TARRANT US 287 (0172-09-034)

Items: 87

County: TARRANT
Length: N/A
Highway: US 287
District: FORT WORTH
Control Number: 0172-09-034
DBE Goal: N/A
Project: STP 1702(732)
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $2,162,474.41
Date: 10/04/2017 (8 years ago)
Contract Number: N/A
Type: GR, BS, DR, STR, PAV
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,162,474.41
$1,869,823.09
Over/Under Est: -13.53% -$292,651.32
Over/Under Est: -13.39% -$289,609.76
Amt Left: 0.16% $3,041.56
Over/Under Est: -3.06% -$66,090.11
Amt Left: 12.12% $226,561.21
Delta: -11.93% -$223,519.65
$2,543,116.50
Over/Under Est: 17.6% $380,642.09
Amt Left: 36.01% $673,293.41
Delta: -21.31% -$446,732.20

Bid Items & Bid Tabulations

87 Total 0 of 87
TARRANT  |  US 287  |  FORT WORTH  |  0172-09-034  |  10/04/2017  |  $2,162,474.41  |  STP 1702(732)  |  GR, BS, DR, STR, PAV  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
JAY MILLS CONTRACTING, INCORPORATED
GIBSON & ASSOCIATES, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 41.000 $5,454.250 $2,520.000 $750.000 $200.000 $5,000.000
REMOVING CONC (PAV)
SY 1,256.000 $10.000 $14.000 $13.000 $27.500 $20.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 941.000 $12.630 $10.500 $10.000 $7.700 $12.500
REMOVING CONC (FLUME)
SY 402.000 $12.230 $13.650 $12.000 $22.000 $20.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 4,160.000 $10.000 $8.400 $5.000 $9.600 $20.000
EXCAVATION (ROADWAY)
CY 6,881.100 $10.000 $3.150 $12.000 $8.250 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 650.000 $12.000 $21.000 $25.000 $33.000 $30.000
EMBANKMENT (FINAL)(DENS CONT)(TY D)
CY 6,845.800 $11.300 $1.050 $7.000 $8.800 $30.000
COMPOST MANUF TOPSOIL (4")
SY 3,142.000 $1.300 $3.150 $3.500 $1.650 $6.500
BLOCK SODDING
SY 1,715.000 $8.500 $6.300 $4.500 $4.290 $5.500
CELL FBR MLCH SEED(TEMP)(WARM)
SY 8,924.000 $0.750 $0.450 $0.440 $0.440 $0.500
CELL FBR MLCH SEED(TEMP)(COOL)
SY 5,586.000 $0.750 $0.450 $0.440 $0.440 $0.500
VEGETATIVE WATERING
MG 677.900 $20.000 $26.000 $16.000 $48.400 $30.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 295.900 $55.920 $63.000 $54.000 $99.000 $60.000
LIME (HYD, COM, OR QK(SLURRY))
TON 101.600 $182.000 $180.000 $165.000 $176.000 $171.000
LIME TRT (SUBGRADE)(6")
SY 8,125.000 $5.000 $7.750 $2.500 $5.500 $3.500
PRIME COAT (MULTI OPTION)
GAL 2,145.800 $6.500 $7.350 $3.800 $7.150 $6.000
D-GR HMA TY-B PG64-22
TON 2,662.700 $75.000 $82.400 $85.000 $84.320 $78.000
D-GR HMA TY D PG 70-28(LATEX ADDITIVE)
TON 325.700 $100.000 $103.330 $108.000 $107.140 $120.000
PLANE ASPH CONC PAV (6")
SY 1,825.000 $5.000 $8.400 $9.000 $9.600 $20.000
CONC PVMT (CONT REINF - CRCP) (8")
SY 3,978.000 $100.000 $63.000 $58.000 $84.000 $50.000
TRENCH EXCAVATION PROTECTION
LF 1,000.000 $5.000 $0.250 $12.000 $2.200 $3.500
CL B CONC (FLUME)
CY 253.100 $445.950 $525.000 $550.000 $550.000 $500.000
RIPRAP (CONC)(5 IN)
CY 339.700 $408.930 $525.000 $550.000 $460.000 $500.000
RIPRAP (MOW STRIP)(5 IN)
CY 69.300 $550.000 $630.000 $550.000 $600.000 $500.000
RC PIPE (CL III)(21 IN)
LF 91.300 $61.430 $57.500 $51.000 $82.500 $85.000
RC PIPE (CL III)(24 IN)
LF 617.700 $65.440 $63.000 $59.000 $80.300 $85.000
RC PIPE (CL III)(42 IN)
LF 290.500 $119.960 $144.000 $130.000 $170.500 $250.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $3,602.020 $4,200.000 $2,900.000 $9,900.000 $5,000.000
INLET (COMPL)(DROP)(TY 3)
EA 2.000 $3,145.270 $6,300.000 $4,000.000 $5,500.000 $5,000.000
SET (TY II) (21 IN) (RCP) (6: 1) (C)
EA 2.000 $1,200.000 $1,260.000 $1,100.000 $2,200.000 $2,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 1.000 $1,039.020 $1,470.000 $1,100.000 $2,750.000 $2,500.000
SET (TY II) (42 IN) (RCP) (6: 1) (C)
EA 1.000 $5,000.000 $5,250.000 $2,900.000 $12,100.000 $5,000.000
REMOV STR (INLET)
EA 2.000 $1,181.330 $525.000 $1,200.000 $2,750.000 $2,500.000
REMOV STR (HEADWALL)
EA 2.000 $1,440.250 $1,155.000 $1,600.000 $2,750.000 $2,500.000
REMOV STR (PIPE)
LF 554.000 $23.250 $17.850 $15.000 $12.100 $30.000
MOBILIZATION
