TARRANT BU 287P (0172-01-055)

Items: 104

County: TARRANT
Length: 0.0000 MILES
Highway: BU 287P
District: FORT WORTH
Control Number: 0172-01-055
DBE Goal: 8.0%
Project: F 2025(292)
Guaranty: $200,000.00
Time: 278 WORKING DAYS
Engineer's Estimate: $16,105,101.22
Date: 03/04/2025 (1 year ago)
Contract Number: 3253033
Type: PREVENTIVE MAINTENANCE
Project ID: A00129824
Contract Type: Federal
Project Description: MILL & OVERLAY, FULL DEPTH REPAIR, UPGRADE LOOP DETECTION, CURB REPAIR, CLEANING & SEALING BRG JNTS, PAVEMENT MRKNGS, CLEANING DRNG INLETS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MARIBEL RANGEL
JUSTIN THOMEY
RAUL OROZCO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$16,105,101.22
$11,941,324.59
Over/Under Est: -25.85% -$4,163,776.63
$13,130,624.85
Over/Under Est: -18.47% -$2,974,476.37
Amt Left: 9.96% $1,189,300.26
Over/Under Est: -14.57% -$2,345,837.45
Amt Left: 15.22% $1,817,939.18
Delta: -4.79% -$628,638.92
Over/Under Est: -12.81% -$2,063,139.84
Amt Left: 17.59% $2,100,636.79
Delta: -2.05% -$282,697.61
Subcontractor Percentage Amount
LOLLAR CONSTRUCTION GROUP LLC 21.54% $2,702,711.24
CDM HOLDINGS 7.66% $961,131.29
LINEAR TRAFFIC MARKINGS LLC 2.27% $284,826.11
NORTEX CONCRETE LIFT & STABILIZATION, INC. 1.98% $248,438.64
MICA CORPORATION 1.01% $126,728.80
IBCTX, LLC 0.96% $120,455.10
WOOLERY CUSTOM FENCE CO. 0.95% $119,200.36
DURABLE SPECIALTIES, INC. 0.88% $110,417.17
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 0.87% $109,162.43
JNF BRIONES UTILITY CONTRACTING, LLC 0.47% $58,972.81
ACT SAW CUTTING & REMOVAL 0.41% $51,444.36
MOBILE ENTERPRISES, INC. 0.38% $47,680.14
BARRICADES UNLIMITED 0.22% $27,604.29
MAR-ZAP CONSTRUCTION, LLC 0.22% $27,604.29
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.07% $8,783.18
Total: 39.89% $5,005,160.21

Bid Items & Bid Tabulations

104 Total 0 of 104
TARRANT  |  BU 287P  |  FORT WORTH  |  0172-01-055  |  03/04/2025  |  $16,105,101.22  |  F 2025(292)  |  PREVENT MAINT  |  278 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
JAGOE-PUBLIC COMPANY
PEACHTREE CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 277.000 $150.000 $50.000 $100.000 $850.000 $662.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 1.000 $1,000.000 $5,000.000 $2,300.000 $1,900.000 $2,200.000
REMOV CONC (DRIVEWAYS)
SY 433.000 $30.000 $40.000 $45.000 $44.300 $45.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 58.000 $60.000 $40.000 $45.000 $44.300 $45.000
REMOV CONC (CURB)
LF 1,882.000 $20.000 $10.000 $11.000 $8.750 $9.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 2,211.000 $40.000 $12.000 $14.000 $13.300 $15.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 147.000 $10.000 $50.000 $10.000 $25.000 $20.000
RMV (0"-12") TRT/UNTRT BASE & ASPH PAV
CY 7,897.000 $15.000 $40.000 $30.000 $10.900 $12.000
EXCAV (SPECIAL)
CY 900.000 $75.000 $50.000 $30.000 $49.500 $52.000
EMBANK (FNL)(OC)(TY A)
CY 1,000.000 $120.000 $75.000 $35.000 $79.000 $85.000
EMBANK (FNL)(OC)(TY C)
CY 1,500.000 $110.000 $65.000 $50.000 $70.000 $72.000
BACKFILL (TY B)
STA 48.000 $371.920 $200.000 $800.000 $620.000 $650.000
COMPOST MANUF TOPSOIL (4")
SY 7,729.000 $8.000 $1.000 $8.000 $3.500 $2.620
BLOCK SODDING
SY 7,729.000 $16.000 $5.000 $6.000 $6.440 $6.750
VEGETATIVE WATERING
TGL 271.000 $260.000 $1.000 $100.000 $25.000 $70.000
ASPH (AC-20XP)
GAL 53,643.000 $5.430 $6.000 $6.500 $8.600 $5.000
AGGR (TY-PB, GR-5)(SAC-B)
CY 1,441.000 $500.000 $325.000 $275.000 $500.000 $513.370
D-GR HMA TY-D SAC-A PG64-22
TON 131.000 $275.000 $300.000 $200.000 $360.000 $255.000
SP MIXES SP-C SAC-A PG70-28
TON 24,682.000 $183.180 $170.000 $176.000 $171.000 $181.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 4,000.000 $80.000 $45.000 $50.000 $60.500 $67.000
PLANE & TEXT ASPH CONC PAV(0" TO 3")
SY 214,532.000 $6.000 $2.000 $3.000 $3.500 $3.170
FULL - DEPTH REPAIR CRCP (6")
CY 86.000 $1,200.000 $300.000 $900.000 $1,800.000 $1,900.000
