TARRANT BU 287P (0013-10-096)

Items: 18

County: TARRANT
Length: 0.0000 MILES
Highway: BU 287P
District: FORT WORTH
Control Number: 0013-10-096
DBE Goal: 0.0%
Project: F 2025(869)
Guaranty: $14,000.00
Time: 64 WORKING DAYS
Engineer's Estimate: $675,946.70
Date: 07/01/2025 (11 months ago)
Contract Number: 7253033
Type: LANDSCAPE DEVELOPMENT
Project ID: A00211766
Contract Type: Federal
Project Description: LANDSCAPE, HARDSCAPE AND IRRIGATION IMPROVEMENTS AMONG BUS 287 WITHIN CITY OF SAGINAW LIMITS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
ALFREDO LUERA
RAUL OROZCO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$675,946.70
$494,457.50
Over/Under Est: -26.85% -$181,489.20
Over/Under Est: -23.11% -$156,183.70
Amt Left: 5.12% $25,305.50
Over/Under Est: -16.86% -$113,950.70
Amt Left: 13.66% $67,538.50
Delta: -8.13% -$42,233.00
Over/Under Est: 14.17% $95,778.80
Amt Left: 56.08% $277,268.00
Delta: -37.32% -$209,729.50

Bid Items & Bid Tabulations

18 Total 0 of 18
TARRANT  |  BU 287P  |  FORT WORTH  |  0013-10-096  |  07/01/2025  |  $675,946.70  |  F 2025(869)  |  LANDSCAPE DEVELOPMENT  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
C. GREEN SCAPING, L.P.
CENTRAL NORTH CONSTRUCTION, LLC
TIGHT LINE CONSTRUCTION, LLC
ABESCAPE LANDSCAPING, LLC
PREPARING ROW
STA 4.000 $5,000.000 $9,615.000 $32,000.000 $10,000.000 $7,000.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 258.000 $6.500 $3.500 $0.500 $7.000 $4.000
VEGETATIVE WATERING
TGL 3.000 $200.000 $290.000 $100.000 $250.000 $100.000
IRRIGATION SYSTEM
LS 1.000 $80,000.000 $75,840.000 $150,022.500 $100,000.000 $90,000.000
PLANT BED PREP
SY 411.000 $20.000 $53.000 $4.500 $25.000 $3.500
LANDSCAPE EDGE
LF 1,881.000 $30.000 $9.000 $6.500 $15.000 $30.000
PLANT MATERIAL (5 GAL) (SHRUB)
EA 2,203.000 $50.000 $16.000 $25.000 $40.000 $55.000
LANDSCAPE ESTABLISH
MO 12.000 $2,000.000 $2,200.000 $1,900.000 $2,000.000 $2,500.000
IRRIG SYS OPER AND MAINT
MO 12.000 $1,000.000 $1,440.000 $900.000 $1,000.000 $1,500.000
RIPRAP (CONC)(4 IN)
CY 15.000 $1,500.000 $1,730.000 $2,500.000 $750.000 $1,300.000
RIPRAP (SPECIAL)
CY 295.000 $600.000 $525.000 $200.000 $400.000 $650.000
MOBILIZATION
LS 1.000 $61,449.700 $17,800.000 $26,000.000 $50,000.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $4,250.000 $1,800.000 $4,500.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 64.000 $125.000 $140.000 $50.000 $250.000 $1,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 3,030.000 $8.000 $6.650 $0.250 $8.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,030.000 $6.000 $3.000 $0.100 $3.000 $5.000
CONDT (PVC) (SCH 40) (4") (BORE)
LF 100.000 $60.000 $45.000 $35.000 $75.000 $40.000
ELEC CONDR (NO.8) BARE
LF 110.000 $50.000 $22.000 $10.000 $25.000 $6.000
Totals: $675,946.700 $494,457.500 $519,763.000 $561,996.000 $771,725.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $20,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $60,000.00
Total: $80,000.00