Bid Cobra

TARRANT US 287 (0172-09-033)

Items: 109

County: TARRANT
Length: N/A
Highway: US 287
District: FORT WORTH
Control Number: 0172-09-033
DBE Goal: N/A
Project: CC 172-9-33
Guaranty: N/A
Time: 277 WORKING DAYS
Engineer's Estimate: $4,609,429.85
Date: 11/03/2016 (9 years ago)
Contract Number: N/A
Type: GR,BS,DR,STR AND PAV
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$4,609,429.85
$4,196,348.59
Over/Under Est: -8.96% -$413,081.26
Over/Under Est: -0.64% -$29,651.60
Amt Left: 9.14% $383,429.66
Over/Under Est: 0.5% $22,912.76
Amt Left: 10.39% $435,994.02
Delta: -1.15% -$52,564.36
$4,776,777.30
Over/Under Est: 3.63% $167,347.45
Amt Left: 13.83% $580,428.71
Delta: -3.12% -$144,434.69
$5,300,538.85
Over/Under Est: 14.99% $691,109.00
Amt Left: 26.31% $1,104,190.26
Delta: -10.96% -$523,761.55
Over/Under Est: 17.68% $815,141.98
Amt Left: 29.27% $1,228,223.24
Delta: -2.34% -$124,032.98
$5,680,627.45
Over/Under Est: 23.24% $1,071,197.60
Amt Left: 35.37% $1,484,278.86
Delta: -4.72% -$256,055.62

Bid Items & Bid Tabulations

109 Total 0 of 109
TARRANT  |  US 287  |  FORT WORTH  |  0172-09-033  |  11/03/2016  |  $4,609,429.85  |  CC 172-9-33  |  GR,BS,DR,STR AND PAV  |  277 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
MCMAHON CONTRACTING, L.P.
RAGLE CONSTRUCTION, INC.
TEXAS-REYES GROUP LTD.
REBCON, INC.
LONE STAR CIVIL CONSTRUCTION, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 57.000 $3,000.000 $525.000 $3,024.190 $8,000.000 $3,200.000 $8,800.000 $12,500.000 $5,000.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 6,361.000 $10.000 $9.450 $8.640 $6.500 $15.000 $15.000 $7.000 $20.000
EXCAVATION (ROADWAY)
CY 16,800.000 $12.000 $3.150 $19.670 $16.000 $25.000 $24.000 $18.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,800.000 $11.000 $21.000 $26.180 $16.000 $35.000 $24.000 $50.000 $35.000
COMPOST MANUF TOPSOIL (4")
SY 16,550.000 $1.000 $1.580 $1.720 $0.930 $1.100 $3.040 $1.000 $3.000
BLOCK SODDING
SY 5,488.000 $3.500 $4.200 $2.850 $6.000 $4.000 $2.710 $4.000 $5.000
STRAW/HAY MLCH SEED(PERM)(URBAN)(CLAY)
SY 16,550.000 $1.000 $0.580 $0.440 $0.250 $0.550 $0.420 $0.400 $0.500
CELL FBR MLCH SEED(TEMP)(WARM)
SY 8,275.000 $1.000 $0.450 $0.700 $0.440 $0.500 $0.660 $0.650 $0.750
CELL FBR MLCH SEED(TEMP)(COOL)
SY 8,275.000 $1.000 $0.450 $0.710 $0.400 $0.510 $0.670 $0.650 $0.750
VEGETATIVE WATERING
MG 780.000 $25.000 $30.000 $19.620 $17.000 $25.000 $28.600 $19.000 $100.000
LIME (HYD, COM, OR QK(SLURRY))
TON 3,995.000 $160.000 $0.010 $10.000 $1.000 $1.000 $1.000 $1.000 $171.000
LIME TRT (EXIST MATL)(18")
SY 2,549.000 $3.000 $11.550 $9.990 $7.000 $9.000 $15.000 $9.000 $10.000
LIME TRT (SUBGRADE)(8")
SY 25,490.000 $6.000 $6.300 $7.240 $2.900 $8.000 $2.250 $5.000 $3.500
CEMENT
TON 100.000 $160.000 $180.000 $217.560 $185.000 $200.000 $225.000 $140.000 $171.000
CEMENT TREAT (SUBGRADE) (8")
SY 2,549.000 $5.000 $3.150 $5.880 $2.900 $6.000 $6.000 $7.000 $4.000
PRIME COAT (MULTI OPTION)
GAL 2,987.000 $5.000 $5.250 $4.060 $3.500 $4.000 $5.000 $3.750 $7.500
D-GR HMA TY-B PG64-22
TON 6,500.000 $75.000 $70.000 $69.600 $60.000 $70.000 $65.000 $65.000 $75.000
D-GR HMA TY-D PG70-28
TON 1,115.000 $72.000 $102.000 $107.420 $92.600 $100.000 $98.000 $100.000 $115.000
CONC PVMT (CONT REINF - CRCP) (8")
SY 13,768.000 $55.000 $84.000 $60.300 $75.000 $78.000 $82.500 $80.000 $60.000
TRENCH EXCAVATION PROTECTION
