TARRANT BU 287P (0172-01-055)

Items: 101

County: TARRANT
Length: N/A
Highway: BU 287P
District: FORT WORTH
Control Number: 0172-01-055
DBE Goal: 800.0%
Project: F 2025(292)
Guaranty: N/A
Time: 192 WORKING DAYS
Engineer's Estimate: $16,079,037.44
Date: 12/03/2024 (1 year ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
MARIBEL RANGEL
JUSTIN THOMEY
RAUL OROZCO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$16,079,037.44
$14,389,594.52
Over/Under Est: -10.51% -$1,689,442.92
Over/Under Est: -5.16% -$830,210.99
Amt Left: 5.97% $859,231.93
Over/Under Est: -1.49% -$239,210.84
Amt Left: 10.08% $1,450,232.08
Delta: -3.88% -$591,000.15
$16,517,171.50
Over/Under Est: 2.72% $438,134.06
Amt Left: 14.79% $2,127,576.98
Delta: -4.28% -$677,344.90
$16,661,470.00
Over/Under Est: 3.62% $582,432.56
Amt Left: 15.79% $2,271,875.48
Delta: -0.87% -$144,298.50
Over/Under Est: 8.79% $1,413,111.81
Amt Left: 21.56% $3,102,554.73
Delta: -4.99% -$830,679.25

Bid Items & Bid Tabulations

101 Total 0 of 101
TARRANT  |  BU 287P  |  FORT WORTH  |  0172-01-055  |  12/03/2024  |  $16,079,037.44  |  F 2025(292)  |  PREVENT MAINT  |  192 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
PEACHTREE CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
JAGOE-PUBLIC COMPANY
FNH CONSTRUCTION, LLC
RAGLE CONSTRUCTION, INC.
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 1.000 $1,000.000 $5,000.000 $1,900.000 $2,064.000 $2,400.000 $10,000.000 $3,500.000
REMOV CONC (DRIVEWAYS)
SY 433.000 $30.000 $40.000 $44.300 $48.000 $50.000 $20.000 $23.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 58.000 $60.000 $40.000 $44.300 $48.000 $60.000 $50.000 $26.000
REMOV CONC (CURB)
LF 1,882.000 $20.000 $8.000 $8.750 $10.000 $35.000 $20.000 $6.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 2,211.000 $40.000 $12.000 $13.300 $14.000 $30.000 $20.000 $7.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 147.000 $10.000 $25.000 $25.000 $12.000 $40.000 $20.000 $14.000
RMV (0"-12") TRT/UNTRT BASE & ASPH PAV
CY 7,897.000 $15.000 $25.000 $10.900 $12.000 $30.000 $20.000 $5.000
EXCAV (SPECIAL)
CY 900.000 $75.000 $90.000 $49.500 $54.000 $60.000 $50.000 $100.000
EMBANK (FNL)(OC)(TY A)
CY 1,000.000 $120.000 $100.000 $79.000 $85.000 $110.000 $100.000 $150.000
EMBANK (FNL)(OC)(TY C)
CY 1,500.000 $110.000 $100.000 $60.000 $53.000 $90.000 $100.000 $150.000
BACKFILL (TY B)
STA 48.000 $371.920 $200.000 $620.000 $500.000 $250.000 $450.000 $1,600.000
COMPOST MANUF TOPSOIL (4")
SY 7,729.000 $8.000 $2.500 $7.950 $3.250 $4.500 $10.000 $9.700
BLOCK SODDING
SY 7,729.000 $16.000 $6.500 $6.400 $7.000 $18.000 $10.000 $15.000
VEGETATIVE WATERING
TGL 271.000 $260.000 $1.000 $25.000 $50.000 $90.000 $50.000 $55.000
ASPH (AC-20XP)
GAL 53,643.000 $5.430 $7.000 $8.800 $6.000 $8.000 $10.000 $6.000
AGGR (TY-PB, GR-5)(SAC-B)
CY 1,441.000 $500.000 $580.000 $500.000 $455.000 $350.000 $250.000 $350.000
D-GR HMA TY-D SAC-A PG64-22
TON 131.000 $275.000 $320.000 $360.000 $300.000 $150.000 $200.000 $400.000
SP MIXES SP-C SAC-A PG70-28
