TARRANT CS (0902-48-894)

Items: 122

County: TARRANT
Length: N/A
Highway: CS
District: FORT WORTH
Control Number: 0902-48-894
DBE Goal: N/A
Project: BR 1502(322)
Guaranty: N/A
Time: 320 WORKING DAYS
Engineer's Estimate: $6,465,443.50
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$6,465,443.50
$4,807,165.35
Over/Under Est: -25.65% -$1,658,278.15
Over/Under Est: -16.48% -$1,065,359.33
Amt Left: 12.33% $592,918.82
Over/Under Est: -16.24% -$1,049,764.22
Amt Left: 12.66% $608,513.93
Delta: -0.29% -$15,595.11
Over/Under Est: 37.67% $2,435,850.80
Amt Left: 85.17% $4,094,128.95
Delta: -64.36% -$3,485,615.02
Subcontractor Percentage Amount
WYLIE DRILLING & DRAINAGE, INC. 3.61% $173,538.67
FORTSON CONTRACTING, INC. 2.27% $109,122.65
REYNOLDS ASPHALT & CONSTRUCTION COMPANY 0.98% $47,110.22
BREDA COMPANY, INC. 0.98% $47,110.22
BARRICADES UNLIMITED 0.71% $34,130.87
TEX OP CONSTRUCTION, LP 0.37% $17,786.51
PRIMATE CONSTRUCTION, LP 0.19% $9,133.61
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 0.19% $9,133.61
DFW REBAR, INC. 0.18% $8,652.90
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.16% $7,691.46
ACT SAW CUTTING & REMOVAL 0.16% $7,691.46
Total: 9.80% $471,102.18

Bid Items & Bid Tabulations

122 Total 0 of 122
TARRANT  |  CS  |  FORT WORTH  |  0902-48-894  |  08/03/2023  |  $6,465,443.50  |  BR 1502(322)  |  BRIDGE REPL  |  320 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HARPER BROTHERS CONSTRUCTION LLC
ED BELL CONSTRUCTION COMPANY
RAGLE CONSTRUCTION, INC.
INDUS ROAD & BRIDGE, INC.
PREPARING ROW
STA 6.120 $10,000.000 $41,438.000 $20,000.000 $87,000.000 $20,000.000
REMOVING CONC (PAV)
SY 2,179.000 $20.000 $15.000 $14.000 $13.000 $65.000
REMOVING CONC (RIPRAP)
SY 2,313.000 $50.000 $12.000 $16.000 $9.000 $65.000
REMOVING CONC (MEDIANS)
SY 50.000 $20.000 $33.000 $40.000 $24.000 $300.000
REMOVING CONC (DRIVEWAYS)
SY 13.000 $35.000 $72.000 $80.000 $47.000 $86.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 4.000 $50.000 $140.000 $250.000 $72.000 $230.000
EXCAVATION (ROADWAY)
CY 515.000 $66.000 $38.000 $35.000 $80.000 $192.000
EMBANKMENT (FINAL)(DENS CONT)(TY D)
CY 186.000 $15.000 $103.000 $50.000 $100.000 $241.000
COMPOST MANUF TOPSOIL (4")
SY 1,190.000 $10.000 $3.850 $9.250 $3.850 $20.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,190.000 $1.000 $0.500 $5.790 $0.500 $10.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 595.000 $2.500 $1.500 $1.580 $0.500 $10.000
CELL FBR MLCH SEED(TEMP)(COOL)
SY 595.000 $2.500 $1.750 $1.840 $1.750 $10.000
VEGETATIVE WATERING
MG 42.000 $100.000 $45.000 $220.500 $89.000 $80.000
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
CY 313.000 $150.000 $120.000 $125.000 $88.000 $250.000
LIME (HYDRATED LIME (SLURRY))
TON 3.000 $500.000 $2,000.000 $450.000 $771.000 $2,170.000
LIME TRT (EXST MATL)(8")
SY 110.000 $5.000 $100.000 $45.000 $15.000 $250.000
SALV, HAUL & STKPL RCL APH PV (6 TO 8")
SY 806.000 $15.000 $15.000 $31.500 $19.000 $30.000
PRIME COAT (MULTI OPTION)
