TARRANT SS 341 (1068-03-024)

Items: 28

County: TARRANT
Length: 0.0000 MILES
Highway: SS 341
District: FORT WORTH
Control Number: 1068-03-024
DBE Goal: 0.0%
Project: C 1068-3-24
Guaranty: $32,000.00
Time: 56 WORKING DAYS
Engineer's Estimate: $1,576,570.05
Date: 05/01/2025 (1 year ago)
Contract Number: 5253026
Type: RESURFACE ROADWAY
Project ID: A00208449
Project Description: MILL AND OVERLAY , INSTALL CHAIN LINK FENCE W BARB TOP, PREP ROW CONSISTING OF TREE REMOVAL, BUSHES REMOVAL, REMOVE CABLE BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MARIBEL RANGEL
JUSTIN THOMEY
RAUL OROZCO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$1,576,570.05
$1,214,768.05
Over/Under Est: -22.95% -$361,802.00
Over/Under Est: -21.28% -$335,551.68
Amt Left: 2.16% $26,250.32
Over/Under Est: -20.97% -$330,573.49
Amt Left: 2.57% $31,228.51
Delta: -0.40% -$4,978.19
Over/Under Est: -20.43% -$322,155.05
Amt Left: 3.26% $39,646.95
Delta: -0.68% -$8,418.44
Over/Under Est: 23.65% $372,782.95
Amt Left: 60.47% $734,584.95
Delta: -55.40% -$694,938.00
Subcontractor Percentage Amount
T-BAR FENCE, INC. 9.55% $114,354.28
CIVIL TREE SOLUTIONS, LLC 6.08% $72,803.56
DUSTROL, INC. 5.66% $67,774.37
AWP SAFETY 1.24% $14,848.10
TRP CONSTRUCTION GROUP, LLC 1.07% $12,812.47
G J SEEDING, LLC 0.57% $6,825.33
Total: 24.17% $289,418.11

Bid Items & Bid Tabulations

28 Total 0 of 28
TARRANT  |  SS 341  |  FORT WORTH  |  1068-03-024  |  05/01/2025  |  $1,576,570.05  |  C 1068-3-24  |  RESURF ROADWAY  |  56 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PEACHTREE CONSTRUCTION, LTD.
AUSTIN BRIDGE & ROAD SERVICES, LP
TEXAS MATERIALS GROUP, INC.
FOUTSCO PAVING COMPANY, LLC
GREY SKY CONSTRUCTION LLC
PREPARING ROW
STA 35.000 $1,250.000 $320.000 $285.000 $260.000 $300.000 $4,571.000
ASPH (AC-20XP)
GAL 9,578.000 $7.000 $7.600 $8.050 $3.850 $8.000 $6.000
SP MIXES SP-C SAC-A PG70-28
TON 4,348.000 $200.000 $158.000 $139.250 $163.000 $152.000 $185.000
PLANE & TEXT ASPH CONC PAV(0" TO 3")
SY 25,204.000 $5.750 $2.850 $2.800 $2.880 $3.000 $6.000
MOBILIZATION
LS 1.000 $100,000.000 $60,000.000 $136,512.020 $122,266.000 $120,000.000 $190,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $15,000.000 $50,000.000 $24,000.000 $40,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $5,500.000 $4,384.130 $4,200.000 $7,000.000 $16,500.000
TMA (STATIONARY)
DAY 80.000 $340.000 $200.000 $2.000 $1.000 $1.000 $250.000
TMA (MOBILE OPERATION)
DAY 4.000 $380.000 $500.000 $5.000 $1.000 $1.000 $550.000
CHAIN LINK FENCE(INSTALL)(6 )(BARB TOP)
LF 3,465.000 $30.000 $43.000 $27.480 $36.000 $25.000 $40.000
WIRE FENCE (REMOVE)
LF 2,936.000 $6.000 $2.750 $5.010 $3.800 $2.500 $5.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 421.000 $2.100 $1.350 $1.250 $1.400 $2.000 $10.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 4.000 $200.000 $220.000 $200.000 $222.000 $200.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 4.000 $250.000 $245.000 $225.000 $250.000 $250.000 $250.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 3,000.000 $1.650 $0.850 $0.780 $0.870 $1.100 $3.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 6,043.000 $1.500 $0.750 $0.690 $0.770 $1.000 $3.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 5,959.000 $1.550 $0.750 $0.690 $0.770 $1.000 $3.000
SPOT TREE TRIMMING / BRUSH REMOVAL
LF 2,760.000 $28.500 $1.600 $6.730 $7.400 $1.500 $50.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 2.000 $12,000.000 $3,000.000 $10,000.000 $11,000.000 $2,750.000 $15,000.000
TREE REMOVAL (4" - 12" DIA)
EA 27.000 $560.000 $435.000 $150.000 $165.000 $500.000 $1,200.000
TREE REMOVAL (12" - 18" DIA)
EA 6.000 $500.000 $925.000 $200.000 $220.000 $850.000 $1,500.000
TREE REMOVAL (18" - 24" DIA)
EA 8.000 $500.000 $1,200.000 $400.000 $440.000 $1,100.000 $1,650.000
TREE REMOVAL (24" - 30" DIA)
EA 3.000 $750.000 $1,600.000 $600.000 $665.000 $1,500.000 $2,000.000
TREE REMOVAL (30" - 36" DIA)
EA 1.000 $1,500.000 $2,050.000 $800.000 $885.000 $1,900.000 $2,500.000
TREE REMOVAL (36" - 42" DIA)
EA 1.000 $1,500.000 $2,550.000 $1,200.000 $1,350.000 $2,400.000 $5,000.000
TREE REMOVAL (42" - 48" DIA)
EA 2.000 $1,500.000 $3,100.000 $1,500.000 $1,650.000 $2,850.000 $6,000.000
TREE REMOVAL (48" - 60" DIA)
EA 1.000 $1,500.000 $3,500.000 $1,750.000 $1,945.000 $3,250.000 $8,500.000
TREE REMOVAL (60" - 72" DIA)
EA 2.000 $1,500.000 $5,250.000 $2,050.000 $2,270.000 $5,000.000 $12,500.000
Totals: $1,576,570.050 $1,214,768.050 $1,241,018.370 $1,245,996.560 $1,254,415.000 $1,949,353.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $16,200.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $37,320.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $54,520.00