Bid Cobra

TARRANT SH 183 (0094-02-145)

Items: 48

County: TARRANT
Length: N/A
Highway: SH 183
District: FORT WORTH
Control Number: 0094-02-145
DBE Goal: N/A
Project: F 2023(174)
Guaranty: N/A
Time: 56 WORKING DAYS
Engineer's Estimate: $888,966.43
Date: 11/02/2022 (3 years ago)
Contract Number: N/A
Type: EMBANKMENT STABILIZATION
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$888,966.43
$857,399.06
Over/Under Est: -3.55% -$31,567.37
$877,712.00
Over/Under Est: -1.27% -$11,254.43
Amt Left: 2.37% $20,312.94
Over/Under Est: 14.17% $125,966.67
Amt Left: 18.37% $157,534.04
Delta: -15.63% -$137,221.10
$1,158,242.75
Over/Under Est: 30.29% $269,276.32
Amt Left: 35.09% $300,843.69
Delta: -14.12% -$143,309.65

Bid Items & Bid Tabulations

48 Total 0 of 48
TARRANT  |  SH 183  |  FORT WORTH  |  0094-02-145  |  11/02/2022  |  $888,966.43  |  F 2023(174)  |  EMBANKMENT STABILIZATION  |  56 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
IBCTX, LLC
GIBSON & ASSOCIATES, INC.
FNH CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 462.000 $25.000 $10.000 $50.000 $35.750 $50.000
REMOVING CONCRETE(MOW STRIP)
LF 135.000 $15.000 $6.000 $50.000 $22.000 $50.000
EXCAVATION (SPECIAL)
CY 1,425.000 $30.000 $34.000 $40.000 $94.600 $30.000
EXCAVATION (ROADWAY AND CHANNEL)
CY 4.100 $20.000 $158.000 $500.000 $440.000 $50.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,425.000 $45.000 $40.000 $40.000 $128.700 $40.000
BLOCK SODDING
SY 225.000 $10.000 $10.000 $20.000 $8.800 $10.000
VEGETATIVE WATERING
MG 7.900 $20.000 $182.000 $350.000 $330.000 $550.000
FLOWABLE BACKFILL
CY 50.000 $300.000 $197.000 $500.000 $462.000 $350.000
TEMPORARY SPL SHORING
SF 1,330.000 $35.000 $39.000 $20.000 $31.900 $85.000
SOIL NAIL ANCHORS
LF 6,030.000 $55.000 $41.850 $30.000 $28.440 $65.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 30.000 $200.000 $495.000 $500.000 $426.800 $350.000
CL A CONC (FLUME)
CY 10.000 $800.000 $827.000 $1,000.000 $1,100.000 $2,000.000
RETAINING WALL (SOIL NAIL)(FACIA)
SF 2,100.000 $35.000 $16.500 $35.000 $28.500 $45.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 51.786 $475.000 $626.000 $1,000.000 $1,100.000 $850.000
RIPRAP (MOW STRIP)(4 IN)
CY 15.061 $700.000 $715.000 $1,000.000 $1,100.000 $650.000
RIPRAP (CONC) (CHANNEL) (4IN)
CY 24.360 $900.000 $662.000 $1,000.000 $1,100.000 $750.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 304.000 $45.000 $36.000 $50.000 $46.000 $100.000
RESIZING AND SEALING JOINTS
LF 60.000 $75.000 $36.000 $50.000 $70.000 $100.000
MOBILIZATION
LS 1.000 $80,815.130 $85,500.000 $87,000.000 $120,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $20,000.000 $10,000.000 $8,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 60.000 $35.000 $21.000 $30.000 $23.100 $30.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 60.000 $60.000 $55.000 $70.000 $60.500 $40.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $9.000 $8.500 $10.000 $9.350 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 225.000 $50.000 $24.000 $30.000 $26.400 $60.000
CONSTRUCTION EXITS (REMOVE)
SY 225.000 $20.000 $7.000 $10.000 $7.700 $30.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 150.000 $3.000 $3.000 $10.000 $3.300 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 150.000 $2.000 $0.750 $3.000 $0.830 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 25.000 $10.000 $4.000 $10.000 $4.400 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 25.000 $1.750 $1.000 $3.000 $1.100 $9.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 200.000 $15.000 $60.000 $150.000 $50.000 $65.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 40.000 $18.000 $60.000 $150.000 $50.000 $65.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 200.000 $15.000 $15.500 $50.000 $50.000 $30.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 40.000 $18.000 $27.000 $50.000 $50.000 $30.000
CONC CURB (MONO) (TY II)
LF 35.000 $45.000 $36.000 $50.000 $15.000 $55.000
MTL W-BEAM GD FEN (TIM POST)
LF 225.000 $35.000 $20.750 $23.000 $22.830 $40.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $3,000.000 $1,100.000 $1,200.000 $1,210.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 225.000 $5.000 $2.750 $5.000 $3.030 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $500.000 $150.000 $165.000 $165.000 $500.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $300.000 $120.000 $135.000 $132.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,600.000 $2,800.000 $3,100.000 $3,080.000 $3,000.000
CONDT (PVC) (SCH 40) (2")
LF 475.000 $8.500 $22.000 $12.000 $11.000 $20.000
ELEC CONDR (NO.8) BARE
LF 1,180.000 $1.500 $2.450 $3.000 $1.970 $6.000
ELEC CONDR (NO.8) INSULATED
LF 2,360.000 $1.750 $3.000 $3.000 $2.010 $6.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 1.000 $30.000 $20.000 $25.000 $22.000 $50.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 4.000 $55.000 $25.000 $30.000 $27.500 $100.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 1.000 $90.000 $40.000 $50.000 $44.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $30,000.000 $30,000.000 $5,100.000 $12,500.000
TMA (STATIONARY)
DAY 30.000 $200.000 $310.000 $50.000 $250.000 $250.000
Totals: $888,966.430 $857,399.071 $877,712.000 $1,014,933.100 $1,158,242.750