TARRANT SH 199 (0171-05-096)
Items: 85
County: TARRANT
Length: 4.5880 MILES
Highway: SH 199
District: FORT WORTH
Control Number: 0171-05-096
DBE Goal: 0.0%
Project: C 171-5-96
Guaranty: $100,000.00
Time: 161 WORKING DAYS
Engineer's Estimate: $9,912,447.25
Date: 09/04/2025 (9 months ago)
Contract Number: 9253008
Type: RESURFACE ROADWAY
Project ID: A00058987
Project Description: REPAIR BASE FAILURES, MILL, HMAC OVERLAY, PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
RAUL OROZCO
TARRANT SH 199 (0171-05-096)
Project Name: N/A
Project: C 171-5-96
Length: 4.5880 MILES
Project Type: CONSTRUCTION
Limits From: PAUL MEADOR RD/NW CENTER DR.
Limits To: NORTHSIDE CENTER
Project Description: REPAIR BASE FAILURES, MILL, HMAC OVERLAY, PAVEMENT MARKINGS
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$9,912,447.25 | |||
| $8,888,715.70 |
-10.33%
-$1,023,731.55
|
|||
| $9,029,404.70 |
-8.91%
-$883,042.55
|
1.58%
$140,689.00
|
||
| $9,677,139.16 |
-2.37%
-$235,308.09
|
8.87%
$788,423.46
|
-7.17%
-$647,734.46
|
|
| $9,925,768.57 |
0.13%
$13,321.32
|
11.67%
$1,037,052.87
|
-2.57%
-$248,629.41
|
|
| $9,983,894.67 |
0.72%
$71,447.42
|
12.32%
$1,095,178.97
|
-0.59%
-$58,126.10
|
|
| $10,742,540.69 |
8.37%
$830,093.44
|
20.86%
$1,853,824.99
|
-7.60%
-$758,646.02
|
|
| $11,129,057.50 |
12.27%
$1,216,610.25
|
25.2%
$2,240,341.80
|
-3.60%
-$386,516.81
|
E
Engineer's Estimate
$9,912,447.25
1
Awarded
$8,888,715.70
Over/Under Est:
-10.33%
-$1,023,731.55
$9,029,404.70
Over/Under Est:
-8.91%
-$883,042.55
Amt Left:
1.58%
$140,689.00
$9,677,139.16
Over/Under Est:
-2.37%
-$235,308.09
Amt Left:
8.87%
$788,423.46
Delta:
-7.17%
-$647,734.46
$9,925,768.57
Over/Under Est:
0.13%
$13,321.32
Amt Left:
11.67%
$1,037,052.87
Delta:
-2.57%
-$248,629.41
$9,983,894.67
Over/Under Est:
0.72%
$71,447.42
Amt Left:
12.32%
$1,095,178.97
Delta:
-0.59%
-$58,126.10
$10,742,540.69
Over/Under Est:
8.37%
$830,093.44
Amt Left:
20.86%
$1,853,824.99
Delta:
-7.60%
-$758,646.02
$11,129,057.50
Over/Under Est:
12.27%
$1,216,610.25
Amt Left:
25.2%
$2,240,341.80
Delta:
-3.60%
-$386,516.81
| Subcontractor | Percentage | Amount |
|---|---|---|
| FORTSON CONTRACTING, INC. | 0.00% | $0.00 |
| HILBASH INVESTMENT LLC | 0.00% | $0.00 |
| IBCTX, LLC | 0.00% | $0.00 |
| LINEAR TRAFFIC MARKINGS LLC | 0.00% | $0.00 |
| SITE PARTNERS, LLC | 0.00% | $0.00 |
| STRAIGHT LINE SAWING & SEALING, INC. | 0.00% | $0.00 |
| SYNERGY SIGNS & SERVICES LLC | 0.00% | $0.00 |
| USA SWPPP INSPECTIONS, INC.DBA USA EROSION | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
85
Total
0 of 85
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $50,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $30,000.00 |
| Total: | $100,000.00 |