PREPARING ROW
|
AC
|
9.900
|
$6,000.000
|
$3,500.000
|
$50,505.000
|
$5,000.000
|
$11,500.000
|
$14,094.940
|
$20,000.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
154.000
|
$30.000
|
$52.000
|
$20.000
|
$40.000
|
$25.000
|
$6.150
|
$50.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
1,293.000
|
$30.000
|
$40.000
|
$20.000
|
$40.000
|
$25.000
|
$12.280
|
$40.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
523.000
|
$20.000
|
$45.000
|
$20.000
|
$40.000
|
$25.000
|
$24.750
|
$40.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
321.000
|
$30.000
|
$52.000
|
$20.000
|
$40.000
|
$25.000
|
$19.230
|
$20.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
3,099.000
|
$13.000
|
$7.750
|
$20.000
|
$20.000
|
$10.000
|
$16.320
|
$10.000
|
|
|
REMOVING STAB BASE & ASPH PAV (9")
|
SY
|
1,849.000
|
$10.000
|
$27.000
|
$20.000
|
$30.000
|
$15.000
|
$4.620
|
$6.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-8")
|
SY
|
4,020.000
|
$8.000
|
$12.000
|
$20.000
|
$20.000
|
$12.000
|
$4.430
|
$8.000
|
|
|
OBLITERATING ABANDONED ROAD
|
SY
|
891.000
|
$20.000
|
$14.000
|
$35.000
|
$20.000
|
$22.000
|
$7.200
|
$30.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
147.000
|
$25.000
|
$33.000
|
$30.000
|
$20.000
|
$65.000
|
$19.730
|
$60.000
|
|
|
EMBANKMENT (ORIGINAL)(ORD COMP)(TY B)
|
CY
|
2,278.000
|
$30.000
|
$20.000
|
$35.000
|
$40.000
|
$35.000
|
$49.330
|
$50.000
|
|
|
BLOCK SODDING
|
SY
|
33,086.000
|
$3.500
|
$4.000
|
$4.000
|
$10.000
|
$4.550
|
$5.290
|
$9.000
|
|
|
STRAW OR HAY MULCH
|
SY
|
33,086.000
|
$0.250
|
$0.450
|
$0.600
|
$0.250
|
$0.410
|
$0.540
|
$0.250
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
33,086.000
|
$0.250
|
$0.200
|
$0.600
|
$0.500
|
$0.200
|
$0.540
|
$0.550
|
|
|
VEGETATIVE WATERING
|
MG
|
1,640.000
|
$35.000
|
$5.000
|
$35.000
|
$20.000
|
$65.000
|
$39.470
|
$80.000
|
|
|
SUPERPAVE MIXTURES SP-B PG64-22
|
TON
|
244.900
|
$250.000
|
$150.000
|
$200.000
|
$150.000
|
$185.000
|
$211.420
|
$270.000
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
|
TON
|
45.900
|
$250.000
|
$155.000
|
$200.000
|
$150.000
|
$250.000
|
$211.420
|
$1,000.000
|
|
|
TACK COAT
|
GAL
|
55.700
|
$20.000
|
$40.000
|
$10.000
|
$5.000
|
$10.000
|
$21.140
|
$190.000
|
|
|
CONC PVMT (CONT REINF)(FAST TRK)(13")
|
SY
|
1,512.000
|
$80.000
|
$110.000
|
$150.000
|
$150.000
|
$325.000
|
$169.140
|
$260.000
|
|
|
CEM STABIL BKFL
|
CY
|
80.200
|
$170.000
|
$200.000
|
$350.000
|
$240.000
|
$200.000
|
$102.790
|
$400.000
|
|
|
CUT & RESTORING PAV
|
SY
|
18.000
|
$120.000
|
$195.000
|
$200.000
|
$120.000
|
$175.000
|
$108.070
|
$500.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
295.000
|
$25.000
|
$20.000
|
$10.000
|
$50.000
|
$10.000
|
$3.970
|
$20.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
944.000
|
$40.000
|
$20.000
|
$65.000
|
$40.000
|
$80.000
|
$36.730
|
$190.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
572.000
|
$150.000
|
$145.000
|
$185.000
|
$250.000
|
$185.000
|
$352.370
|
$280.000
|
|
|
DRILL SHAFT (30 IN)
|
LF
|
776.000
|
$170.000
|
$185.000
|
$250.000
|
$300.000
|
$275.000
|
$458.090
|
$300.000
|
|
|
CL C CONC (ABUT)(HPC)(EXTEND)
