Show Job Controls
Bid Cobra

TARRANT VA (0902-90-178)

Items: 20

County: TARRANT
Length: N/A
Highway: VA
District: FORT WORTH
Control Number: 0902-90-178
DBE Goal: N/A
Project: NH 2B20(007)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $492,853.40
Date: 09/04/2020 (5 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$492,853.40
$386,800.00
Over/Under Est: -21.52% -$106,053.40
Over/Under Est: 3.01% $14,824.60
Amt Left: 31.25% $120,878.00
Over/Under Est: 18.34% $90,412.60
Amt Left: 50.79% $196,466.00
Delta: -14.89% -$75,588.00

Bid Items & Bid Tabulations

20 Total 0 of 20
TARRANT  |  VA  |  FORT WORTH  |  0902-90-178  |  09/04/2020  |  $492,853.40  |  NH 2B20(007)  |  LANDSCAPE DEVELOPMENT  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CENTRAL NORTH CONSTRUCTION, LLC
COLE CONSTRUCTION, INC.
ENCINO LANDSCAPE, INC.
PREPARING ROW
AC 1.000 $30,000.000 $10,000.000 $5,000.000 $30,000.000
EXCAVATION (ROADWAY)
CY 1,191.000 $25.000 $25.000 $30.000 $30.000
IRRIGATION SYSTEM
LS 1.000 $50,000.000 $123,281.100 $120,430.000 $100,000.000
MULCH
CY 201.000 $60.000 $30.000 $88.000 $60.000
PLANT SOIL MIX
CY 1,191.000 $55.000 $35.000 $75.000 $60.000
PLANT BED PREPARATION
SY 2,178.000 $10.000 $1.500 $3.800 $5.000
VEGETATION BARRIER
SY 2,178.000 $5.000 $4.050 $3.200 $5.000
PLANT MATERIAL (45 GAL) (TREE)
EA 12.000 $600.000 $400.000 $610.000 $500.000
PLANT MATERIAL (1 GAL) (SHRUB)
EA 5,057.000 $12.000 $8.000 $8.000 $12.000
PLANT MATERIAL (3 GAL) (SHRUB)
EA 1,129.000 $20.000 $20.000 $15.000 $30.000
PLANT MAINTENANCE
MO 12.000 $3,000.000 $1,500.000 $409.000 $2,000.000
IRRIGATION SYSTEM OPER AND MAINT
MO 12.000 $1,500.000 $750.000 $300.000 $1,000.000
MOBILIZATION
LS 1.000 $46,159.400 $20,000.000 $48,000.000 $40,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $8,500.000 $1,800.000 $3,000.000 $5,000.000
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 160.000 $22.500 $1.000 $20.000 $100.000
CONSTRUCTION EXITS (REMOVE)
SY 160.000 $9.000 $1.000 $5.000 $50.000
CONDT (PVC) (SCH 40) (4") (BORE)
LF 985.000 $28.000 $19.000 $56.000 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 90.000 $100.000 $85.000 $140.000 $300.000
TMA (STATIONARY)
DAY 96.000 $100.000 $175.000 $200.000 $167.000
CURB INLET SEDIMENT PROTECTION
LF 220.000 $25.000 $1.000 $14.000 $20.000
Totals: $492,853.400 $386,800.000 $507,678.000 $583,266.000