TON 24,682.000 $183.180 $196.000 $165.000 $180.000 $165.000 $185.000 $200.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 4,000.000 $80.000 $40.000 $64.000 $65.000 $60.000 $85.000 $50.000
PLANE & TEXT ASPH CONC PAV(0" TO 3")
SY 214,532.000 $6.000 $2.300 $3.250 $3.100 $4.000 $6.000 $7.000
FULL - DEPTH REPAIR CRCP (10")
CY 1,500.000 $450.000 $250.000 $1,425.000 $1,200.000 $1,000.000 $1,000.000 $1,117.000
TRENCH EXCAVATION PROTECTION
LF 846.000 $25.000 $2.000 $1.000 $1.250 $4.500 $10.000 $1.000
TEMPORARY SPL SHORING
SF 1,335.000 $20.000 $65.000 $55.000 $60.000 $49.000 $85.000 $60.000
RETAINING WALL (SPREAD FOOTING)
SF 5,370.000 $105.000 $100.000 $76.500 $83.000 $130.000 $85.000 $68.000
RIPRAP (CONC)(5 IN)
CY 30.000 $1,500.000 $750.000 $703.000 $900.000 $1,200.000 $650.000 $788.000
RIPRAP (CONC)(FLUME)
CY 1.000 $900.000 $3,000.000 $2,215.000 $2,500.000 $2,500.000 $2,500.000 $1,415.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 83.000 $250.000 $300.000 $249.000 $300.000 $450.000 $185.000 $290.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 468.000 $110.000 $40.000 $24.300 $35.000 $36.000 $100.000 $26.000
RAIL (HANDRAIL)(TY B)
LF 1,321.000 $225.000 $90.000 $158.500 $200.000 $150.000 $185.000 $85.000
HEADER TYPE EXPANSION JOINT
CF 65.000 $175.000 $550.000 $548.000 $325.000 $400.000 $850.000 $245.000
RC PIPE (CL III)(24 IN)
LF 775.000 $225.000 $125.000 $101.000 $112.000 $130.000 $165.000 $85.000
RC PIPE (CL III)(36 IN)
LF 24.000 $215.000 $325.000 $360.000 $400.000 $300.000 $200.000 $186.000
INLET (COMPL)(CO)(15 FT)(FTW)
EA 2.000 $15,000.000 $25,000.000 $15,500.000 $20,000.000 $30,000.000 $15,000.000 $12,000.000
INLET (COMPL)( CO)(20 FT)(FTW)
EA 1.000 $20,000.000 $25,000.000 $21,000.000 $25,000.000 $32,000.000 $25,000.000 $10,500.000
GRATE & FRAME
EA 100.000 $4,500.000 $5,000.000 $4,650.000 $5,300.000 $2,000.000 $8,500.000 $3,400.000
ADJUSTING MANHOLES
EA 28.000 $2,548.520 $3,000.000 $1,800.000 $2,000.000 $2,000.000 $2,500.000 $1,200.000
MOBILIZATION
LS 1.000 $1,445,367.040 $1,400,000.000 $1,350,000.000 $1,583,596.000 $1,804,204.000 $1,650,000.000 $1,590,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $20,000.000 $130,000.000 $35,000.000 $61,000.000 $100,000.000 $15,000.000 $200,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $25,000.000 $50,000.000 $25,000.000 $20,000.000 $40,000.000 $16,500.000 $30,000.000
TMA (STATIONARY)
DAY 283.000 $373.180 $1.000 $150.000 $375.000 $500.000 $250.000 $345.000
TMA (MOBILE OPERATION)
DAY 79.000 $380.940 $1.000 $250.000 $1.150 $500.000 $550.000 $680.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,393.000 $4.000 $1.000 $3.050 $5.000 $4.000 $4.000 $3.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,393.000 $1.300 $1.000 $1.850 $1.220 $1.000 $2.000 $1.250
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,500.000 $7.180 $1.000 $4.750 $6.550 $10.000 $18.000 $3.650
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,500.000 $2.800 $1.000 $2.100 $1.220 $1.000 $9.000 $1.250
