TARRANT IH0820 (6330-10-001)

Items: 64

County: TARRANT
Length: N/A
Highway: IH0820
District: FORT WORTH
Control Number: 6330-10-001
DBE Goal: N/A
Project: RMC - 633010001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,888,875.00
Date: 09/07/2018 (7 years ago)
Contract Number: N/A
Type: GUARDRAIL REPAIR/INSTALLATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,888,875.00
$1,745,320.00
Over/Under Est: -7.6% -$143,555.00
$1,758,850.00
Over/Under Est: -6.88% -$130,025.00
Amt Left: 0.78% $13,530.00
$2,062,180.00
Over/Under Est: 9.18% $173,305.00
Amt Left: 18.15% $316,860.00
Delta: -17.25% -$303,330.00
Over/Under Est: 16.36% $309,025.00
Amt Left: 25.93% $452,580.00
Delta: -6.58% -$135,720.00

Bid Items & Bid Tabulations

64 Total 0 of 64
TARRANT  |  IH0820  |  FORT WORTH  |  6330-10-001  |  09/07/2018  |  $1,888,875.00  |  RMC - 633010001  |  GUARDRAIL REPAIR/INSTL  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VANN/ELLI, INC.
IIPL USA LLC
K-BAR SERVICES, INC.
ROY JORGENSEN ASSOCIATES, INC.
MOBILIZATION (CALLOUT)
EA 26.000 $200.000 $100.000 $1,000.000 $100.000 $1,250.000
MOBILIZATION (EMERGENCY)
EA 3.000 $500.000 $100.000 $1,500.000 $1,000.000 $2,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $25.000 $21.000 $50.000 $28.000 $75.000
TERMINAL ANCHOR SECTION
EA 10.000 $500.000 $20.000 $800.000 $150.000 $600.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $2,000.000 $1,600.000 $2,500.000 $2,200.000 $2,100.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 500.000 $20.000 $15.000 $20.000 $18.000 $25.000
SHORT RADIUS
LF 250.000 $30.000 $20.000 $40.000 $20.000 $25.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $500.000 $600.000 $700.000 $900.000 $500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 20.000 $1,220.000 $1,000.000 $1,500.000 $1,500.000 $1,400.000
MTL BEAM GD FEN TRANS(THRIE BEAM)28"
EA 5.000 $1,800.000 $1,600.000 $2,000.000 $1,000.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $5.000 $2.000 $10.000 $8.000 $10.000
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $100.000 $50.000 $500.000 $800.000 $100.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 2.000 $800.000 $500.000 $1,200.000 $1,000.000 $500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $200.000 $100.000 $500.000 $500.000 $100.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 2.000 $2,500.000 $2,460.000 $2,000.000 $4,000.000 $2,500.000
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 5.000 $2,700.000 $2,800.000 $2,800.000 $4,000.000 $3,500.000
CHAIN LINK FENCE (REMOVE)
LF 100.000 $5.000 $2.000 $2.000 $10.000 $2.000
CHAIN LINK FENCE (REPAIR) (4')
LF 500.000 $25.000 $20.000 $10.000 $15.000 $15.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 50,000.000 $11.000 $11.000 $9.000 $14.000 $14.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 50.000 $35.000 $40.000 $40.000 $20.000 $25.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 50.000 $25.000 $40.000 $40.000 $20.000 $25.000
RAISE RAIL ELEMENT
LF 1,000.000 $7.000 $3.000 $5.000 $10.000 $4.000
REALIGN EXISTING RAIL
LF 200.000 $7.000 $10.000 $5.000 $15.000 $4.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 2,000.000 $45.000 $45.000 $35.000 $15.000 $50.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 75.000 $75.000 $50.000 $100.000 $50.000 $100.000
REALIGN POSTS
EA 1,500.000 $15.000 $15.000 $10.000 $10.000 $16.000
REMOVE & REPLACE BLOCKOUT
