TAYLOR FM 18 (0006-10-011)

Items: 34

County: TAYLOR
Length: N/A
Highway: FM 18
District: ABILENE
Control Number: 0006-10-011
DBE Goal: 0.0%
Project: F 2B24(019)
Guaranty: N/A
Time: 110 WORKING DAYS
Engineer's Estimate: $5,439,857.50
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,439,857.50
$4,570,547.00
Over/Under Est: -15.98% -$869,310.50
Over/Under Est: -5.45% -$296,242.10
Amt Left: 12.54% $573,068.40
Over/Under Est: 4.03% $219,087.70
Amt Left: 23.81% $1,088,398.20
Delta: -10.02% -$515,329.80
$6,981,176.00
Over/Under Est: 28.33% $1,541,318.50
Amt Left: 52.74% $2,410,629.00
Delta: -23.37% -$1,322,230.80
Subcontractor Percentage Amount
HJC FARMS, INC. 5.98% $273,318.71
FLAT LINE, INC. 2.61% $119,291.28
PROFESSIONAL TRAFFIC CONTROL LLC 0.41% $18,739.24
CONTRACTORS SERVICE, LTD. 0.36% $16,453.97
Total: 9.36% $427,803.20

Bid Items & Bid Tabulations

34 Total 0 of 34
TAYLOR  |  FM 18  |  ABILENE  |  0006-10-011  |  05/02/2024  |  $5,439,857.50  |  F 2B24(019)  |  REHAB EXIST ROADWAY  |  110 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
FOUTSCO PAVING COMPANY, LLC
BONTKE BROTHERS CONSTRUCTION COMPANY
CK NEWBERRY, LLC
BACKFILL (TY A)
STA 403.140 $500.000 $350.000 $150.000 $900.000 $700.000
BACKFILL (TY B)
STA 34.970 $500.000 $350.000 $150.000 $1,500.000 $500.000
PRIME COAT (AE-P)
GAL 2,466.000 $9.000 $8.000 $0.100 $12.000 $10.000
PLANE ASPH CONC PAV(0" TO 2")
SY 6,914.000 $6.000 $7.000 $1.500 $8.000 $7.000
PLANE ASPH CONC PAV (2")
SY 400.000 $6.000 $10.000 $8.000 $8.000 $20.000
PLANE ASPH CONC PAV (4")
SY 11,836.000 $10.000 $5.000 $4.000 $12.000 $6.000
MOBILIZATION
LS 1.000 $490,000.000 $440,000.000 $500,000.000 $680,000.000 $650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $20,000.000 $15,000.000 $25,000.000 $8,000.000 $25,000.000
RUMBLE STRIPS (SHOULDER)
LF 80,628.000 $0.500 $0.310 $0.150 $1.000 $0.500
RUMBLE STRIPS (CENTERLINE)
LF 33,376.000 $0.500 $0.390 $0.150 $1.000 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 4,300.000 $30.000 $26.000 $22.000 $55.000 $50.000
MTL BEAM GD FEN TRANS (T6)
EA 4.000 $2,500.000 $965.000 $1,000.000 $3,500.000 $1,100.000
REMOVE METAL BEAM GUARD FENCE
LF 4,300.000 $2.500 $2.250 $3.000 $5.000 $3.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $300.000 $227.000 $200.000 $1,500.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $3,700.000 $3,460.000 $3,000.000 $4,500.000 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $300.000 $227.000 $300.000 $1,000.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 53.000 $40.000 $40.000 $12.000 $50.000 $50.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 55.000 $5.000 $5.000 $5.000 $0.500 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,913.000 $5.000 $2.750 $1.000 $0.500 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,077.000 $2.000 $1.250 $1.000 $1.500 $2.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 91,414.000 $0.500 $0.620 $0.500 $0.700 $1.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 21,981.000 $0.500 $0.620 $0.500 $0.700 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 71,746.000 $0.500 $0.620 $0.500 $0.700 $1.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 268.000 $35.000 $22.750 $20.000 $23.000 $20.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $775.000 $284.000 $250.000 $350.000 $400.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 3.000 $800.000 $340.000 $300.000 $350.000 $550.000
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $575.000 $340.000 $300.000 $350.000 $500.000
REFL PAV MRKR TY I-C
EA 54.000 $4.000 $5.700 $5.000 $6.000 $12.000
REFL PAV MRKR TY II-A-A
EA 1,282.000 $4.000 $4.550 $4.000 $6.000 $6.000
SP MIXES SP-C SAC-B PG70-22
TON 24,226.000 $155.000 $131.610 $156.000 $138.000 $196.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 388.000 $155.000 $200.000 $195.000 $136.000 $200.000
TACK COAT
GAL 20,839.000 $6.000 $3.000 $8.800 $10.000 $10.000
TMA (STATIONARY)
DAY 96.000 $350.000 $300.000 $1.000 $250.000 $750.000
TMA (MOBILE OPERATION)
DAY 12.000 $350.000 $300.000 $1.000 $500.000 $750.000
Totals: $5,439,857.500 $4,570,547.000 $5,143,615.400 $5,658,945.200 $6,981,176.000