Show Job Controls
Bid Cobra

TARRANT VA (0902-00-312)

Items: 19

County: TARRANT
Length: N/A
Highway: VA
District: FORT WORTH
Control Number: 0902-00-312
DBE Goal: N/A
Project: C 902-00-312
Guaranty: N/A
Time: 365 WORKING DAYS
Engineer's Estimate: $3,433,330.00
Date: 06/29/2022 (3 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
DANNY HENDERSON
JUSTIN STREET
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$3,433,330.00
$4,103,210.00
Over/Under Est: 19.51% $669,880.00
Over/Under Est: 27.94% $959,210.00
Amt Left: 7.05% $289,330.00
$5,471,035.38
Over/Under Est: 59.35% $2,037,705.38
Amt Left: 33.34% $1,367,825.38
Delta: -24.55% -$1,078,495.38

Bid Items & Bid Tabulations

19 Total 0 of 19
TARRANT  |  VA  |  FORT WORTH  |  0902-00-312  |  06/29/2022  |  $3,433,330.00  |  C 902-00-312  |  REHAB EXIST ROADWAY  |  365 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NEW WORLD CONTRACTING, LLC
O. TREVINO CONSTRUCTION, LLC
ALTUS CONSTRUCTION LLC
CURB (TYPE II)
LF 330.000 $71.000 $32.000 $93.000 $68.090
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 100.000 $512.000 $342.000 $650.000 $1,147.110
FULL-DEPTH REPAIR CRCP (6"-7")
SY 1,875.000 $191.000 $289.000 $236.000 $224.250
FULL-DEPTH REPAIR CRCP (8"-10")
SY 3,650.000 $233.000 $318.000 $265.000 $250.940
FULL-DEPTH REPAIR CRCP (11"-12")
SY 4,525.000 $227.000 $289.000 $319.000 $276.680
FULL-DEPTH REPAIR CRCP (13"-15")
SY 575.000 $320.000 $368.000 $416.000 $354.570
CNC STR REP(ULTR RPD DCK REP)(TYB)(P D)
SF 225.000 $40.000 $53.000 $250.000 $340.460
CNC STR REP(ULTR RPD DCK REP)(TYB)(F D)
SF 225.000 $192.000 $53.000 $250.000 $340.460
CLEANING AND SEALING JOINTS (CL 7)
LF 1,000.000 $26.000 $28.000 $24.000 $43.580
HEADER TYPE EXPANSION JOINT
CF 350.000 $486.000 $202.000 $570.000 $626.460
MOBILIZATION (CALLOUT 1)
EA 12.000 $2,500.000 $15,800.000 $3,500.000 $27,237.180
MOBILIZATION (EMERGENCY)
EA 5.000 $4,500.000 $15,800.000 $5,500.000 $34,046.480
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $15,000.000 $4,900.000 $22,000.000 $68,092.960
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $7.500 $16.000 $8.000 $27.240
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $1.500 $10.000 $1.750 $10.890
SPALLING REPAIR (POLYMERIC) (FLEXIBLE)
GAL 5,000.000 $44.000 $26.000 $52.000 $88.520
FIBER REINFORCED POLYMER PATCHING MATLS
LB 30,000.000 $4.000 $4.500 $5.000 $8.170
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 250.000 $175.000 $224.000 $185.000 $136.190
TMA (STATIONARY)
DAY 420.000 $175.000 $150.000 $185.000 $204.280
Totals: $3,433,330.000 $4,103,210.000 $4,392,540.000 $5,471,035.380