Type: Federal
Project Description: BMIP
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (14)
E
Engineer's Estimate
$5,992,792.40
$4,004,004.00
Over/Under Est: -33.19% -$1,988,788.40
Over/Under Est: -30.49% -$1,827,360.60
Amt Left: 4.03% $161,427.80
Over/Under Est: -29.81% -$1,786,664.40
Amt Left: 5.05% $202,124.00
Delta: -0.98% -$40,696.20
Over/Under Est: -29.26% -$1,753,489.40
Amt Left: 5.88% $235,299.00
Delta: -0.79% -$33,175.00
$4,389,566.50
Over/Under Est: -26.75% -$1,603,225.90
Amt Left: 9.63% $385,562.50
Delta: -3.54% -$150,263.50
Over/Under Est: -26.28% -$1,575,101.40
Amt Left: 10.33% $413,687.00
Delta: -0.64% -$28,124.50
Over/Under Est: -20.51% -$1,229,034.25
Amt Left: 18.97% $759,754.15
Delta: -7.83% -$346,067.15
Over/Under Est: -18.41% -$1,103,393.40
Amt Left: 22.11% $885,395.00
Delta: -2.64% -$125,640.85
Over/Under Est: -14.89% -$892,452.40
Amt Left: 27.38% $1,096,336.00
Delta: -4.31% -$210,941.00
$5,257,325.00
Over/Under Est: -12.27% -$735,467.40
Amt Left: 31.3% $1,253,321.00
Delta: -3.08% -$156,985.00
Over/Under Est: -10.64% -$637,535.40
Amt Left: 33.75% $1,351,253.00
Delta: -1.86% -$97,932.00
Over/Under Est: -8.36% -$500,773.36
Amt Left: 37.16% $1,488,015.04
Delta: -2.55% -$136,762.04
$5,608,891.25
Over/Under Est: -6.41% -$383,901.15
Amt Left: 40.08% $1,604,887.25
Delta: -2.13% -$116,872.21
Over/Under Est: 22.82% $1,367,264.60
Amt Left: 83.82% $3,356,053.00
Delta: -31.22% -$1,751,165.75

Bid Items & Bid Tabulations

31 Total 0 of 31
TAYLOR  |  US 83  |  ABILENE  |  0033-06-129  |  05/07/2026  |  $5,992,792.40  |  BR 2026(587)  |  BRIDGE MAINT  |  114 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
GIBSON & ASSOCIATES, INC.
RAGLE CONSTRUCTION, INC.
BLACKSMITH VENTURES LLC
MPB, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
GARRET SHIELDS INFRASTRUCTURE
STRUCTURAL INTEGRITY GROUP LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
PREMIER CONTRACTORS LLC
PATHFIELD INVESTMENTS LLC
MYERS & SONS CONSTRUCTION LLC
TI-ZACK CONCRETE, LLC
SOUTHERN ROAD & BRIDGE, LLC
PLANE ASPH CONC PAV(0" TO 4")
SY 4,600.000 $10.000 $9.000 $18.780 $7.500 $13.250 $10.500 $20.000 $10.000 $15.000 $21.000 $11.000 $11.000 $12.000 $17.500 $18.000
FLOWABLE BACKFILL
CY 20.000 $500.000 $650.000 $800.000 $400.000 $500.000 $545.000 $500.000 $300.000 $495.000 $966.000 $2,000.000 $700.000 $1,115.000 $937.500 $950.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 5,790.000 $18.000 $16.000 $17.600 $16.500 $8.000 $18.000 $16.000 $10.000 $16.000 $29.000 $8.500 $19.000 $23.000 $81.250 $11.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 4,100.000 $150.000 $150.000 $175.000 $125.000 $175.000 $80.000 $250.000 $200.000 $190.000 $116.000 $300.000 $200.000 $77.000 $133.750 $440.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 10.000 $300.000 $300.000 $500.000 $360.000 $200.000 $665.000 $275.000 $200.000 $450.000 $366.000 $380.000 $450.000 $2,115.000 $781.250 $950.000
ELASTOMERIC BEARING (LAMINATED)
EA 26.000 $5,000.000 $1,200.000 $2,000.000 $350.000 $2,000.000 $1,120.000 $1,000.000 $5,000.000 $855.000 $1,101.000 $3,250.000 $3,000.000 $2,541.000 $10,625.000 $3,850.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 1,010.000 $50.000 $65.000 $78.500 $23.000 $42.000 $36.000 $55.000 $50.000 $48.000 $37.000 $75.000 $55.000 $54.000 $31.250 $65.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 6,200.000 $125.000 $88.000 $101.500 $105.000 $99.000 $105.000 $100.000 $125.000 $110.000 $142.000 $150.000 $130.000 $130.000 $138.750 $220.000
POLYESTER POLYMER CONC OVERLAY (3")
SY 5,500.000 $400.000 $257.000 $200.000 $265.000 $286.000 $345.000 $250.000 $300.000 $306.000 $321.000 $300.000 $370.000 $382.000 $312.500 $345.000
STR STEEL (PEDESTAL)
LB 4,200.000 $20.000 $10.500 $12.000 $10.000 $25.000 $11.500 $15.000 $30.000 $40.000 $19.000 $10.000 $26.000 $48.000 $18.750 $68.000
CLEAN AND PAINT EXIST STR (REF NO. 1)
