Show Job Controls
Bid Cobra

TARRANT SH 10 (0094-02-147)

Items: 52

County: TARRANT
Length: 0.0000 MILES
Highway: SH 10
District: FORT WORTH
Control Number: 0094-02-147
DBE Goal: 0.0%
Project: F 2026(494)
Guaranty: $100,000.00
Time: 80 WORKING DAYS
Engineer's Estimate: $5,591,881.98
Date: 04/08/2026 (2 months ago)
Contract Number: 4263214
Type: RESURFACE ROADWAY
Project ID: A00211468
Contract Type: Federal
Project Description: MILL AND OVERLAY CONSISTING OF BASE REPAIR, MBGF AND PAVEMENT MARKINGS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
SURAFEL SINTAYEHU
JASON PASCOE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$5,591,881.98
$5,358,724.17
Over/Under Est: -4.17% -$233,157.81
Over/Under Est: 0.98% $54,683.51
Amt Left: 5.37% $287,841.32
$5,869,310.24
Over/Under Est: 4.96% $277,428.26
Amt Left: 9.53% $510,586.07
Delta: -3.94% -$222,744.75
Over/Under Est: 15.67% $876,305.95
Amt Left: 20.7% $1,109,463.76
Delta: -10.20% -$598,877.69
Over/Under Est: 21.41% $1,197,465.25
Amt Left: 26.7% $1,430,623.06
Delta: -4.97% -$321,159.30
$7,669,358.12
Over/Under Est: 37.15% $2,077,476.14
Amt Left: 43.12% $2,310,633.95
Delta: -12.96% -$880,010.89
Over/Under Est: 43.81% $2,449,609.21
Amt Left: 50.06% $2,682,767.02
Delta: -4.85% -$372,133.07