FULL - DEPTH REPAIR CRCP (10")
CY 274.000 $1,500.000 $400.000 $800.000 $1,400.000 $1,500.000
TRENCH EXCAVATION PROTECTION
LF 846.000 $25.000 $2.000 $4.250 $1.000 $1.100
TEMPORARY SPL SHORING
SF 1,335.000 $20.000 $50.000 $60.000 $55.000 $55.000
RETAINING WALL (SPREAD FOOTING)
SF 5,370.000 $105.000 $83.000 $90.000 $75.500 $80.000
RIPRAP (CONC)(5 IN)
CY 30.000 $1,500.000 $750.000 $800.000 $703.000 $800.000
RIPRAP (CONC)(FLUME)
CY 1.000 $900.000 $2,500.000 $800.000 $2,215.000 $2,400.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 83.000 $250.000 $300.000 $360.000 $249.000 $260.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 468.000 $110.000 $40.000 $37.000 $23.250 $25.000
RAIL (HANDRAIL)(TY B)
LF 1,321.000 $225.000 $100.000 $75.000 $162.000 $136.000
HEADER TYPE EXPANSION JOINT
CF 65.000 $175.000 $500.000 $500.000 $545.000 $600.000
RC PIPE (CL III)(24 IN)
LF 775.000 $225.000 $200.000 $160.000 $101.000 $105.000
RC PIPE (CL III)(36 IN)
LF 24.000 $215.000 $400.000 $340.000 $360.000 $400.000
INLET (COMPL)(CO)(15 FT)(FTW)
EA 2.000 $15,000.000 $25,000.000 $26,000.000 $15,500.000 $16,000.000
INLET (COMPL)( CO)(20 FT)(FTW)
EA 1.000 $20,000.000 $25,000.000 $25,000.000 $21,000.000 $22,000.000
GRATE & FRAME
EA 100.000 $4,500.000 $1,700.000 $3,200.000 $4,650.000 $4,750.000
ADJUSTING MANHOLES
EA 28.000 $2,548.520 $2,000.000 $700.000 $1,800.000 $1,800.000
REMOV STR (INLET)
EA 1.000 $1,500.000 $5,000.000 $2,500.000 $1,100.000 $1,200.000
MOBILIZATION
LS 1.000 $1,445,367.040 $1,000,000.000 $1,450,000.000 $1,325,000.000 $1,404,003.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $20,000.000 $95,000.000 $50,000.000 $45,000.000 $65,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $25,000.000 $15,000.000 $25,000.000 $25,000.000 $17,000.000
TMA (STATIONARY)
DAY 454.000 $373.180 $1.000 $150.000 $150.000 $1.000
TMA (MOBILE OPERATION)
DAY 79.000 $380.940 $1.000 $150.000 $250.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,393.000 $4.000 $1.000 $3.250 $3.800 $4.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,393.000 $1.300 $1.000 $1.750 $1.300 $1.400
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,500.000 $7.180 $1.000 $5.000 $6.600 $7.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,500.000 $2.800 $1.000 $2.250 $1.700 $1.800
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 1,360.000 $85.000 $40.000 $45.000 $50.000 $44.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 120.000 $85.000 $60.000 $70.000 $75.000 $65.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 1,360.000 $19.000 $15.000 $17.000 $18.000 $16.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 120.000 $20.000 $20.000 $23.000 $24.000 $22.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 1,360.000 $29.000 $20.000 $23.000 $24.000 $22.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 120.000 $35.000 $30.000 $34.000 $35.000 $33.000
CONC CURB (TY II)
LF 1,882.000 $45.500 $32.000 $36.000 $43.500 $43.000
CONC CURB (MONO) (TY II)
LF 22.000 $20.000 $25.000 $28.000 $11.000 $11.000
CONC CURB & GUTTER (TY II)
LF 9,389.000 $50.000 $43.000 $60.000 $48.700 $50.000
CONC CURB (DOWEL)
LF 55.000 $35.000 $55.000 $60.000 $27.700 $28.000
CONC CURB & GUTTER (ARMOR CURB)
LF 462.000 $500.000 $215.000 $240.000 $245.000 $243.000
DRIVEWAYS (CONC)
SY 795.000 $170.000 $90.000 $120.000 $121.500 $125.000
CONC SIDEWALKS (4")
SY 5,903.000 $110.000 $72.000 $90.000 $88.500 $90.000
CURB RAMPS (TY 1)
SY 77.000 $375.000 $150.000 $370.000 $385.000 $387.000
CURB RAMPS (TY 2)
SY 94.000 $385.000 $100.000 $290.000 $385.000 $387.000
CURB RAMPS (TY 3)
SY 14.000 $200.000 $275.000 $400.000 $385.000 $387.000
CURB RAMPS (TY 7)
SY 84.000 $290.000 $100.000 $390.000 $321.000 $321.000
CURB RAMPS (TY 10)
SY 62.000 $220.000 $300.000 $360.000 $321.000 $321.000
CONC SIDEWALKS (SPECIAL)
SY 298.000 $550.000 $115.000 $280.000 $285.000 $282.000