EA 500.000 $20.000 $15.000 $15.000 $100.000 $15.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 3,000.000 $16.000 $5.000 $20.000 $15.000 $35.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 500.000 $65.000 $100.000 $35.000 $80.000 $75.000
REPLACE TERMINAL ANCHOR POSTS
EA 20.000 $30.000 $10.000 $50.000 $50.000 $50.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 100.000 $2,750.000 $2,550.000 $2,800.000 $4,000.000 $3,000.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 50.000 $825.000 $700.000 $800.000 $660.000 $1,250.000
REM & RESET SGT IMPACT HEAD
EA 100.000 $150.000 $25.000 $100.000 $200.000 $50.000
REPLACE SGT CABLE ASSEMBLY
EA 30.000 $40.000 $100.000 $100.000 $100.000 $100.000
REPLACE SGT CABLE ANCHOR
EA 10.000 $75.000 $100.000 $200.000 $100.000 $100.000
REPLACE SGT STRUT
EA 10.000 $75.000 $100.000 $200.000 $100.000 $100.000
REPLACE SGT OBJECT MARKER
EA 50.000 $45.000 $100.000 $50.000 $100.000 $35.000
REPAIR STEEL POST WITH BASE PLATE
EA 200.000 $175.000 $300.000 $150.000 $125.000 $200.000
REPLACE POSTS (TL-3)
EA 750.000 $100.000 $100.000 $75.000 $100.000 $5.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 2.000 $200.000 $300.000 $350.000 $200.000 $250.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 5.000 $50.000 $50.000 $100.000 $50.000 $80.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 2.000 $1,500.000 $1,000.000 $1,500.000 $3,500.000 $2,000.000
REPLACE CABLE (TL-3)
LF 100.000 $5.000 $4.000 $10.000 $8.000 $100.000
CHECK / RE-TENSION CABLE
EA 10.000 $500.000 $300.000 $300.000 $300.000 $250.000
POST AND CABLE FENCE (REMOVAL)
LF 200.000 $10.000 $1.000 $5.000 $10.000 $3.000
POST AND CABLE FENCE (NEW INSTALLATION)
LF 200.000 $20.000 $10.000 $5.000 $15.000 $5.000
REMOVE AND REPLACE (TRACC)
EA 5.000 $13,500.000 $14,500.000 $11,000.000 $15,000.000 $14,500.000
REMOVE AND REPLACE (NARROW REACT 350)
EA 5.000 $18,500.000 $22,000.000 $18,500.000 $20,000.000 $20,000.000
REPAIR (TRACC)
EA 10.000 $2,000.000 $2,500.000 $2,500.000 $1,800.000 $2,250.000
REPAIR (REACT)
EA 25.000 $2,000.000 $1,500.000 $2,500.000 $2,000.000 $2,250.000
REPAIR REACT (N) (MISC HARDWARE)
EA 10.000 $750.000 $1,000.000 $800.000 $1,000.000 $750.000
REPAIR REACT (N) (CYLINDERS)
EA 4.000 $2,000.000 $3,850.000 $2,000.000 $2,500.000 $3,000.000
REMOVE AND REPLACE (SMTC) (N)
EA 2.000 $20,000.000 $23,000.000 $20,000.000 $25,000.000 $23,000.000
REPAIR (SMTC) (N)
EA 10.000 $2,000.000 $3,000.000 $5,000.000 $1,000.000 $2,500.000
REMOVE AND REPLACE (SHORTRACC)
EA 2.000 $11,000.000 $11,000.000 $9,000.000 $15,000.000 $12,000.000
REPAIR (SHORTRACC)
LF 2.000 $500.000 $300.000 $3,000.000 $1,000.000 $500.000
REMOVE AND REPLACE (TAU II) (N)
EA 1.000 $15,000.000 $15,500.000 $20,000.000 $25,000.000 $16,000.000
REPAIR TAU II (N) (MISC HARDWARE)
EA 1.000 $2,500.000 $2,000.000 $2,000.000 $1,500.000 $2,000.000
REPAIR TAU II (N)
LF 2.000 $400.000 $300.000 $2,000.000 $1,000.000 $500.000
REMOVE & REPLACE BEAT - SSCC
LF 50.000 $500.000 $200.000 $200.000 $250.000 $350.000
REPAIR (BEAT - SSCC)
LF 100.000 $200.000 $200.000 $100.000 $100.000 $450.000
REPAIR TY (T4 (S) RAIL)
LF 200.000 $200.000 $120.000 $100.000 $80.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 2.000 $200.000 $200.000 $200.000 $540.000 $200.000
TMA (STATIONARY)
DAY 260.000 $350.000 $25.000 $250.000 $50.000 $400.000
Totals: $1,888,875.000 $1,745,320.000 $1,758,850.000 $2,062,180.000 $2,197,900.000