LS 1.000 $196,874.000 $179,000.000 $180,000.000 $191,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $7,483.140 $15,750.000 $15,000.000 $6,800.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 160.000 $20.000 $21.000 $12.500 $31.900 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 160.000 $8.500 $10.500 $6.000 $15.400 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,032.000 $2.480 $2.000 $2.750 $3.270 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,032.000 $1.000 $0.550 $1.000 $1.100 $2.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 120.000 $4.560 $7.350 $4.000 $7.700 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 120.000 $1.000 $1.100 $1.000 $1.870 $8.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 3,300.000 $12.580 $5.250 $9.500 $12.000 $20.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 2,190.000 $7.230 $5.250 $12.500 $17.500 $30.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 20.000 $10.160 $21.000 $12.000 $17.500 $30.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 1,380.000 $6.390 $5.250 $8.000 $11.500 $20.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 1,740.000 $4.460 $5.250 $8.000 $17.000 $20.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 20.000 $7.620 $21.000 $15.000 $17.000 $20.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 3,300.000 $10.520 $5.250 $8.000 $12.000 $20.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 2,190.000 $6.000 $5.250 $8.000 $17.500 $20.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 20.000 $8.740 $21.000 $15.000 $17.500 $20.000
CONC CURB (MONO) (TY II)
LF 176.500 $10.000 $21.000 $9.000 $7.000 $35.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,186.000 $30.000 $21.180 $24.000 $20.630 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,500.000 $892.500 $1,200.000 $990.000 $1,850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,500.000 $2,231.250 $3,000.000 $2,183.500 $2,850.000
CRASH CUSH ATTEN (INSTL)
EA 1.000 $20,140.000 $16,800.000 $23,000.000 $15,345.000 $1,250.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,650.000 $1,500.000 $3,000.000 $1,980.000 $5,000.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $729.600 $750.000 $2,500.000 $880.000 $2,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $480.570 $572.250 $610.000 $600.000 $650.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 7.000 $476.470 $341.250 $370.000 $358.000 $650.000
REMOVE SM RD SN SUP&AM
EA 1.000 $76.910 $105.000 $150.000 $125.000 $50.000
RELOCATE LRSA
EA 3.000 $6,360.380 $3,675.000 $4,000.000 $3,850.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BR)
EA 19.000 $76.300 $47.250 $50.000 $50.000 $100.000
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND(BR)
EA 36.000 $87.000 $50.400 $54.000 $50.000 $100.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 20.000 $75.000 $52.500 $56.000 $50.000 $100.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 10,016.000 $0.600 $0.680 $0.720 $1.100 $0.500
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 6,863.000 $0.620 $0.680 $0.720 $1.100 $0.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 8.000 $150.000 $122.850 $129.000 $170.500 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $200.000 $137.550 $145.000 $192.500 $250.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 1.000 $500.000 $577.500 $620.000 $1,100.000 $250.000
PAVEMENT SEALER 4"
LF 17,665.000 $0.100 $0.040 $0.040 $0.170 $0.500
PAVEMENT SEALER 8"
LF 501.000 $0.430 $0.070 $0.080 $0.550 $0.500
PAVEMENT SEALER (ARROW)
EA 8.000 $33.600 $26.250 $27.500 $27.780 $250.000
PAVEMENT SEALER (WORD)
EA 2.000 $43.850 $31.500 $33.000 $49.780 $250.000
REFL PAV MRKR TY II-C-R
EA 92.000 $7.500 $3.150 $3.300 $5.500 $10.000
ELIM EXT PAV MRK & MRKS (4")
LF 1,196.000 $1.000 $1.050 $1.100 $1.100 $0.500
PAV SURF PREP FOR MRK (4")
LF 17,665.000 $0.250 $0.260 $0.280 $0.070 $0.500
PAV SURF PREP FOR MRK (8")
LF 501.000 $0.700 $0.530 $0.550 $0.280 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 8.000 $19.190 $15.750 $16.500 $27.500 $250.000
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $26.500 $21.000 $22.000 $38.500 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 110.000 $120.000 $189.000 $94.000 $100.000 $100.000
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 3,075.000 $1.000 $1.050 $1.100 $1.100 $0.500
MULTIPOLYMER PAV MRK (W)(4")(BRK)
LF 7,148.000 $1.060 $1.050 $1.100 $1.100 $0.500
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 501.000 $2.500 $2.100 $2.200 $2.200 $0.500
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 7,442.000 $1.000 $1.050 $1.100 $1.100 $0.500
Totals: $2,162,474.411 $1,869,823.096 $1,872,864.650 $2,096,384.317 $2,543,116.500