LF 1,168.000 $11.000 $1.050 $2.080 $1.000 $2.000 $1.000 $7.000 $3.000
SOIL NAIL ANCHORS
LF 8,756.000 $19.000 $17.000 $19.310 $12.750 $24.000 $17.000 $20.000 $25.000
DRILL SHAFT (30 IN)
LF 36.000 $200.000 $281.400 $310.880 $268.000 $425.000 $294.800 $225.000 $200.000
DRILL SHAFT (42 IN)
LF 30.000 $250.000 $395.850 $437.320 $377.000 $430.000 $414.700 $250.000 $300.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 128.000 $150.000 $129.150 $142.680 $123.000 $145.000 $135.300 $150.000 $150.000
RETAINING WALL (SOIL NAIL)(FACIA)
SF 3,800.000 $50.000 $63.000 $83.320 $60.000 $45.000 $75.280 $65.000 $42.000
CONCRETE PAINT FINISH
SF 3,335.000 $1.000 $1.000 $0.780 $0.350 $7.500 $1.000 $1.000 $2.000
RIPRAP (CONC)(4 IN)
CY 75.000 $500.000 $735.000 $861.230 $450.000 $625.000 $453.850 $450.000 $550.000
RIPRAP (CONC)(FLUME)
CY 30.000 $450.000 $735.000 $1,314.620 $525.000 $1,100.000 $600.000 $550.000 $650.000
RIPRAP (MOW STRIP)(4 IN)
CY 12.000 $555.000 $735.000 $1,003.760 $450.000 $850.000 $500.000 $750.000 $650.000
RC PIPE (CL III)(18 IN)
LF 1,014.000 $62.000 $63.000 $82.940 $100.000 $105.000 $51.000 $70.000 $68.000
RC PIPE (CL III)(24 IN)
LF 154.000 $75.000 $168.000 $111.610 $10.000 $150.000 $100.000 $90.000 $75.000
INLET(COMPL)(DROP)(TY 1)(1 GRATE)
EA 3.000 $4,500.000 $3,150.000 $5,220.000 $5,000.000 $8,100.000 $5,500.000 $7,300.000 $5,000.000
INLET (COMPL)(CURB)(TY 1)(10')
EA 1.000 $4,500.000 $7,350.000 $6,844.000 $5,000.000 $6,700.000 $7,000.000 $7,500.000 $5,000.000
INLET (COMPL)(DROP)(TY W-1)
EA 1.000 $4,500.000 $4,200.000 $6,380.000 $5,500.000 $7,000.000 $6,550.000 $4,500.000 $5,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 8.000 $1,500.000 $1,155.000 $1,218.780 $900.000 $1,650.000 $1,788.000 $3,000.000 $1,250.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,600.000 $1,785.000 $1,402.910 $1.000 $2,200.000 $1,799.000 $3,500.000 $2,000.000
ADJUSTING INLET (CAP)
EA 3.000 $1,260.000 $2,100.000 $4,176.000 $750.000 $3,500.000 $4,360.000 $3,000.000 $750.000
REMOV STR (INLET)
EA 1.000 $1,000.000 $630.000 $700.390 $1,000.000 $1,500.000 $6,500.000 $1,000.000 $1,500.000
REMOV STR (SET)
EA 4.000 $1,000.000 $630.000 $700.390 $600.000 $1,500.000 $500.000 $1,500.000 $1,500.000
MOBILIZATION
LS 1.000 $411,923.000 $360,000.000 $435,846.000 $458,000.000 $192,500.000 $500,000.000 $500,000.000 $560,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $11,000.000 $16,800.000 $3,497.580 $31,350.000 $6,500.000 $25,000.000 $25,000.000 $12,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 390.000 $20.000 $21.000 $25.520 $13.500 $21.500 $27.860 $30.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 390.000 $7.000 $8.400 $9.280 $7.750 $13.000 $8.730 $10.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 217.000 $4.000 $2.100 $2.610 $3.450 $5.000 $5.560 $7.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 217.000 $1.000 $0.270 $1.160 $2.000 $1.000 $1.200 $1.250 $2.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 393.000 $5.000 $4.200 $4.930 $4.000 $6.500 $6.340 $7.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 393.000 $1.000 $0.780 $0.580 $1.000 $1.000 $2.610 $3.000 $6.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,280.000 $50.000 $63.000 $82.890 $48.000 $75.000 $79.520 $72.000 $68.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 2,680.000 $50.000 $63.000 $76.540 $48.000 $76.000 $75.510 $70.000 $68.