GAL 161.000 $10.000 $10.000 $10.500 $24.000 $17.000
CONC PVMT (CONT REINF - CRCP) (7.5")
SY 1,875.000 $205.000 $167.000 $125.000 $95.000 $189.000
CEM STABIL BKFL
CY 588.000 $175.000 $160.000 $371.030 $135.000 $466.000
TEMPORARY SPL SHORING
SF 850.000 $50.000 $30.000 $90.000 $57.000 $121.000
DRILL SHAFT (18 IN)
LF 216.000 $100.000 $123.000 $120.650 $124.000 $298.000
DRILL SHAFT (36 IN)
LF 868.000 $300.000 $261.000 $255.140 $244.000 $513.000
CL A CONC (COLLAR)
EA 1.000 $5,000.000 $1,211.000 $1,750.000 $2,350.000 $2,600.000
CL C CONC (ABUT)(HPC)
CY 153.300 $1,650.000 $1,744.000 $1,500.000 $800.000 $2,127.000
CL C CONC (CAP)(HPC)
CY 124.800 $1,150.000 $1,936.000 $1,500.000 $1,050.000 $2,510.000
CL C CONC (COLUMN)(HPC)
CY 78.800 $1,220.000 $1,769.000 $1,500.000 $1,100.000 $3,080.000
CL C CONC (RAIL FOUNDATION)
CY 4.000 $900.000 $1,932.000 $1,500.000 $1,050.000 $800.000
REINF CONC SLAB (HPC)
SF 19,200.000 $30.000 $25.000 $25.000 $25.000 $30.000
BRIDGE SIDEWALK (HPC)
SF 3,746.000 $30.000 $19.000 $16.000 $13.000 $20.000
APPROACH SLAB (HPC)
CY 338.600 $1,400.000 $717.000 $750.000 $585.000 $1,001.000
PRESTR CONC GIRDER (TX28)
LF 2,697.600 $265.000 $190.000 $243.000 $200.000 $300.000
RIPRAP (CONC)(4 IN)
CY 19.000 $700.000 $1,629.000 $875.000 $725.000 $1,110.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 370.000 $800.000 $652.000 $830.000 $640.000 $1,100.000
RIPRAP (MOW STRIP)(4 IN)
CY 10.000 $1,500.000 $940.000 $1,000.000 $810.000 $2,000.000
STR STEEL (MISC NON - BRIDGE)
LB 320.000 $20.000 $35.000 $30.900 $24.500 $30.000
RAIL (TY T223)(HPC)
LF 492.000 $190.000 $111.000 $200.000 $129.000 $373.000
RAIL (TY C223)(HPC)
LF 467.000 $250.000 $168.000 $275.000 $164.000 $427.000
ARMOR JOINT (SEALED)
LF 224.000 $165.000 $103.000 $80.000 $101.000 $449.000
RC PIPE (CL III)(18 IN)
LF 25.000 $160.000 $501.000 $191.800 $138.000 $200.000
RC PIPE (CL III)(24 IN)
LF 22.000 $120.000 $597.000 $234.880 $151.000 $340.000
RC PIPE (CL III)(27 IN)
LF 62.000 $200.000 $472.000 $400.630 $135.000 $400.000
JCTBOX(COMPL)(PJB)(6FTX6FT)
EA 3.000 $12,000.000 $20,751.000 $23,322.090 $11,000.000 $21,000.000
INLET (COMPL)(PCU)(5FT)(BOTH)
EA 2.000 $15,000.000 $10,391.000 $12,776.170 $4,950.000 $21,000.000
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 1.000 $5,500.000 $6,849.000 $7,232.980 $6,400.000 $21,000.000
SET (TY II) (27 IN) (RCP) (6: 1) (P)
EA 1.000 $5,000.000 $8,216.000 $3,706.090 $2,100.000 $6,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 2.000 $225,000.000 $88,696.000 $90,000.000 $400,000.000 $300,000.000
MOBILIZATION
LS 1.000 $587,768.000 $376,546.110 $486,467.500 $540,000.000 $890,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $20,000.000 $5,170.000 $20,000.000 $6,500.000 $20,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 225.000 $50.000 $28.000 $25.200 $28.000 $100.000
CONSTRUCTION EXITS (REMOVE)