EA 1.000 $750,000.000 $320,000.000 $330,000.000 $350,000.000 $275,000.000 $336,000.000 $300,000.000 $300,000.000 $300,000.000 $293,012.000 $100,000.000 $170,000.000 $259,105.000 $375,000.000 $250,000.000
CLEAN AND PAINT EXIST STR (REF NO. 2)
EA 1.000 $60,000.000 $30,000.000 $30,800.000 $100,000.000 $50,000.000 $31,360.000 $60,000.000 $35,000.000 $28,000.000 $50,228.000 $100,000.000 $25,000.000 $85,890.000 $35,000.000 $75,000.000
HEADER TYPE EXPANSION JOINT
CF 80.000 $400.000 $500.000 $650.000 $475.000 $400.000 $525.000 $650.000 $300.000 $780.000 $508.000 $400.000 $1,200.000 $795.000 $687.500 $950.000
JOINT SEALANT
LF 168.000 $45.000 $75.000 $56.000 $25.000 $42.000 $17.000 $55.000 $20.000 $28.000 $43.000 $40.000 $45.000 $36.000 $143.750 $35.000
SHOT BLASTING
SY 11,700.000 $5.000 $3.000 $4.850 $3.000 $6.000 $22.000 $4.000 $5.000 $3.500 $6.000 $6.000 $9.000 $9.000 $21.250 $8.000
RAISING EXIST STRUCT
LS 1.000 $50,000.000 $89,000.000 $121,250.000 $85,000.000 $80,000.000 $134,400.000 $75,000.000 $100,000.000 $99,500.000 $207,165.000 $40,000.000 $55,000.000 $200,000.000 $100,000.000 $85,000.000
MOBILIZATION
LS 1.000 $544,028.400 $410,644.500 $400,000.000 $410,000.000 $225,000.000 $285,000.000 $202,000.000 $400,000.000 $460,000.000 $510,000.000 $450,000.000 $500,000.000 $500,000.000 $146,250.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $20,000.000 $3,400.000 $27,000.000 $25,000.000 $1.000 $8,250.000 $6,000.000 $5,000.000 $26,350.000 $25,841.000 $3,500.000 $2,500.000 $22,317.500 $18,750.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 7.000 $10,000.000 $3,500.000 $3,200.000 $3,500.000 $13,000.000 $2,400.000 $2,200.000 $1,000.000 $7,500.000 $4,704.000 $3,000.000 $1.000 $6,495.000 $6,875.000 $2,500.000
TMA (STATIONARY)
DAY 146.000 $375.000 $380.000 $360.000 $325.000 $345.000 $100.000 $300.000 $300.000 $250.000 $377.000 $500.000 $1.000 $216.500 $193.750 $850.000
TMA (MOBILE OPERATION)
DAY 5.000 $300.000 $500.000 $750.000 $700.000 $10,000.000 $250.000 $300.000 $300.000 $800.000 $735.000 $400.000 $1.000 $216.500 $312.500 $850.000
RE PM TY III (W)(6")(SLD)
LF 1,757.000 $3.000 $3.500 $3.300 $3.000 $3.000 $2.000 $4.000 $1.150 $3.000 $4.000 $2.000 $4.000 $2.000 $3.750 $5.000
RE PM TY III (W)(6")(BRK)
LF 2,087.000 $4.000 $3.500 $3.300 $3.000 $3.000 $2.500 $4.000 $1.200 $1.500 $4.000 $2.000 $4.000 $2.000 $3.750 $5.000
RE PM TY III (W)(12")(DOT)
LF 1,222.000 $2.000 $5.500 $5.500 $5.000 $5.000 $2.000 $6.000 $1.500 $6.000 $6.000 $4.000 $5.000 $3.500 $6.250 $6.000
RE PM TY III (Y)(6")(SLD)
LF 1,757.000 $3.000 $3.500 $3.300 $3.000 $3.000 $2.000 $4.000 $1.100 $1.500 $4.000 $2.000 $4.000 $2.000 $3.750 $5.000
REFL PAV MRKR TY II-C-R
EA 25.000 $20.000 $27.000 $27.500 $25.000 $25.000 $2.000 $30.000 $2.300 $12.000 $10.000 $22.000 $30.000 $500.000 $31.250 $30.000
DRAIN INLET CLEANING
EA 16.000 $400.000 $250.000 $400.000 $450.000 $1.000 $160.000 $1,500.000 $100.000 $175.000 $201.000 $500.000 $2,590.000 $786.440 $6,250.000 $1,000.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 200.000 $75.000 $41.000 $35.000 $25.000 $75.000 $45.000 $100.000 $50.000 $37.000 $81.000 $100.000 $60.000 $139.000 $143.750 $150.000
CNC CRACK REPAIR (DISCRETE)(SURF SEAL)
LF 265.000 $100.000 $41.000 $30.000 $25.000 $75.000 $45.000 $85.000 $50.000 $40.000 $80.000 $80.000 $75.000 $115.000 $131.250 $150.000
REP STL BRIDGE MEMBER (BEARINGS)
EA 26.000 $4,000.000 $1,200.000 $100.000 $1,000.000 $1.000 $1.000 $3,000.000 $1,000.000 $1.000 $1.000 $3,200.000 $6,800.000 $2,974.000 $1,875.000 $4,500.000
BENT CAP/ABUTMENT CAP CLEANING
EA 33.000 $1,000.000 $425.000 $300.000 $850.000 $825.000 $350.000 $1,000.000 $1,000.000 $550.000 $725.000 $1,000.000 $500.000 $2,570.000 $2,500.000 $850.000
Totals: $5,992,792.400 $4,004,004.000 $4,165,431.800 $4,206,128.000 $4,239,303.000 $4,389,566.500 $4,417,691.000 $4,763,758.150 $4,889,399.000 $5,100,340.000 $5,257,325.000 $5,355,257.000 $5,492,019.040 $5,608,891.250 $7,360,057.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $125,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $135,000.00