MOBILIZATION (CALLOUT)
|
EA
|
20.000
|
$2,500.000
|
$10,149.500
|
|
|
MOBILIZATION (EMERGENCY)
|
EA
|
12.000
|
$1,900.000
|
$5,500.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
20.000
|
$150.000
|
$100.000
|
|
|
TMA (STATIONARY)
|
DAY
|
20.000
|
$500.000
|
$400.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
100.000
|
$2.000
|
$25.000
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
100.000
|
$9.000
|
$28.000
|
|
|
CONDT (PVC) (SCH 40) (4")
|
LF
|
100.000
|
$25.000
|
$28.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
5,000.000
|
$3.500
|
$3.000
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
40.000
|
$1,600.000
|
$1,900.000
|
|
RE PM TY I (W)4"(BRK)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
RE PM TY I (W)4"(SLD)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
RE PM TY I (W)4"(DOT)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
RE PM TY I (W)6"(BRK)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.500
|
$3.600
|
|
RE PM TY I (W)6"(SLD)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.500
|
$3.600
|
|
RE PM TY I (W)8"(SLD)(090MIL)(CALLOUT)
|
LF
|
200.000
|
$2.000
|
$4.800
|
|
RE PM TY I(W)12"(SLD)(090MIL)(CALLOUT)
|
LF
|
200.000
|
$4.000
|
$9.600
|
|
RE PM TY I(W)24"(SLD)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$9.000
|
$23.900
|
|
RE PM TY I (W)(ARROW)(090MIL)(CALLOUT)
|
EA
|
10.000
|
$210.000
|
$388.000
|
|
RE PM TY I(W)(DBL ARW)(090MIL)(CALLOUT)
|
EA
|
10.000
|
$400.000
|
$626.800
|
|
RE PM TY I(W)(RR XING)(090MIL)(CALLOUT)
|
EA
|
10.000
|
$70.000
|
$1,223.700
|
|
RE PM TY I (W)(WORD)(090MIL)(CALLOUT)
|
EA
|
10.000
|
$220.000
|
$567.100
|
|
RE PM TY I (Y)4"(BRK)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
RE PM TY I (Y)4"(SLD)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
RE PM TY I (Y)8"(SLD)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$1.500
|
$4.800
|
|
RE PM TY I (Y)24"(SLD)(090MIL)(CALLOUT)
|
LF
|
500.000
|
$9.000
|
$23.900
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
500.000
|
$1.000
|
$1.200
|
|
|
ELIM EXT PM & MRKS (8")
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
|
ELIM EXT PM & MRKS (12")
|
LF
|
500.000
|
$2.000
|
$3.600
|
|
|
ELIM EXT PM & MRKS (24")
|
LF
|
500.000
|
$4.000
|
$7.200
|
|
|
ELIM EXT PM & MRKS (ARROW)
|
EA
|
10.000
|
$35.000
|
$179.100
|
|
|
ELIM EXT PM & MRKS (DBL ARROW)
|
EA
|
10.000
|
$70.000
|
$268.600
|
|
|
ELIM EXT PM & MRKS (WORD)
|
EA
|
10.000
|
$40.000
|
$238.800
|
|
|
ELIM EXT PM & MRKS (18")(YLD TRI)
|
EA
|
30.000
|
$10.000
|
$119.400
|
|
|
ELIM EXT PM & MRKS (36")(YLD TRI)
|
EA
|
30.000
|
$18.000
|
$143.300
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
500.000
|
$1.000
|
$1.200