SY 225.000 $30.000 $10.000 $12.600 $10.000 $50.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 609.000 $5.000 $2.850 $2.360 $2.850 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 609.000 $3.000 $0.850 $0.530 $0.850 $4.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 122.000 $8.000 $3.500 $3.940 $3.500 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 122.000 $3.000 $1.000 $1.580 $1.000 $2.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 200.000 $55.000 $76.000 $32.550 $40.000 $210.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 100.000 $70.000 $61.000 $49.920 $40.000 $210.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 280.000 $10.000 $12.000 $8.960 $8.000 $30.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 60.000 $12.000 $9.000 $27.230 $8.000 $30.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 200.000 $20.000 $17.000 $17.970 $10.000 $30.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 100.000 $25.000 $18.000 $35.500 $10.000 $30.000
CONC CURB (TY II A)
LF 96.000 $25.000 $40.000 $14.130 $13.000 $250.000
CONC CURB (MONO) (TY II)
LF 1,104.000 $10.000 $6.000 $7.380 $9.000 $20.000
DRIVEWAYS (CONC) (HES)
SY 14.000 $175.000 $703.000 $318.770 $142.000 $500.000
CONC SIDEWALKS (4")
SY 90.000 $200.000 $121.000 $121.160 $54.000 $200.000
CURB RAMPS (TY 1)
EA 1.000 $3,500.000 $2,289.000 $2,492.920 $1,710.000 $4,775.000
CURB RAMPS (TY 2)
EA 1.000 $4,000.000 $2,588.000 $2,728.350 $1,940.000 $4,775.000
MTL W-BEAM GD FEN (TIM POST)
LF 162.500 $35.000 $26.000 $26.250 $24.000 $52.000
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,000.000 $1,161.000 $2,099.790 $1,225.000 $2,745.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,500.000 $1,161.000 $1,155.000 $1,425.000 $3,255.000
REMOVE METAL BEAM GUARD FENCE
LF 463.000 $7.500 $8.000 $3.150 $6.000 $10.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $360.000 $1,500.000 $262.500 $600.000 $800.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 2.000 $45,000.000 $17,672.000 $31,394.490 $28,800.000 $55,000.000
CRASH CUSH ATTEN (INSTL)(L)(W)(TL2)
EA 2.000 $50,000.000 $35,345.000 $59,862.730 $40,250.000 $65,000.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 100.000 $60.000 $152.000 $157.500 $60.000 $170.000
ELEC CONDR (NO.8) BARE
LF 100.000 $4.000 $3.860 $3.990 $2.000 $3.000
ELEC CONDR (NO.8) INSULATED
LF 200.000 $4.000 $3.860 $3.990 $2.000 $3.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $1,050.000 $794.000 $729.750 $794.000 $1,440.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $800.000 $745.000 $630.000 $745.000 $1,300.000
REMOVE SM RD SN SUP&AM
EA 1.000 $300.000 $170.000 $262.500 $170.000 $240.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 10.000 $30.000 $33.000 $26.250 $27.000 $66.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 10.000 $30.000 $33.000 $26.250 $27.000 $50.000
INSTL DEL ASSM (D-DY)SZ 2(WC)GND
EA 2.000 $65.000 $67.000 $52.500 $67.000 $200.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 6.000 $40.000 $45.000 $31.500 $31.000 $100.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 1,850.000 $5.000 $1.500 $1.580 $1.500 $3.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 5,905.000 $2.000 $1.350 $1.420 $1.350 $2.600