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 1,360.000 $85.000 $40.000 $52.000 $50.000 $120.000 $100.000 $40.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 120.000 $85.000 $50.000 $78.000 $72.000 $120.000 $100.000 $40.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 1,360.000 $19.000 $15.000 $19.000 $20.000 $18.000 $20.000 $9.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 120.000 $20.000 $20.000 $26.000 $25.000 $18.000 $20.000 $9.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 1,360.000 $29.000 $20.000 $26.000 $25.000 $18.000 $20.000 $9.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 120.000 $35.000 $20.000 $39.000 $40.000 $18.000 $20.000 $9.000
CONC CURB (TY II)
LF 1,882.000 $45.500 $45.000 $43.500 $51.000 $60.000 $45.000 $14.000
CONC CURB (MONO) (TY II)
LF 22.000 $20.000 $55.000 $11.000 $13.000 $60.000 $100.000 $37.000
CONC CURB & GUTTER (TY II)
LF 9,389.000 $50.000 $57.000 $57.600 $66.000 $65.000 $65.000 $35.000
CONC CURB (DOWEL)
LF 55.000 $35.000 $55.000 $27.700 $31.000 $75.000 $75.000 $30.000
CONC CURB & GUTTER (ARMOR CURB)
LF 462.000 $500.000 $320.000 $245.000 $280.000 $400.000 $250.000 $208.000
DRIVEWAYS (CONC)
SY 795.000 $170.000 $95.000 $121.500 $160.000 $175.000 $100.000 $200.000
CONC SIDEWALKS (4")
SY 5,903.000 $110.000 $75.000 $88.500 $103.000 $70.000 $65.000 $85.000
CURB RAMPS (TY 1)
SY 77.000 $375.000 $200.000 $385.000 $500.000 $360.000 $500.000 $181.000
CURB RAMPS (TY 2)
SY 94.000 $385.000 $166.000 $385.000 $500.000 $270.000 $500.000 $174.000
CURB RAMPS (TY 3)
SY 14.000 $200.000 $250.000 $385.000 $500.000 $340.000 $500.000 $216.000
CURB RAMPS (TY 7)
SY 84.000 $290.000 $205.000 $321.000 $365.000 $330.000 $500.000 $171.000
CURB RAMPS (TY 10)
SY 62.000 $220.000 $210.000 $321.000 $365.000 $190.000 $500.000 $181.000
CONC SIDEWALKS (SPECIAL)
SY 298.000 $550.000 $175.000 $285.000 $325.000 $430.000 $100.000 $151.000
PIPE UNDERDRAINS (TY 6) (6")
LF 1,306.000 $40.000 $45.000 $49.800 $56.000 $10.000 $45.000 $45.000
GROUND BOX TY D (162922)W/APRON
EA 1.000 $1,651.920 $4,750.000 $5,300.000 $6,000.000 $5,000.000 $1,500.000 $1,610.050
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $815.000 $570.000 $830.000 $755.000 $860.000 $1,500.000 $575.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,000.000 $870.000 $1,100.000 $1,200.000 $1,300.000 $1,500.000 $775.000
REMOVE SM RD SN SUP&AM
EA 10.000 $150.000 $100.000 $161.000 $145.000 $160.000 $650.000 $150.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 1.000 $380.000 $390.000 $579.000 $700.000 $780.000 $100.000 $300.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 1.000 $95.000 $25.000 $26.900 $135.000 $150.000 $100.000 $200.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 26,970.000 $2.230 $0.380 $1.550 $0.460 $0.600 $0.500 $1.000
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 470.000 $1.520 $0.900 $2.300 $2.270 $3.000 $1.000 $1.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 102,372.000 $1.270 $0.350 $1.350 $0.390 $0.500 $0.500 $1.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 11,738.000 $1.540 $0.580 $1.500 $0.940 $1.000 $1.000 $1.000