|
CY
|
47.200
|
$1,500.000
|
$1,050.000
|
$1,500.000
|
$3,000.000
|
$1,400.000
|
$2,512.760
|
$10,000.000
|
|
|
CL C CONC (CAP)(HPC)(EXTEND)
|
CY
|
48.400
|
$3,500.000
|
$1,050.000
|
$1,500.000
|
$3,000.000
|
$1,400.000
|
$2,442.080
|
$5,000.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
40.800
|
$1,400.000
|
$1,050.000
|
$1,500.000
|
$3,000.000
|
$1,400.000
|
$2,114.240
|
$6,000.000
|
|
|
BRIDGE SIDEWALK (HPC)
|
SF
|
10,155.000
|
$10.000
|
$20.000
|
$25.000
|
$20.000
|
$18.000
|
$16.910
|
$20.000
|
|
|
APPROACH SLAB (EXTEND) (HPC)
|
CY
|
73.600
|
$700.000
|
$350.000
|
$1,500.000
|
$750.000
|
$1,000.000
|
$1,691.390
|
$3,000.000
|
|
|
REINF CONC SLAB(SLAB BEAM)(EXT SLAB)HPC
|
SF
|
7,301.000
|
$33.000
|
$20.000
|
$20.000
|
$30.000
|
$28.000
|
$70.470
|
$30.000
|
|
|
RETAINING WALL (SPREAD FOOTING)
|
SF
|
256.000
|
$75.000
|
$150.000
|
$50.000
|
$120.000
|
$140.000
|
$169.140
|
$300.000
|
|
|
PRESTR CONC SLAB BEAM (4SB12)
|
LF
|
1,339.000
|
$155.000
|
$155.000
|
$165.000
|
$200.000
|
$155.000
|
$317.140
|
$230.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
357.250
|
$210.000
|
$195.000
|
$165.000
|
$240.000
|
$200.000
|
$352.370
|
$220.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
729.000
|
$162.000
|
$145.000
|
$350.000
|
$200.000
|
$175.000
|
$255.920
|
$140.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
4.000
|
$480.000
|
$300.000
|
$650.000
|
$500.000
|
$675.000
|
$566.690
|
$2,000.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
193.000
|
$540.000
|
$300.000
|
$650.000
|
$600.000
|
$700.000
|
$595.120
|
$1,000.000
|
|
|
RIPRAP (CONC)(CL B)(RR8&RR9)
|
CY
|
96.500
|
$500.000
|
$400.000
|
$650.000
|
$600.000
|
$750.000
|
$643.240
|
$1,000.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
28.000
|
$300.000
|
$120.000
|
$285.000
|
$300.000
|
$250.000
|
$239.610
|
$400.000
|
|
|
RIPRAP (SPECIAL)
|
CY
|
100.000
|
$680.000
|
$600.000
|
$1,000.000
|
$600.000
|
$750.000
|
$916.170
|
$1,000.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
49.000
|
$520.000
|
$325.000
|
$450.000
|
$500.000
|
$725.000
|
$599.090
|
$1,000.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
3,362.000
|
$20.000
|
$10.000
|
$20.000
|
$20.000
|
$18.000
|
$35.240
|
$20.000
|
|
|
RAIL (TY C402)
|
LF
|
148.000
|
$110.000
|
$200.000
|
$185.000
|
$200.000
|
$250.000
|
$123.050
|
$300.000
|
|
|
RAIL (TY C402)(HPC)
|
LF
|
934.400
|
$150.000
|
$205.000
|
$210.000
|
$500.000
|
$250.000
|
$289.450
|
$250.000
|
|
|
RAIL (HANDRAIL)(TY E)
|
LF
|
182.000
|
$100.000
|
$120.000
|
$185.000
|
$300.000
|
$200.000
|
$220.600
|
$180.000
|
|
|
CONC BOX CULV (7 FT X 3 FT)
|
LF
|
8.000
|
$500.000
|
$1,900.000
|
$750.000
|
$1,500.000
|
$1,000.000
|
$1,057.120
|
$2,000.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
14.000
|
$660.000
|
$1,500.000
|
$1,000.000
|
$1,200.000
|
$1,000.000
|
$845.700
|
$3,000.000
|
|
|
CONC BOX CULV (8 FT X 8 FT)(EXTEND)
|
LF
|
24.000
|
$1,000.000
|
$2,000.000
|
$1,500.000
|
$2,500.000
|
$1,300.000
|
$2,114.240
|
$2,000.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
249.000
|
$90.000
|
$150.000
|
$85.000
|
$200.000
|
$185.000
|
$126.850
|
$190.000
|
|
|