Bid Items & Bid Tabulations

52 Total 0 of 52
TARRANT  |  SH 10  |  FORT WORTH  |  0094-02-147  |  04/08/2026  |  $5,591,881.98  |  F 2026(494)  |  RESURF ROADWAY  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EUROVIA ATLANTIC COAST LLC
AUSTIN BRIDGE & ROAD SERVICES, LP
JAGOE-PUBLIC COMPANY
PEACHTREE CONSTRUCTION, LTD.
RAGLE CONSTRUCTION, INC.
OVERLAND CORPORATION
TEXAS MATERIALS GROUP, INC.
REMOV CONC (CURB OR CURB & GUTTER)
LF 200.000 $18.330 $21.000 $21.000 $15.250 $23.000 $6.040 $41.000 $23.000
EMBANK (FNL)(OC)(TY B)
CY 10.000 $75.000 $200.000 $200.000 $105.000 $215.000 $300.000 $61.000 $219.000
ASPH (AC-20-5TR)
GAL 58,204.000 $4.500 $4.650 $5.250 $5.500 $4.650 $6.500 $5.250 $5.000
AGGR (TY-B, GR-4)(SAC-B)
CY 1,392.000 $172.000 $186.000 $105.000 $110.000 $185.000 $225.000 $105.000 $355.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 4,404.000 $125.000 $112.000 $120.210 $125.000 $157.000 $113.000 $156.430 $153.000
SP MIXES SP-C SAC-A PG70-28
TON 22,018.000 $145.000 $131.000 $147.930 $142.000 $158.000 $155.500 $189.000 $210.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 756.000 $68.000 $105.000 $102.520 $90.000 $120.000 $167.000 $142.000 $130.000
PLANE ASPH CONC PAV (2" TO 4 1/2")
SY 153,169.000 $1.800 $2.770 $1.090 $3.000 $3.150 $1.650 $5.000 $3.350
FULL-DEPTH REPAIR CRCP (8"-10")
SY 504.000 $208.000 $203.000 $203.000 $215.000 $227.000 $302.000 $219.490 $265.000
RIPRAP (MOW STRIP)(4 IN)
CY 31.000 $625.000 $794.000 $685.000 $1,150.000 $740.000 $638.900 $687.720 $750.000
MOBILIZATION
LS 1.000 $508,353.000 $295,000.000 $621,122.200 $641,000.000 $485,000.000 $670,000.000 $765,000.000 $613,639.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $35,500.000 $34,599.140 $25,000.000 $25,500.000 $100,000.000 $32,465.000 $45,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $17,500.000 $130.000 $20,000.000 $15,000.000 $20,000.000 $18,500.000 $9,000.000
TMA (STATIONARY)
DAY 160.000 $170.000 $320.000 $1.000 $25.000 $150.000 $287.000 $1,000.000 $428.000
TMA (MOBILE OPERATION)
DAY 15.000 $175.000 $700.000 $1.500 $335.000 $475.000 $616.000 $5.000 $0.110
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 780.000 $4.800 $4.000 $4.750 $5.000 $8.500 $4.750 $4.750 $8.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 780.000 $1.500 $2.000 $1.000 $1.000 $2.250 $1.000 $1.000 $2.200
CONC CURB & GUTTER (TY II)
LF 200.000 $40.000 $69.000 $69.000 $65.000 $75.000 $30.000 $70.690 $75.000
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $30.000 $28.000 $24.000 $28.570 $30.000 $28.000 $28.350 $31.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,550.000 $1,200.000 $1,300.000 $1,225.000 $1,300.000 $1,200.000 $1,214.940 $1,314.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 1.000 $1,350.000 $1,125.000 $1,200.000 $1,148.000 $1,225.000 $1,125.000 $1,139.010 $1,232.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $3.500 $3.000 $3.000 $3.050 $3.250 $3.000 $3.040 $3.280
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $250.000 $200.000 $300.000 $204.000 $215.000 $200.000 $202.490 $219.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,280.000 $2,950.000 $3,100.000 $3,300.000 $3,200.000 $2,950.000 $2,986.730 $3,230.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 4,576.000 $0.450 $0.250 $0.250 $0.260 $0.880 $0.500 $0.250 $0.270
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 30,885.000 $0.360 $0.190 $0.190 $0.190 $0.900 $0.450 $0.190 $0.200
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 9,309.000 $0.650 $0.370 $0.370 $0.380 $1.400 $0.600 $0.370 $0.390
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 46.000 $1.350 $1.000 $1.000 $1.020 $4.250 $2.000 $1.000 $1.070
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 1,336.000 $2.800 $2.000 $2.000 $2.040 $7.000 $3.200 $2.000 $2.150
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 98.000 $85.000 $25.000 $25.000 $25.510 $130.000 $50.000 $25.000 $26.800
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 98.000 $75.000 $28.000 $28.000 $28.570 $150.000 $60.000 $28.000 $30.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 30,100.000 $0.360 $0.200 $0.200 $0.200 $0.950 $0.450 $0.200 $0.210
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,576.000 $1.200 $1.650 $0.500 $2.030 $4.500 $2.370 $1.000 $1.200
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 171.000 $1.330 $1.000 $1.000 $1.020 $1.850 $1.000 $1.000 $1.070
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 9,566.000 $1.010 $0.790 $0.790 $0.810 $1.000 $0.900 $0.790 $0.840
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 47.000 $3.500 $3.000 $3.000 $3.060 $4.250 $4.000 $3.000 $3.200
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,350.000 $6.440 $6.290 $6.290 $6.420 $7.500 $7.100 $6.290 $6.740
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 98.000 $150.000 $145.000 $145.000 $147.960 $145.000 $150.000 $145.000 $155.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 98.000 $170.000 $150.000 $150.000 $153.060 $175.000 $170.000 $150.000 $160.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 577.000 $3.500 $2.750 $2.750 $2.810 $4.000 $4.000 $2.750 $2.950
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 15,400.000 $0.650 $0.520 $0.520 $0.530 $0.750 $0.690 $0.520 $0.550
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 31,197.000 $0.660 $0.510 $0.510 $0.520 $0.650 $0.670 $0.510 $0.540
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 30,406.000 $0.600 $0.510 $0.510 $0.520 $0.650 $0.670 $0.510 $0.540
PAVEMENT SLER 6"
LF 61,603.000 $0.220 $0.110 $0.110 $0.110 $0.200 $0.200 $0.110 $0.120
PAVEMENT SLER 8"
LF 9,566.000 $0.650 $0.150 $0.150 $0.150 $0.300 $0.250 $0.150 $0.160
PAVEMENT SLER 12"
LF 47.000 $0.800 $0.500 $0.500 $0.510 $0.900 $1.000 $0.500 $0.530
PAVEMENT SLER 24"
LF 1,350.000 $2.100 $0.600 $0.600 $0.610 $1.550 $2.000 $0.600 $0.640
PAVEMENT SLER (ARROW)
EA 98.000 $50.000 $9.000 $9.000 $9.180 $30.000 $30.000 $9.000 $9.650
PAVEMENT SLER (WORD)
EA 98.000 $60.000 $9.000 $9.000 $9.180 $36.000 $40.000 $9.000 $9.650
REFL PAV MRKR TY I-C
EA 526.000 $4.000 $3.500 $3.500 $3.570 $5.250 $4.000 $3.500 $3.750
REFL PAV MRKR TY II-C-R
EA 959.000 $4.240 $3.490 $3.490 $3.560 $5.250 $4.000 $3.490 $0.370
EXISTING MANHOLE ADJUSTMENTS
EA 9.000 $2,250.000 $2,000.000 $2,000.000 $650.000 $2,150.000 $1,162.000 $750.980 $1,070.000
Totals: $5,591,881.980 $5,358,724.170 $5,646,565.490 $5,869,310.240 $6,468,187.930 $6,789,347.230 $7,669,358.120 $8,041,491.190
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $25,000.00