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 500.000 $6.000 $1.750 $5.500 $4.660 $6.000 $6.000 $4.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 7,428.000 $7.310 $2.750 $9.750 $7.870 $10.000 $20.000 $6.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 116.000 $115.850 $55.000 $155.000 $119.000 $150.000 $250.000 $100.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 112.000 $138.680 $60.000 $185.000 $142.000 $170.000 $250.000 $50.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 189,582.000 $0.730 $0.350 $1.350 $0.390 $0.500 $0.500 $1.200
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 2,140.000 $5.800 $3.800 $6.750 $6.000 $7.000 $6.000 $5.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 3,026.000 $4.960 $3.800 $6.750 $6.000 $7.000 $6.000 $5.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 235.000 $2.150 $0.800 $2.000 $3.600 $4.000 $3.000 $1.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,869.000 $2.240 $0.900 $1.200 $2.000 $2.500 $6.000 $2.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 250.000 $5.310 $3.000 $4.500 $7.250 $8.000 $6.000 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 3,714.000 $11.430 $6.000 $8.000 $13.000 $15.000 $20.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 58.000 $200.310 $140.000 $185.000 $222.000 $1,800.000 $250.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 56.000 $246.170 $170.000 $225.000 $305.000 $350.000 $250.000 $200.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 13,485.000 $3.000 $0.600 $0.850 $1.200 $1.500 $1.000 $2.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 51,186.000 $2.340 $0.580 $0.750 $1.100 $1.000 $1.000 $2.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 94,791.000 $2.020 $0.600 $0.750 $1.000 $1.000 $1.000 $1.000
REFL PAV MRKR TY I-C
EA 970.000 $6.770 $4.000 $5.700 $8.000 $9.000 $6.000 $60.000
REFL PAV MRKR TY II-A-A
EA 1,513.000 $19.710 $4.000 $5.700 $8.000 $9.000 $6.000 $60.000
REMOVE TRAFFIC SIGNAL
EA 1.000 $3,500.000 $5,000.000 $7,500.000 $6,000.000 $10,000.000 $10,000.000 $2,500.000
DRAIN INLET CLEANING
EA 42.000 $521.750 $1,500.000 $1,100.000 $1,200.000 $1,400.000 $500.000 $1,500.000
RAIS AND UNDERSEAL CONC SLBS W FOAM SYS
LB 61,365.000 $7.500 $3.000 $4.500 $6.000 $8.000 $6.000 $3.850
VDS PROSR SYS
EA 1.000 $11,892.670 $16,100.000 $17,500.000 $22,000.000 $30,000.000 $35,000.000 $32,100.800
VDS ATSPM
EA 1.000 $2,500.000 $9,800.000 $10,800.000 $12,000.000 $10,000.000 $15,000.000 $5,500.000
VDS CABLING
LF 950.000 $3.000 $7.000 $7.700 $9.000 $5.000 $3.000 $5.000
VDS (HVDS) (VIVDS AND RVDS)
EA 3.000 $26,082.000 $10,600.000 $11,700.000 $13,000.000 $15,000.000 $30,000.000 $12,000.000
HIGHWAY TRAFFIC SIGNALS (COFW)
EA 1.000 $55,000.000 $55,500.000 $61,500.000 $68,000.000 $100,000.000 $165,000.000 $50,000.000
Totals: $16,079,037.440 $14,389,594.520 $15,248,826.450 $15,839,826.600 $16,517,171.500 $16,661,470.000 $17,492,149.250