INLET (COMPL)(PCO)(4FT)(NONE)
|
EA
|
2.000
|
$4,500.000
|
$6,500.000
|
$6,500.000
|
$4,000.000
|
$8,000.000
|
$7,752.220
|
$9,000.000
|
|
|
INLET(COMPL)(CURB)(SPL)
|
EA
|
24.000
|
$5,000.000
|
$3,500.000
|
$6,500.000
|
$8,000.000
|
$8,000.000
|
$21,142.410
|
$11,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
1.000
|
$5,650.000
|
$6,500.000
|
$3,500.000
|
$7,500.000
|
$5,000.000
|
$8,549.480
|
$18,000.000
|
|
|
WINGWALL (PW - 1) (HW=10 FT)
|
EA
|
2.000
|
$30,000.000
|
$15,000.000
|
$25,000.000
|
$45,000.000
|
$40,000.000
|
$63,707.660
|
$22,000.000
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
4.000
|
$14,400.000
|
$15,000.000
|
$15,000.000
|
$25,000.000
|
$14,000.000
|
$19,936.310
|
$17,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$1,200.000
|
$15,000.000
|
$2,200.000
|
$2,500.000
|
$2,500.000
|
$2,231.250
|
$7,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$1,400.000
|
$2,000.000
|
$2,500.000
|
$2,000.000
|
$2,500.000
|
$2,562.720
|
$4,000.000
|
|
|
ADJUSTING MANHOLES (SANITARY)
|
EA
|
1.000
|
$2,500.000
|
$1,200.000
|
$1,500.000
|
$1,000.000
|
$1,000.000
|
$2,677.600
|
$2,000.000
|
|
|
ADJUSTING MANHOLES (WATER VALVE BOX)
|
EA
|
16.000
|
$500.000
|
$1,000.000
|
$750.000
|
$500.000
|
$1,000.000
|
$1,170.620
|
$1,000.000
|
|
|
REMOV STR (INLET)
|
EA
|
2.000
|
$660.000
|
$750.000
|
$1,500.000
|
$800.000
|
$900.000
|
$838.850
|
$3,000.000
|
|
|
REMOV STR (SET)
|
EA
|
8.000
|
$450.000
|
$400.000
|
$500.000
|
$800.000
|
$700.000
|
$1,429.860
|
$2,000.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
4.000
|
$1,500.000
|
$4,500.000
|
$2,500.000
|
$1,500.000
|
$1,800.000
|
$1,825.280
|
$3,000.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$1,100.000
|
$3,000.000
|
$2,500.000
|
$1,200.000
|
$1,500.000
|
$1,718.470
|
$3,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
170.000
|
$17.000
|
$25.000
|
$30.000
|
$20.000
|
$25.000
|
$20.440
|
$80.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
1,058.000
|
$15.500
|
$25.000
|
$30.000
|
$5.000
|
$25.000
|
$29.050
|
$30.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$452,000.000
|
$170,000.100
|
$700,000.000
|
$500,000.000
|
$625,000.000
|
$775,221.860
|
$943,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$7,200.000
|
$5,500.000
|
$8,500.000
|
$9,500.000
|
$7,500.000
|
$21,142.410
|
$5,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
660.000
|
$28.500
|
$28.000
|
$30.000
|
$30.000
|
$47.000
|
$38.760
|
$60.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
660.000
|
$12.000
|
$7.000
|
$15.000
|
$10.000
|
$14.000
|
$11.280
|
$30.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
8,213.000
|
$3.500
|
$2.400
|
$4.000
|
$3.000
|
$3.500
|
$3.660
|
$3.750
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
8,213.000
|
$1.500
|
$0.600
|
$2.000
|
$1.000
|
$1.000
|
$0.820
|
$0.750
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
160.000
|
$6.000
|
$5.000
|
$18.000
|
$5.000
|
$25.000
|
$8.460
|
$10.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
160.000
|
$1.250
|
$5.000
|
$12.000
|
$1.000
|
$15.750
|
$5.640
|
$8.000
|
|
|
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
|
LF
|
