MOBILIZATION (CALLOUT)
|
EA
|
12.000
|
$3,863.350
|
$5,436.480
|
$1,500.000
|
|
|
MOBILIZATION (EMERGENCY)
|
EA
|
6.000
|
$2,340.990
|
$5,474.190
|
$2,800.000
|
|
|
BARR, SIGNS, TRAFFIC HANDLING
|
EA
|
12.000
|
$552.830
|
$2,146.930
|
$3,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
50.000
|
$3.400
|
$2.850
|
$2.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
50.000
|
$1.450
|
$1.510
|
$1.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
20.000
|
$13.570
|
$18.900
|
$14.000
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
40.000
|
$14.980
|
$19.660
|
$16.000
|
|
|
CONDT (PVC) (SCH 40) (3") (BORE)
|
LF
|
20.000
|
$24.700
|
$33.230
|
$34.000
|
|
|
CONDT (PVC) (SCH 40) (4")
|
LF
|
50.000
|
$16.730
|
$19.410
|
$17.000
|
|
|
CONDT (PVC) (SCH 40) (4") (BORE)
|
LF
|
40.000
|
$27.970
|
$33.640
|
$36.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
40.000
|
$17.410
|
$25.230
|
$32.000
|
|
|
CONDT (RM) (1 1/2")
|
LF
|
20.000
|
$22.070
|
$18.520
|
$25.000
|
|
|
CONDT (RM) (4")
|
LF
|
20.000
|
$64.360
|
$51.250
|
$100.000
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
3.000
|
$971.070
|
$1,148.400
|
$1,800.000
|
|
|
REMOVAL OF GROUND BOXES
|
EA
|
3.000
|
$302.540
|
$347.300
|
$200.000
|
|
|
REPLACE OF CABLES
|
LF
|
800.000
|
$13.120
|
$19.800
|
$6.000
|
|
|
INSTALL OF CABLES
|
LF
|
800.000
|
$12.620
|
$19.080
|
$4.000
|
|
|
REPLACE OF ELECTRICAL SERVICE
|
EA
|
2.000
|
$1,650.000
|
$5,450.980
|
$4,000.000
|
|
|
INSTALL OF ELECTRICAL SERVICE
|
EA
|
2.000
|
$3,000.000
|
$5,450.980
|
$3,500.000
|
|
|
REPLACE OF TIMBER POLES
|
EA
|
2.000
|
$1,662.750
|
$798.560
|
$1,500.000
|
|
|
INSTALL OF TIMBER POLES
|
EA
|
2.000
|
$1,178.650
|
$798.560
|
$1,100.000
|
|
|
REMOVAL OF SIGNAL HEAD ASSM
|
EA
|
2.000
|
$152.920
|
$166.880
|
$200.000
|
|
|
REPLACE OF SIGNAL HEAD ASSM
|
EA
|
2.000
|
$579.800
|
$483.280
|
$1,000.000
|
|
|
INSTALL OF SIGNAL HEAD ASSM
|
EA
|
2.000
|
$551.580
|
$546.000
|
$800.000
|
|
|
REMOVAL OF SIGNAL RELATED SIGNS
|
EA
|
2.000
|
$72.560
|
$85.960
|
$20.000
|
|
|
REPLACE OF SIGNAL RELATED SIGNS
|
EA
|
2.000
|
$284.170
|
$334.880
|
$330.000
|
|
|
INSTALL OF SIGNAL RELATED SIGNS
|
EA
|
2.000
|
$229.180
|
$334.880
|
$300.000
|
|
|
REPLACE OF PEDESTRIAN PUSH BUTTONS
|
EA
|
2.000
|
$172.920
|
$155.680
|
$300.000
|
|
|
INSTALL OF PEDESTRIAN PUSH BUTTONS
|
EA
|
2.000
|
$147.920
|
$408.800
|
$200.000
|
|
|
REMOVAL OF TRAFFIC SIGNAL POLE FND
|
LF
|
20.000
|
$424.140
|
$447.670
|
$230.000
|
|
|
INSTALL OF FND FOR GROUND MNT CABINETS
|
EA
|
2.000
|
$3,157.300
|
$2,611.730
|
$5,500.000
|
|
|
REPLACE OF CONTROL CABINET(GRND MNT)
|
EA
|
2.000
|
$6,278.120
|
$3,372.410
|
$9,000.000
|
|
|
INSTALL OF CONTROL CABINET(GRND MNT)
|
EA
|
2.000
|
$5,478.200
|
$3,372.410
|
$8,000.000
|
|
|
REPLACE OF CONTROL CABINET(POLE MNT)
|
EA
|
2.000
|
$5,978.200
|
$3,372.410
|
$9,000.000
|
|
|
INSTALL OF CONTROL CABINET(POLE MNT)
|
EA
|
2.000
|
$5,478.200
|
$3,372.410
|
$8,000.000
|
|
|
REPLACE OF FLASHER CABINET
|
EA
|
2.000
|
$1,769.730
|
$1,906.130
|
$750.000
|
|
|
INSTALL OF FLASHER CABINET
|
EA
|