PIPE UNDERDRAINS (TY 6) (6")
LF 1,306.000 $40.000 $45.000 $50.000 $49.800 $50.000
GROUND BOX TY D (162922)W/APRON
EA 1.000 $1,651.920 $7,000.000 $7,000.000 $7,000.000 $6,900.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $815.000 $600.000 $600.000 $700.000 $745.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,000.000 $1,000.000 $900.000 $1,000.000 $850.000
REMOVE SM RD SN SUP&AM
EA 10.000 $150.000 $100.000 $130.000 $140.000 $100.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 1.000 $380.000 $400.000 $550.000 $579.000 $330.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 1.000 $95.000 $25.000 $70.000 $75.000 $28.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 26,970.000 $2.230 $0.300 $0.400 $0.400 $0.350
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 470.000 $1.520 $0.900 $1.000 $1.000 $1.100
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 102,372.000 $1.270 $0.270 $0.400 $0.350 $0.320
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 11,738.000 $1.540 $0.550 $0.700 $0.640 $0.620
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 500.000 $6.000 $1.000 $2.000 $1.940 $1.100
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 7,428.000 $7.310 $2.500 $3.000 $3.040 $2.750
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 116.000 $115.850 $49.000 $90.000 $83.040 $60.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 112.000 $138.680 $40.000 $100.000 $94.110 $48.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 189,582.000 $0.730 $0.270 $0.400 $0.350 $0.330
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 2,140.000 $5.800 $3.500 $5.000 $4.930 $5.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 3,026.000 $4.960 $3.500 $5.000 $4.930 $5.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 235.000 $2.150 $0.800 $0.900 $0.890 $0.880
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,869.000 $2.240 $0.850 $1.000 $1.000 $0.930
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 250.000 $5.310 $3.000 $3.500 $3.320 $3.300
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 3,714.000 $11.430 $6.000 $7.000 $6.640 $6.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 58.000 $200.310 $139.000 $160.000 $154.990 $151.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 56.000 $246.170 $155.000 $190.000 $188.200 $169.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 13,485.000 $3.000 $0.600 $0.800 $0.740 $0.650
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 51,186.000 $2.340 $0.560 $0.700 $0.640 $0.610
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 94,791.000 $2.020 $0.550 $0.700 $0.640 $0.600
REFL PAV MRKR TY I-C
EA 970.000 $6.770 $4.000 $4.250 $4.040 $4.400
REFL PAV MRKR TY II-A-A
EA 1,513.000 $19.710 $4.000 $4.250 $4.040 $4.400
REMOVE TRAFFIC SIGNAL
EA 1.000 $3,500.000 $20,000.000 $6,000.000 $5,500.000 $5,500.000
DRAIN INLET CLEANING
EA 42.000 $521.750 $500.000 $1,300.000 $1,100.000 $1,150.000
RAIS AND UNDERSEAL CONC SLBS W FOAM SYS
LB 61,365.000 $7.500 $3.850 $4.500 $4.500 $4.700
VDS PROSR SYS
EA 1.000 $11,892.670 $5,000.000 $3,400.000 $3,300.000 $3,300.000
VDS ATSPM
EA 1.000 $2,500.000 $5,000.000 $3,400.000 $3,300.000 $3,300.000
VDS CABLING
LF 950.000 $3.000 $10.000 $5.000 $5.300 $5.250
VDS (HVDS) (VIVDS AND RVDS)
EA 3.000 $26,082.000 $5,000.000 $4,000.000 $4,000.000 $4,000.000
HIGHWAY TRAFFIC SIGNALS (COFW)
EA 1.000 $55,000.000 $50,000.000 $85,000.000 $89,000.000 $90,000.000
Totals: $16,105,101.220 $11,941,324.590 $13,130,624.850 $13,759,263.770 $14,041,961.380
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) $238,220.01
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $476,440.01
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $105,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,096,945.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $200,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $548,473.00
Total: $2,665,078.02