398.000
|
$8.000
|
$15.000
|
$30.000
|
$15.000
|
$25.000
|
$28.190
|
$40.000
|
|
|
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$12.500
|
$15.000
|
$30.000
|
$15.000
|
$25.000
|
$28.190
|
$50.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
684.000
|
$10.000
|
$10.000
|
$30.000
|
$15.000
|
$15.000
|
$8.690
|
$30.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$15.000
|
$15.000
|
$30.000
|
$15.000
|
$15.000
|
$14.920
|
$30.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
398.000
|
$7.000
|
$15.000
|
$30.000
|
$15.000
|
$22.000
|
$13.530
|
$7.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$8.000
|
$12.000
|
$30.000
|
$15.000
|
$22.000
|
$15.590
|
$10.000
|
|
|
CONC CURB (MONO) (TY II)
|
LF
|
936.000
|
$5.500
|
$25.000
|
$35.000
|
$20.000
|
$25.000
|
$5.760
|
$30.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
4,529.000
|
$20.000
|
$15.000
|
$35.000
|
$25.000
|
$28.000
|
$33.690
|
$50.000
|
|
|
CONC CURB (SLOTTED)
|
LF
|
590.000
|
$25.000
|
$25.000
|
$50.000
|
$45.000
|
$30.000
|
$14.090
|
$70.000
|
|
|
CONC CURB (DOWEL) (TY II)
|
LF
|
260.000
|
$25.000
|
$25.000
|
$30.000
|
$30.000
|
$32.000
|
$50.970
|
$60.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
2,791.000
|
$80.000
|
$65.000
|
$85.000
|
$120.000
|
$155.000
|
$98.130
|
$130.000
|
|
|
CONC SIDEWALKS (5")
|
SY
|
9,104.000
|
$51.000
|
$56.500
|
$55.000
|
$80.000
|
$115.000
|
$71.910
|
$120.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
25.000
|
$1,700.000
|
$1,250.000
|
$2,000.000
|
$1,500.000
|
$1,900.000
|
$2,277.460
|
$3,000.000
|
|
|
CURB RAMPS (TY 2)
|
EA
|
6.000
|
$1,800.000
|
$2,000.000
|
$2,000.000
|
$1,500.000
|
$1,900.000
|
$2,210.780
|
$3,000.000
|
|
|
CURB RAMPS (TY 3)
|
EA
|
2.000
|
$1,600.000
|
$2,000.000
|
$2,000.000
|
$1,600.000
|
$2,700.000
|
$2,509.110
|
$3,000.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
2.000
|
$1,750.000
|
$2,000.000
|
$2,000.000
|
$1,800.000
|
$2,500.000
|
$2,409.900
|
$3,000.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
15.000
|
$1,800.000
|
$2,200.000
|
$2,000.000
|
$2,100.000
|
$2,850.000
|
$2,371.420
|
$3,000.000
|
|
|
CURB RAMPS (TY 22)
|
EA
|
4.000
|
$2,800.000
|
$2,000.000
|
$2,000.000
|
$3,000.000
|
$2,800.000
|
$3,964.540
|
$8,000.000
|
|
|
CONC DIRECTIONAL ISLAND
|
SY
|
66.000
|
$75.000
|
$70.000
|
$125.000
|
$125.000
|
$115.000
|
$174.900
|
$300.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
400.000
|
$23.000
|
$20.000
|
$25.000
|
$30.000
|
$26.000
|
$29.670
|
$40.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,100.000
|
$1,800.000
|
$1,850.000
|
$2,000.000
|
$2,400.000
|
$2,592.920
|
$4,000.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,200.000
|
$1,600.000
|
$1,850.000
|
$1,400.000
|
$1,800.000
|
$1,603.570
|
$2,000.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
517.000
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
$4.000
|
$3.650
|
$7.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$275.000
|
$1,500.000
|
$500.000
|
$250.000
|
$360.000
|
$325.950
|
$1,000.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$2,800.000
|
$3,000.000
|
$3,000.000
|
$3,000.000
|
$3,600.000
|
$3,824.650