2.000
|
$1,519.730
|
$1,906.130
|
$600.000
|
|
|
REPLACE OF RDSD FLSH BEACON ASSM
|
EA
|
2.000
|
$4,886.290
|
$6,004.210
|
$2,800.000
|
|
|
INSTALL OF RDSD FLSH BEACON ASSM
|
EA
|
2.000
|
$4,436.290
|
$6,004.210
|
$2,300.000
|
|
|
REMOVAL OF SIGNAL POLE ASSM
|
EA
|
2.000
|
$1,816.780
|
$2,666.610
|
$3,500.000
|
|
|
REPLACE OF SIGNAL POLE ASSM
|
EA
|
2.000
|
$2,754.550
|
$3,262.560
|
$5,000.000
|
|
|
INSTALL OF SIGNAL POLE ASSM
|
EA
|
2.000
|
$2,304.550
|
$3,262.560
|
$4,500.000
|
|
|
REPLACE OF LUMINAIRE HEAD
|
EA
|
4.000
|
$521.410
|
$425.600
|
$500.000
|
|
|
INSTALL OF LUMINAIRE HEAD
|
EA
|
4.000
|
$429.940
|
$405.440
|
$450.000
|
|
|
REPLACE OF LUMINAIRE MAST ARMS
|
EA
|
2.000
|
$649.360
|
$376.880
|
$700.000
|
|
|
INSTALL OF LUMINAIRE MAST ARMS
|
EA
|
2.000
|
$227.900
|
$293.440
|
$600.000
|
|
|
INS OF TRF SIG PL FND (24" DRIL SHFT)
|
LF
|
30.000
|
$205.830
|
$233.610
|
$350.000
|
|
|
INS OF TRF SIG PL FND (30" DRIL SHFT)
|
LF
|
10.000
|
$287.900
|
$271.210
|
$415.000
|
|
|
INS OF TRF SIG PL FND (36" DRIL SHFT)
|
LF
|
10.000
|
$310.910
|
$428.260
|
$475.000
|
|
|
INSTL DOWN GUY W/GUARD
|
EA
|
2.000
|
$310.540
|
$207.200
|
$350.000
|
|
|
REPLACE DOWN GUY W/GUARD
|
EA
|
2.000
|
$335.540
|
$207.200
|
$500.000
|
|
|
INSTL DOWN GUY AND ANCHOR W/GUARD
|
EA
|
2.000
|
$356.770
|
$321.840
|
$600.000
|
|
|
REPLACE DOWN GUY AND ANCHOR W/GUARD
|
EA
|
2.000
|
$366.760
|
$321.840
|
$900.000
|
|
|
INSTL PED POLE ASSM
|
EA
|
1.000
|
$2,362.600
|
$2,963.410
|
$2,115.000
|
|
|
REPLACE PED POLE ASSM
|
EA
|
1.000
|
$2,513.910
|
$2,396.490
|
$2,315.000
|
|
|
REMOVE PED POLE ASSM
|
EA
|
1.000
|
$838.660
|
$1,449.280
|
$200.000
|
|
|
REPLACE LED TRAF SIG LAMP UNIT
|
EA
|
40.000
|
$109.850
|
$146.720
|
$250.000
|
|
|
REPLACE PED SIG LED TRAF SIG LAMP UNIT
|
EA
|
5.000
|
$200.850
|
$146.720
|
$200.000
|
|
|
INSTALL PED SGN LED TRAF SIG AMP UNIT
|
EA
|
5.000
|
$175.850
|
$115.080
|
$100.000
|
|
|
REPLACE SPREAD SPECTRUM ANTENNA
|
EA
|
2.000
|
$280.940
|
$872.480
|
$500.000
|
|
|
INSTALL SCREW-IN FND
|
EA
|
2.000
|
$1,087.620
|
$1,351.530
|
$2,000.000
|
|
|
INSTALL BBU SYSTEM
|
EA
|
3.000
|
$1,216.590
|
$933.120
|
$810.000
|
|
|
REPLACE BBU SYSTEM
|
EA
|
2.000
|
$950.350
|
$1,009.520
|
$910.000
|
|
|
INSTALL RADAR VEHICLE DETECTION SYSTEM
|
EA
|
2.000
|
$2,940.940
|
$3,096.800
|
$3,825.000
|
|
|
REPLACE RADAR VEHICLE DETECTION SYSTEM
|
EA
|
2.000
|
$3,440.940
|
$3,096.800
|
$4,225.000
|
|
|
REMOVE RADAR VEHICLE DETECTION SYSTEM
|
EA
|
2.000
|
$1,264.510
|
$454.720
|
$1,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
20.000
|
$220.990
|
$198.380
|
$200.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
100.000
|
$5.900
|
$13.470
|
$3.000
|
|
|
GROUND BOX (PREPARE)
|
EA
|
2.000
|
$369.890
|
$211.680
|
$200.000
|
|
|
ITS RADIO (INSTALL ONLY)
|
EA
|
2.000
|
$1,938.050
|
$1,125.600
|
$500.000
|
|
|
TMA (STATIONARY)
|
DAY
|
10.000
|
$878.350
|
$833.840
|
$1,000.000
|
|
|
PREVENTATIVE MAINT (TRAFFIC SIGNALS)
|
EA
|
100.000
|
$1,328.780
|
$1,971.760
|
$2,735.000
|
|
Totals: |
$424,326.270
|
$558,254.260
|
$604,800.000
|