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 60.000 $55.000 $126.000 $95.110 $56.000 $116.000 $75.510 $90.000 $68.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 3,000.000 $8.000 $5.250 $9.670 $7.500 $16.000 $7.310 $8.000 $20.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 2,400.000 $8.000 $5.250 $11.360 $7.500 $16.250 $8.050 $10.000 $20.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 80.000 $8.000 $10.500 $15.580 $9.000 $30.000 $8.050 $25.000 $20.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 2,280.000 $10.000 $6.300 $8.890 $8.500 $21.000 $8.490 $10.000 $20.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 2,680.000 $10.000 $6.300 $10.480 $8.500 $19.000 $8.110 $13.000 $20.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 60.000 $10.000 $12.600 $24.040 $11.000 $38.500 $8.110 $38.000 $20.000
CONC CURB (MONO) (TY II)
LF 1,455.000 $10.000 $4.500 $2.240 $6.250 $9.000 $2.000 $7.000 $7.500
CURB RAMPS (TY 5)
EA 1.000 $2,000.000 $3,150.000 $1,566.000 $1,000.000 $2,500.000 $1,200.000 $2,200.000 $1,850.000
CURB RAMPS (TY 10)
EA 1.000 $2,000.000 $2,500.000 $1,566.000 $1,750.000 $2,500.000 $1,700.000 $2,800.000 $1,850.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,100.000 $20.000 $19.370 $18.910 $16.300 $19.500 $17.930 $20.000 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 7.000 $1,100.000 $1,164.290 $1,136.800 $980.000 $1,150.000 $1,078.000 $1,000.000 $1,800.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,200.000 $2,266.870 $2,523.000 $2,175.000 $2,650.000 $2,392.500 $2,000.000 $2,850.000
CRASH CUSH ATTEN (INSTL)
EA 3.000 $12,100.000 $12,600.000 $14,575.400 $12,565.000 $7,400.000 $13,821.500 $18,000.000 $15,000.000
CRASH CUSH ATTEN (REMOVE)
EA 3.000 $1,300.000 $945.000 $1,044.000 $900.000 $300.000 $990.000 $3,000.000 $7,500.000
ALUMINUM SIGNS (TY A)
SF 19.000 $35.000 $27.300 $30.160 $26.000 $30.000 $28.600 $30.000 $30.000
ALUMINUM SIGNS (TY G)
SF 310.000 $19.000 $21.530 $23.780 $20.500 $24.500 $22.550 $19.000 $30.000
ALUMINUM SIGNS (TY O)
SF 747.000 $21.000 $25.460 $28.130 $24.250 $30.000 $26.680 $22.000 $30.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $525.000 $572.250 $632.200 $545.000 $650.000 $600.000 $500.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 13.000 $590.000 $766.500 $846.800 $730.000 $875.000 $803.000 $650.000 $650.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $800.000 $918.750 $1,015.000 $875.000 $1,000.000 $963.000 $800.000 $650.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $925.000 $1,244.250 $1,374.600 $1,185.000 $1,300.000 $1,304.000 $1,000.000 $550.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 13.000 $325.000 $798.000 $881.600 $760.000 $900.000 $836.000 $300.000 $550.000
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $350.000 $929.250 $1,026.600 $885.000 $1,000.000 $973.500 $500.000 $550.000
REMOVE SM RD SN SUP&AM
EA 2.000 $100.000 $299.250 $330.600 $285.000 $325.000 $313.500 $100.000 $550.000
INSTALL LRSS (STRUCT STEEL)
LB 4,179.000 $5.550 $3.850 $4.260 $3.670 $4.250 $4.040 $4.000 $6.000
RELOCATE LRSA
EA 5.000 $1,500.000 $1,260.000 $1,392.000 $1,200.000 $1,250.000 $1,320.000 $3,300.000 $1,000.000
REMOVE LRSA
EA 6.000 $700.000 $598.500 $661.200 $570.000 $650.000 $575.000 $700.000 $2,500.000
INS OH SN SUP(35 FT CANT)
EA 2.000 $26,000.000 $16,117.500 $17,806.000 $15,350.000 $18,000.000 $16,885.000 $19,000.000 $20,000.000
INS OH SN SUP(65 FT BRDG)