|
$4,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$300.000
|
$500.000
|
$1,500.000
|
$300.000
|
$360.000
|
$408.960
|
$1,000.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
4.000
|
$450.000
|
$500.000
|
$650.000
|
$500.000
|
$540.000
|
$627.970
|
$1,000.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
470.000
|
$12.300
|
$30.000
|
$12.000
|
$10.000
|
$36.000
|
$10.530
|
$50.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
475.000
|
$29.000
|
$60.000
|
$40.000
|
$30.000
|
$70.000
|
$30.080
|
$90.000
|
|
|
CONDT (PVC) (SCH 80) (4")
|
LF
|
55.000
|
$50.000
|
$40.000
|
$20.000
|
$20.000
|
$48.000
|
$22.260
|
$60.000
|
|
|
CONDT (PVC) (SCH 80) (4") (BORE)
|
LF
|
975.000
|
$40.000
|
$70.000
|
$40.000
|
$50.000
|
$84.000
|
$34.830
|
$110.000
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
1,930.000
|
$1.500
|
$1.750
|
$3.000
|
$1.000
|
$2.100
|
$1.850
|
$2.750
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
95.000
|
$2.500
|
$2.000
|
$3.000
|
$1.000
|
$2.400
|
$2.310
|
$3.250
|
|
|
TRAY CABLE (3 CONDR) (8 AWG)
|
LF
|
155.000
|
$10.000
|
$7.000
|
$3.000
|
$3.000
|
$8.400
|
$4.380
|
$10.000
|
|
|
GROUND BOX TY C (162911)W/APRON
|
EA
|
17.000
|
$1,200.000
|
$1,800.000
|
$650.000
|
$1,000.000
|
$2,100.000
|
$1,553.560
|
$3,000.000
|
|
|
REMOVE GROUND BOX
|
EA
|
11.000
|
$336.000
|
$500.000
|
$550.000
|
$200.000
|
$600.000
|
$431.290
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
26.000
|
$520.000
|
$500.000
|
$650.000
|
$500.000
|
$900.000
|
$683.590
|
$2,000.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
3.000
|
$940.000
|
$500.000
|
$650.000
|
$600.000
|
$960.000
|
$735.500
|
$3,000.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
8.000
|
$750.000
|
$500.000
|
$450.000
|
$400.000
|
$720.000
|
$1,035.710
|
$2,000.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$740.000
|
$500.000
|
$450.000
|
$400.000
|
$780.000
|
$721.530
|
$2,000.000
|
|
|
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
|
EA
|
4.000
|
$350.000
|
$500.000
|
$450.000
|
$400.000
|
$120.000
|
$246.750
|
$1,000.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
29.000
|
$80.000
|
$80.000
|
$150.000
|
$90.000
|
$125.000
|
$135.420
|
$120.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
24.000
|
$37.000
|
$100.000
|
$100.000
|
$30.000
|
$25.000
|
$27.850
|
$30.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
20.000
|
$68.000
|
$100.000
|
$100.000
|
$70.000
|
$100.000
|
$86.370
|
$130.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
12.000
|
$38.000
|
$50.000
|
$100.000
|
$30.000
|
$45.000
|
$36.170
|
$30.000
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
112.000
|
$2.500
|
$5.000
|
$5.000
|
$2.000
|
$9.000
|
$1.610
|
$4.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
311.000
|
$0.500
|
$5.000
|
$5.000
|
$0.500
|
$4.200
|
$0.420
|
$3.000
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
1,873.000
|
$12.000
|
$12.000
|
$30.000
|
$15.000
|
$20.000
|
$17.460
|
$20.000
|
|
PREFAB PAV MRK TY C (W)(BIKE ARROW)
|
EA
|
7.000
|
$120.000
|
$500.000
|
$1,000.000
|
$300.000
|
$186.000
|
$302.280
|
$300.000
|
|
PREFAB PAV MRK TY C (W)(BIKE SYMBOL)
|
EA
