TARRANT SH 183 (0363-01-148)

Items: 71

County: TARRANT
Length: 0.0000 MILES
Highway: SH 183
District: FORT WORTH
Control Number: 0363-01-148
DBE Goal: 0.0%
Project: C 363-1-148
Guaranty: $70,000.00
Time: 170 WORKING DAYS
Engineer's Estimate: $3,511,800.60
Date: 02/07/2025 (1 year ago)
Contract Number: 2253213
Type: RESURFACE ROADWAY
Project ID: A00131543
Project Description: MILLING & OVERLAY, PAVEMENT BASE REPAIR, PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
MARIBEL RANGEL
ALFREDO LUERA
CYNTHIA DELAGARZA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,511,800.60
$3,019,197.05
Over/Under Est: -14.03% -$492,603.55
Over/Under Est: -7.19% -$252,438.51
Amt Left: 7.95% $240,165.04
Over/Under Est: -4.37% -$153,528.44
Amt Left: 11.23% $339,075.11
Delta: -3.03% -$98,910.07
Over/Under Est: 2.7% $94,972.98
Amt Left: 19.46% $587,576.53
Delta: -7.40% -$248,501.42
Over/Under Est: 5.66% $198,863.40
Amt Left: 22.9% $691,466.95
Delta: -2.88% -$103,890.42
Subcontractor Percentage Amount
TEXOP CONSTRUCTION 11.45% $363,623.29
SOUTHERN CROSS CONTRACTORS, LLC 5.21% $165,456.54
FC TRAFFIC CONTROL, INC. 4.93% $156,564.44
TRAFFIC HIGHWAY MAINTENANCE, LLC 3.69% $117,185.15
S & S BRIDGE PAINTING, INC. 1.99% $63,197.41
MACIAS SPECIALTY CONTRACTING LLC 1.50% $47,636.24
ACT SAW CUTTING & REMOVAL 1.49% $47,318.66
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 0.42% $13,338.15
EAST TEXAS R & D SERVICES, INC. 0.00% $0.00
Total: 30.68% $974,319.88