WK ZN PAV MRK REMOV (Y)4"(DOT)
LF 640.000 $2.000 $2.000 $2.100 $2.000 $4.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 7,335.000 $5.000 $1.350 $1.420 $1.350 $2.500
REFL PAV MRK TY II (W) 6" (BRK)
LF 1,035.000 $1.000 $1.450 $1.520 $1.450 $1.000
REFL PAV MRK TY II (W) 6" (DOT)
LF 68.000 $2.000 $2.000 $2.100 $2.000 $2.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 758.000 $1.000 $1.450 $1.520 $1.450 $1.000
REFL PAV MRK TY II (W) 8" (DOT)
LF 25.000 $2.500 $2.000 $3.150 $3.000 $1.600
REFL PAV MRK TY II (W) 8" (SLD)
LF 1,050.000 $1.000 $2.000 $2.100 $2.000 $1.600
REFL PAV MRK TY II (W) 24" (SLD)
LF 73.000 $12.000 $6.000 $6.300 $6.000 $21.000
REFL PAV MRK TY II (W) (ARROW)
EA 7.000 $150.000 $100.000 $105.000 $100.000 $195.000
REFL PAV MRK TY II (W) (WORD)
EA 7.000 $200.000 $130.000 $136.500 $130.000 $450.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 1,224.000 $1.000 $1.450 $1.520 $1.450 $1.000
PAVEMENT SEALER 6"
LF 3,085.000 $1.500 $0.010 $0.010 $0.010 $1.400
PAVEMENT SEALER 8"
LF 1,075.000 $1.500 $0.010 $0.010 $0.010 $1.000
PAVEMENT SEALER 24"
LF 73.000 $3.000 $0.010 $0.010 $0.010 $4.000
PAVEMENT SEALER (ARROW)
EA 7.000 $40.000 $1.000 $1.050 $1.000 $90.000
PAVEMENT SEALER (WORD)
EA 7.000 $50.000 $1.000 $1.050 $1.000 $90.000
REFL PAV MRKR TY I-C
EA 79.000 $10.000 $6.000 $6.300 $6.000 $6.000
REFL PAV MRKR TY II-C-R
EA 36.000 $10.000 $6.000 $6.300 $6.000 $8.000
ELIM EXT PAV MRK & MRKS (4")
LF 628.000 $2.000 $1.500 $1.580 $1.500 $2.200
ELIM EXT PAV MRK & MRKRS(PLOWABLE RPMS)
EA 468.000 $10.000 $5.000 $5.250 $5.000 $90.000
PAV SURF PREP FOR MRK (6")
LF 3,085.000 $1.000 $0.750 $0.790 $0.750 $1.000
PAV SURF PREP FOR MRK (8")
LF 1,075.000 $1.000 $1.000 $1.050 $1.000 $1.000
PAV SURF PREP FOR MRK (24")
LF 73.000 $2.000 $5.000 $5.250 $5.000 $3.000
PAV SURF PREP FOR MRK (ARROW)
EA 7.000 $100.000 $50.000 $52.500 $50.000 $70.000
PAV SURF PREP FOR MRK (WORD)
EA 7.000 $100.000 $75.000 $78.750 $75.000 $90.000
PAV SURF PREP FOR MRK (RPM)
EA 115.000 $35.000 $3.000 $3.150 $3.000 $2.000
TRF SIG CBL (TY A)(14 AWG)(3 CONDR)
LF 225.000 $7.000 $4.000 $4.200 $2.000 $6.500
TRF SIG CBL (TY A)(14 AWG)(20 CONDR)
LF 225.000 $10.000 $13.000 $13.130 $5.000 $19.000
INSTALL OF CABLES
LF 450.000 $7.000 $3.050 $3.150 $1.000 $4.000
D-GR HMA TY-B PG64-22
TON 348.000 $150.000 $127.000 $155.800 $145.000 $260.000
TACK COAT
GAL 161.000 $14.000 $8.000 $8.400 $2.000 $17.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1,960.000 $120.000 $55.000 $64.040 $87.000 $164.000
ITS COM CBL (ETHERNET)
LF 225.000 $10.000 $3.860 $3.990 $20.000 $10.000
GROUND BOX (PREPARE)
EA 4.000 $1,000.000 $2,517.000 $2,604.000 $500.000 $1,600.000
TMA (STATIONARY)
DAY 393.000 $550.000 $150.000 $220.020 $342.000 $651.000
TMA (MOBILE OPERATION)
DAY 5.000 $200.000 $695.000 $1,134.110 $680.000 $2,170.000
Totals: $6,465,443.500 $4,807,165.350 $5,400,084.175 $5,415,679.280 $8,901,294.300