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
500.000
|
$1.000
|
$2.400
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
500.000
|
$1.000
|
$7.200
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
10.000
|
$10.000
|
$119.400
|
|
|
PAV SURF PREP FOR MRK (DBL ARROW)
|
EA
|
10.000
|
$23.000
|
$238.800
|
|
|
PAV SURF PREP FOR MRK (UTURN ARR)
|
EA
|
10.000
|
$34.000
|
$179.100
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
10.000
|
$17.000
|
$209.000
|
|
|
PAV SURF PREP FOR MRK (18")(YLD TRI)
|
EA
|
30.000
|
$17.000
|
$89.600
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
30.000
|
$1.000
|
$119.400
|
|
|
REMOVAL OF GROUND BOXES
|
EA
|
40.000
|
$255.000
|
$300.000
|
|
|
REMOVAL OF CABLES
|
LF
|
3,000.000
|
$2.250
|
$2.000
|
|
|
REPLACE OF CABLES
|
LF
|
3,000.000
|
$7.650
|
$7.000
|
|
|
INSTALL OF CABLES
|
LF
|
3,000.000
|
$5.300
|
$7.000
|
|
|
REMOVAL OF SPAN CABLE ASSM
|
LF
|
3,000.000
|
$3.450
|
$1.000
|
|
|
REPLACE OF SPAN CABLE ASSM
|
LF
|
3,000.000
|
$3.700
|
$6.000
|
|
|
INSTALL OF SPAN CABLE ASSM
|
LF
|
3,000.000
|
$7.000
|
$6.000
|
|
|
REPLACE OF ELECTRICAL SERVICE
|
EA
|
6.000
|
$7,400.000
|
$11,000.000
|
|
|
INSTALL OF ELECTRICAL SERVICE
|
EA
|
12.000
|
$6,200.000
|
$11,000.000
|
|
|
REMOVAL OF TIMBER POLES
|
EA
|
16.000
|
$460.000
|
$200.000
|
|
|
INSTALL OF TIMBER POLES
|
EA
|
16.000
|
$1,170.000
|
$2,000.000
|
|
|
REPLACE OF SIGNAL RELATED SIGNS
|
EA
|
40.000
|
$360.000
|
$500.000
|
|
|
INSTALL OF SIGNAL RELATED SIGNS
|
EA
|
40.000
|
$370.000
|
$500.000
|
|
|
REMOVAL OF PEDESTRIAN PUSH BUTTONS
|
EA
|
60.000
|
$170.000
|
$50.000
|
|
|
REPLACE OF PEDESTRIAN PUSH BUTTONS
|
EA
|
60.000
|
$630.000
|
$600.000
|
|
|
INSTALL OF PEDESTRIAN PUSH BUTTONS
|
EA
|
60.000
|
$490.000
|
$600.000
|
|
|
REMOVAL OF TRAFFIC SIGNAL POLE FND
|
LF
|
10.000
|
$935.000
|
$300.000
|
|
|
REPLACE OF CONTROL CABINET(GRND MNT)
|
EA
|
10.000
|
$9,520.000
|
$8,000.000
|
|
|
INSTALL OF CONTROL CABINET(GRND MNT)
|
EA
|
10.000
|
$8,500.000
|
$8,000.000
|
|
|
REMOVAL OF CONTROL CABINET(POLE MNT)
|
EA
|
10.000
|
$1,100.000
|
$900.000
|
|
|
REPLACE OF CONTROL CABINET(POLE MNT)
|
EA
|
10.000
|
$4,400.000
|
$6,000.000
|
|
|
INSTALL OF CONTROL CABINET(POLE MNT)
|
EA
|
10.000
|
$4,100.000
|
$6,000.000
|
|
|
REMOVAL OF FLASHER CABINET
|
EA
|
10.000
|
$430.000
|
$500.000
|
|
|
REPLACE OF FLASHER CABINET
|
EA
|
10.000
|
$1,880.000
|
$3,000.000
|
|
|
INSTALL OF FLASHER CABINET
|
EA
|
10.000
|
$1,340.000
|
$3,000.000
|
|
|
INSTALL OF FND FOR RDSD FLSH BEA ASSM
|
EA
|
20.000
|
$1,310.000
|
$2,000.000
|
|
|
REMOVAL OF RDSD FLSH BEACON ASSM
|
EA
|
20.000
|
$980.000
|
$1,100.000
|
|
|
REPLACE OF RDSD FLSH BEACON ASSM
|
EA
|
20.000
|
$2,560.000
|
$5,500.000
|
|
|