Bid Items & Bid Tabulations

71 Total 0 of 71
TARRANT  |  SH 183  |  FORT WORTH  |  0363-01-148  |  02/07/2025  |  $3,511,800.60  |  C 363-1-148  |  RESURF ROADWAY  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
PEACHTREE CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
AUSTIN BRIDGE & ROAD SERVICES, LP
GREY SKY CONSTRUCTION LLC
REMOV CONC (CURB & GUTTER)
LF 200.000 $27.560 $40.000 $37.000 $37.000 $23.830 $20.000
EXCAV (ROADWAY)
CY 44.000 $65.000 $30.000 $84.000 $53.000 $200.000 $30.000
EMBANK (FNL)(OC)(TY A)
CY 30.000 $150.000 $30.000 $130.000 $134.000 $300.000 $50.000
BACKFILL (TY A OR B)
STA 58.000 $270.000 $100.000 $345.000 $405.000 $700.000 $250.000
SALV, HAUL & STKPL RCL APH PV (2"-6")
SY 74,794.000 $5.000 $4.500 $4.350 $4.240 $6.000 $5.000
SP MIXES SP-C SAC-A PG70-28
TON 8,601.000 $155.000 $140.000 $159.800 $166.000 $142.000 $165.000
TACK COAT
GAL 14,959.000 $3.500 $1.000 $1.000 $0.010 $0.100 $6.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 5,920.000 $85.000 $40.000 $52.600 $60.000 $60.000 $65.000
PLANE ASPH CONC PAV(1.5" - 3.5")
SY 3,178.000 $6.000 $10.000 $8.150 $8.000 $9.000 $20.000
FLOWABLE BACKFILL
CY 10.000 $1,500.000 $400.000 $696.000 $714.000 $800.000 $350.000
CONCRETE PAINT FINISH
SF 6,965.000 $15.000 $1.250 $6.290 $1.070 $2.030 $11.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 4,064.000 $20.000 $15.000 $20.960 $13.000 $17.290 $18.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 223.000 $200.000 $200.000 $231.630 $237.000 $75.000 $250.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 36.500 $200.000 $200.000 $510.500 $491.000 $175.000 $500.000
RIPRAP (CONC)(4 IN)
CY 1.000 $1,500.000 $5,000.000 $3,635.000 $2,700.000 $6,300.000 $650.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $650.000 $1,000.000 $798.000 $833.000 $1,045.530 $550.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 380.000 $68.000 $50.000 $56.600 $58.000 $42.000 $50.000
RESIZING AND SEALING JOINTS
LF 504.000 $75.000 $80.000 $71.270 $73.000 $105.000 $50.000
CLEAN & PAINT EXIST STR (SYSTEM I)
LS 1.000 $6,000.000 $10,000.000 $46,285.000 $8,067.000 $46,404.440 $25,000.000
RETROFIT RAIL (TY T131RC)
LF 459.000 $300.000 $270.000 $106.000 $106.000 $400.000 $250.000
ADJUSTING MANHOLES
EA 1.000 $2,600.000 $1,000.000 $6,500.000 $5,378.000 $3,500.000 $2,500.000
MOBILIZATION
LS 1.000 $294,478.000 $332,000.000 $325,000.000 $334,976.000 $390,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $9,500.000 $20,000.000 $14,500.000 $37,000.000 $45,000.000 $8,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $15,000.000 $17,000.000 $12,000.000 $16,513.540 $16,500.000
TMA (STATIONARY)
DAY 170.000 $250.000 $10.000 $125.000 $1.000 $5.000 $250.000
TMA (MOBILE OPERATION)
DAY 10.000 $350.000 $250.000 $250.000 $1.000 $450.000 $500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,650.000 $4.000 $2.000 $3.000 $4.250 $2.860 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,650.000 $2.000 $1.000 $1.500 $1.100 $1.400 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 105.000 $6.000 $10.000 $16.000 $6.500 $15.150 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 105.000 $3.000 $0.800 $5.500 $1.070 $5.250 $2.000
CONC CURB (TY II)
LF 13.000 $50.000 $130.000 $84.000 $90.000 $520.000 $55.000
CONC CURB & GUTTER (TY II)
LF 200.000 $50.000 $70.000 $102.500 $110.000 $45.000 $65.000
MTL W-BEAM GD FEN (TIM POST)
LF 550.000 $29.000 $28.000 $23.500 $25.000 $22.800 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $3,700.000 $1,850.000 $2,600.000 $1,955.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,600.000 $1,800.000 $1,275.000 $1,300.000 $1,445.000 $1,850.000
MTL BM GD FEN TRANS (NON - SYM)
EA 4.000 $1,150.000 $1,100.000 $910.000 $925.000 $875.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 575.000 $10.000 $3.000 $2.600 $3.000 $2.750 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $700.000 $340.000 $215.000 $225.000 $275.000 $500.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $1,000.000 $340.000 $215.000 $225.000 $275.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 3.000 $260.000 $340.000 $265.000 $270.000 $275.000 $500.000
RM MTL BM GD FENCE TRANS (TL-2)
EA 3.000 $250.000 $340.000 $265.000 $270.000 $275.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,300.000 $3,700.000 $3,050.000 $3,100.000 $2,969.000 $3,250.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $300.000 $340.000 $260.000 $270.000 $275.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 25.000 $860.000 $790.000 $735.000 $690.000 $635.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $800.000 $990.000 $820.000 $875.000 $795.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $1,350.000 $1,300.000 $1,050.000 $1,150.000 $1,040.000 $1,500.000
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 32.000 $230.000 $200.000 $402.000 $180.000 $165.000 $500.000
REMOVE SM RD SN SUP&AM
EA 31.000 $150.000 $190.000 $155.000 $85.000 $79.000 $500.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 32.000 $100.000 $31.000 $110.000 $27.000 $25.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2
EA 60.000 $45.000 $31.000 $99.000 $27.000 $25.000 $100.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GF2
EA 60.000 $20.000 $31.000 $99.000 $27.000 $25.000 $100.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 16,025.000 $0.500 $0.400 $0.390 $0.250 $0.230 $1.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 18,897.000 $0.500 $0.300 $0.280 $0.250 $0.230 $1.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,703.000 $0.700 $1.000 $0.920 $0.550 $0.500 $6.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 607.000 $10.000 $8.000 $7.750 $3.760 $3.500 $20.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 18,257.000 $0.500 $0.300 $0.280 $0.250 $0.230 $1.000
WK ZN PAV MRK REMOV (W)(ARROW)
EA 45.000 $285.000 $350.000 $275.000 $62.000 $58.000 $250.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 14.000 $220.000 $600.000 $350.000 $74.000 $69.000 $250.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,703.000 $1.000 $1.000 $1.020 $0.950 $0.890 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 607.000 $7.000 $11.000 $9.160 $7.400 $6.900 $10.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 16,025.000 $0.650 $1.000 $0.870 $0.640 $0.600 $0.750
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 18,897.000 $0.650 $0.900 $0.750 $0.640 $0.600 $0.750
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 5,541.000 $0.650 $1.000 $0.870 $0.680 $0.630 $0.750
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 18,257.000 $0.650 $0.900 $0.750 $0.640 $0.600 $0.750
PAVEMENT SLER (ARROW)
EA 45.000 $55.000 $50.000 $40.700 $16.000 $15.000 $250.000
PAVEMENT SLER (WORD)
EA 14.000 $60.000 $60.000 $50.900 $16.000 $15.000 $250.000
PREFAB PM TY C (W)(ARROW)
EA 45.000 $240.000 $300.000 $265.000 $208.000 $194.000 $250.000
PREFAB PM TY C (W)(WORD)
EA 14.000 $280.000 $400.000 $350.000 $301.000 $280.000 $250.000
REFL PAV MRKR TY I-C
EA 261.000 $4.500 $8.000 $7.500 $4.300 $3.990 $5.000
REFL PAV MRKR TY II-A-A
EA 95.000 $5.000 $8.000 $7.500 $4.300 $4.000 $5.000
BENT CAP/ABUTMENT CAP CLEANING
EA 6.000 $2,000.000 $1,200.000 $1,425.000 $1,414.000 $1,900.000 $10,000.000
Totals: $3,511,800.600 $3,019,197.050 $3,259,362.090 $3,358,272.160 $3,606,773.580 $3,710,664.000