|
7.000
|
$210.000
|
$500.000
|
$1,000.000
|
$300.000
|
$252.000
|
$416.620
|
$1,000.000
|
|
|
PAV SURF PREP FOR MRK (BIKE ARROW)
|
EA
|
7.000
|
$15.000
|
$500.000
|
$1,000.000
|
$5.000
|
$102.000
|
$6.200
|
$100.000
|
|
|
PAV SURF PREP FOR MRK (BIKE SYMBOL)
|
EA
|
7.000
|
$10.000
|
$500.000
|
$1,000.000
|
$6.000
|
$102.000
|
$7.130
|
$100.000
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
1.000
|
$24,000.000
|
$45,000.000
|
$35,000.000
|
$25,000.000
|
$54,000.000
|
$32,653.220
|
$71,000.000
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
6.000
|
$227.000
|
$250.000
|
$285.000
|
$250.000
|
$300.000
|
$323.650
|
$400.000
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
8.000
|
$217.000
|
$250.000
|
$285.000
|
$250.000
|
$300.000
|
$319.620
|
$400.000
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
6.000
|
$229.000
|
$250.000
|
$285.000
|
$250.000
|
$300.000
|
$333.770
|
$400.000
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
32.000
|
$563.000
|
$650.000
|
$1,850.000
|
$800.000
|
$780.000
|
$783.120
|
$1,000.000
|
|
|
BACK PLATE (12")(3 SEC)
|
EA
|
4.000
|
$80.000
|
$75.000
|
$125.000
|
$90.000
|
$90.000
|
$120.410
|
$120.000
|
|
|
BACK PLATE (12")(4 SEC)
|
EA
|
2.000
|
$95.000
|
$80.000
|
$150.000
|
$100.000
|
$100.000
|
$130.050
|
$130.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
|
LF
|
8,835.000
|
$6.500
|
$4.000
|
$3.000
|
$1.000
|
$4.800
|
$3.240
|
$6.000
|
|
|
PED POLE ASSEMBLY
|
EA
|
20.000
|
$2,000.000
|
$3,200.000
|
$2,850.000
|
$2,500.000
|
$4,000.000
|
$2,891.380
|
$5,000.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
38.000
|
$800.000
|
$1,100.000
|
$1,850.000
|
$800.000
|
$1,300.000
|
$1,076.290
|
$2,000.000
|
|
|
REMOVE TRAFFIC SIGNAL
|
EA
|
1.000
|
$1,600.000
|
$1,000.000
|
$6,500.000
|
$2,500.000
|
$1,200.000
|
$3,523.740
|
$2,000.000
|
|
|
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
|
LF
|
990.000
|
$50.000
|
$15.000
|
$100.000
|
$50.000
|
$30.000
|
$95.140
|
$40.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$13,300.000
|
$17,000.000
|
$16,500.000
|
$14,000.000
|
$15,000.000
|
$11,893.860
|
$30,000.000
|
|
|
GROUND BOX W/ APRON (ADJUST)
|
EA
|
4.000
|
$1,000.000
|
$1,800.000
|
$650.000
|
$500.000
|
$2,160.000
|
$663.790
|
$3,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
211.000
|
$200.000
|
$100.000
|
$450.000
|
$300.000
|
$250.000
|
$704.750
|
$1,000.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
10.000
|
$180.000
|
$250.000
|
$850.000
|
$300.000
|
$500.000
|
$775.220
|
$2,000.000
|
|
|
VIVDS PROSR SYS
|
EA
|
1.000
|
$11,000.000
|
$8,000.000
|
$8,500.000
|
$8,000.000
|
$10,000.000
|
$9,747.360
|
$13,000.000
|
|
|
VIVDS CAM ASSY VAR LNS
|
EA
|
4.000
|
$3,400.000
|
$2,500.000
|
$8,000.000
|
$4,000.000
|
$3,000.000
|
$3,863.130
|
$4,000.000
|
|
|
VIVDS CNTRL SOFTWARE
|
EA
|
1.000
|
$1,100.000
|
$1,500.000
|
$8,000.000
|
$1,000.000
|
$1,800.000
|
$1,045.180
|
$2,000.000
|
|
|
VIVDS CABLING
|
LF
|
890.000
|
$3.250
|
$40.000
|
$3.000
|
$3.000
|
$4.800
|
$3.590
|
$6.000
|
|
Totals: |
$4,980,707.500
|
$4,596,548.000
|
$6,933,287.950
|
$6,992,425.500
|
$7,293,173.960
|
$8,270,837.200
|
$10,094,208.550
|