EA 1.000 $33,000.000 $20,947.500 $23,142.000 $19,950.000 $23,000.000 $21,945.000 $27,000.000 $25,000.000
INS OH SN SUP(75 FT BRDG)
EA 1.000 $35,000.000 $23,310.000 $25,752.000 $22,200.000 $27,000.000 $24,420.000 $29,000.000 $30,000.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 19,913.000 $0.750 $0.630 $1.160 $1.000 $0.750 $0.660 $0.650 $2.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 7,837.000 $0.750 $0.630 $1.160 $1.000 $0.700 $0.660 $0.650 $2.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 9.000 $135.000 $105.000 $162.980 $140.500 $120.000 $110.000 $110.000 $200.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 7.000 $180.000 $127.050 $209.380 $180.500 $145.000 $133.100 $130.000 $200.000
PAVEMENT SEALER 4"
LF 27,669.000 $0.300 $0.040 $0.130 $0.110 $0.050 $0.040 $0.050 $0.250
PAVEMENT SEALER 8"
LF 5,411.000 $0.700 $0.070 $0.290 $0.250 $0.100 $0.080 $0.100 $0.500
PAVEMENT SEALER 12"
LF 1,188.000 $1.000 $0.120 $2.090 $1.800 $0.150 $0.120 $0.110 $2.000
PAVEMENT SEALER 24"
LF 303.000 $1.000 $0.230 $2.900 $2.500 $0.300 $0.240 $0.250 $3.000
PAVEMENT SEALER (ARROW)
EA 9.000 $30.000 $21.000 $35.380 $30.500 $24.000 $22.000 $21.000 $50.000
PAVEMENT SEALER (WORD)
EA 7.000 $35.000 $26.250 $58.580 $50.500 $30.000 $27.500 $26.000 $60.000
REFL PAV MRKR TY I-C
EA 14.000 $7.500 $5.250 $4.640 $4.000 $6.000 $5.500 $5.250 $5.000
REFL PAV MRKR TY II-C-R
EA 216.000 $7.500 $3.150 $4.640 $4.000 $3.750 $3.300 $3.250 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 23,755.000 $0.200 $0.320 $0.410 $0.350 $0.400 $0.330 $0.310 $0.500
ELIM EXT PAV MRK & MRKS (ARROW)
EA 6.000 $32.000 $15.750 $34.800 $30.000 $18.000 $16.500 $16.000 $50.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 4.000 $53.000 $18.900 $46.400 $40.000 $21.600 $19.800 $19.000 $50.000
PAV SURF PREP FOR MRK (4")
LF 27,669.000 $0.100 $0.110 $0.060 $0.050 $0.150 $0.110 $0.110 $0.200
PAV SURF PREP FOR MRK (8")
LF 5,411.000 $0.200 $0.160 $0.120 $0.100 $0.200 $0.170 $0.160 $0.200
PAV SURF PREP FOR MRK (12")
LF 1,188.000 $0.300 $1.050 $0.870 $0.750 $1.200 $1.100 $1.050 $1.000
PAV SURF PREP FOR MRK (24")
LF 303.000 $0.500 $2.100 $1.390 $1.200 $2.400 $2.200 $2.100 $1.500
PAV SURF PREP FOR MRK (ARROW)
EA 9.000 $15.000 $52.500 $18.270 $15.750 $60.000 $55.000 $52.000 $20.000
PAV SURF PREP FOR MRK (WORD)
EA 7.000 $35.000 $63.000 $41.470 $35.750 $72.000 $66.000 $65.000 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $175.000 $315.000 $350.000 $200.000 $935.000 $150.000 $1.100 $150.000
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 10,495.000 $1.000 $0.740 $0.510 $0.440 $0.850 $0.770 $0.750 $0.500
MULTIPOLYMER PAV MRK (W)(4")(BRK)
LF 3,273.000 $1.000 $0.790 $0.510 $0.440 $0.900 $0.830 $0.750 $0.500
MULTIPOLYMER PAV MRK (W)(4")(DOT)
LF 773.000 $1.000 $1.050 $2.320 $2.000 $1.200 $1.100 $1.000 $3.000
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 5,411.000 $1.500 $1.580 $1.510 $1.300 $1.800 $1.650 $1.250 $2.000
MULTIPOLYMER PAV MRK (W)(12")(SLD)
LF 1,188.000 $3.000 $4.730 $4.640 $4.000 $5.400 $4.950 $5.000 $5.000
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 303.000 $10.000 $9.450 $9.860 $8.500 $10.800 $9.900 $9.000 $9.000
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 13,128.000 $1.000 $0.740 $0.510 $0.440 $0.850 $0.770 $0.750 $0.650
Totals: $4,609,429.850 $4,196,348.590 $4,579,778.250 $4,632,342.610 $4,776,777.300 $5,300,538.850 $5,424,571.830 $5,680,627.450