INSTALL OF RDSD FLSH BEACON ASSM
|
EA
|
20.000
|
$3,200.000
|
$5,500.000
|
|
|
REMOVAL OF SIGNAL POLE ASSM
|
EA
|
40.000
|
$1,790.000
|
$2,000.000
|
|
|
REPLACE OF SIGNAL POLE ASSM
|
EA
|
20.000
|
$3,720.000
|
$4,000.000
|
|
|
INSTALL OF SIGNAL POLE ASSM
|
EA
|
20.000
|
$3,400.000
|
$4,000.000
|
|
|
REMOVAL OF LUMINAIRE HEAD
|
EA
|
30.000
|
$165.000
|
$150.000
|
|
|
REPLACE OF LUMINAIRE HEAD
|
EA
|
30.000
|
$620.000
|
$500.000
|
|
|
INSTALL OF LUMINAIRE HEAD
|
EA
|
30.000
|
$335.000
|
$500.000
|
|
|
REPLACE OF LUMINAIRE MAST ARMS
|
EA
|
30.000
|
$680.000
|
$300.000
|
|
|
INSTALL OF LUMINAIRE MAST ARMS
|
EA
|
30.000
|
$440.000
|
$300.000
|
|
|
INS OF TRF SIG PL FND (24" DRIL SHFT)
|
LF
|
10.000
|
$700.000
|
$400.000
|
|
|
INS OF TRF SIG PL FND (30" DRIL SHFT)
|
LF
|
10.000
|
$490.000
|
$500.000
|
|
|
INS OF TRF SIG PL FND (36" DRIL SHFT)
|
LF
|
10.000
|
$700.000
|
$600.000
|
|
|
REMOVE VID IMAGE VEH DET SYS (VIVDS)
|
EA
|
20.000
|
$430.000
|
$1,000.000
|
|
|
INSTL PED POLE ASSM
|
EA
|
10.000
|
$1,810.000
|
$1,700.000
|
|
|
REPLACE PED POLE ASSM
|
EA
|
10.000
|
$1,940.000
|
$1,700.000
|
|
|
REMOVE PED POLE ASSM
|
EA
|
10.000
|
$960.000
|
$800.000
|
|
|
REPLACE PED SIG LED TRAF SIG LAMP UNIT
|
EA
|
20.000
|
$245.000
|
$300.000
|
|
|
REMOV PED SIG LED TRAF SIG LAMP UNIT
|
EA
|
20.000
|
$435.000
|
$10.000
|
|
|
INSTALL PED SGN LED TRAF SIG AMP UNIT
|
EA
|
20.000
|
$150.000
|
$200.000
|
|
|
REMOVE TRAFFIC SIGNAL
|
EA
|
10.000
|
$1,500.000
|
$7,200.000
|
|
|
TRF SIG HD(REPL)(3SEC)(LED)W/BRKT BKPL
|
EA
|
20.000
|
$860.000
|
$400.000
|
|
|
TRF SIG HD(REPL)(4SEC)(LED)W/BRKT BKPL
|
EA
|
20.000
|
$935.000
|
$500.000
|
|
|
TRF SIG HD(REPL)(5SEC)(LED)W/BRKT BKPL
|
EA
|
20.000
|
$1,100.000
|
$500.000
|
|
|
RELOCATE OF PEDESTRIAN PUSH BUTTON
|
EA
|
20.000
|
$400.000
|
$500.000
|
|
|
INSTALL PED POLE ASSM W/O FOUNDATION
|
EA
|
20.000
|
$1,250.000
|
$1,500.000
|
|
|
INSTALL LUMINAIRE POLE
|
EA
|
20.000
|
$4,200.000
|
$1,800.000
|
|
|
REPLACE LUMINAIRE POLE
|
EA
|
20.000
|
$4,430.000
|
$1,800.000
|
|
|
REMOVE LUMINAIRE POLE
|
EA
|
20.000
|
$1,225.000
|
$1,000.000
|
|
|
INSTALL SCREW-IN FND
|
EA
|
20.000
|
$1,180.000
|
$1,200.000
|
|
|
REMOVE SCREW-IN FND
|
EA
|
10.000
|
$290.000
|
$500.000
|
|
|
REPLACE CONTROLLER BREAKAWAY BASE
|
EA
|
20.000
|
$1,800.000
|
$2,500.000
|
|
|
INSTALL BBU SYSTEM
|
EA
|
20.000
|
$3,600.000
|
$1,800.000
|
|
|
INSTALL RADAR VEHICLE DETECTION SYSTEM
|
EA
|
20.000
|
$3,580.000
|
$2,000.000
|
|
|
REMOVE RADAR VEHICLE DETECTION SYSTEM
|
EA
|
30.000
|
$480.000
|
$600.000
|
|
|
REPLACE BBU BATTERY
|
EA
|
30.000
|
$640.000
|
$700.000
|
|
|
GROUND BOX (PREPARE)
|
EA
|
30.000
|
$510.000
|
$250.000
|
|
Totals: |
$1,967,200.000
|
$2,385,405.000
|