TARRANT IH 820 (0008-14-124)

Items: 29

County: TARRANT
Length: N/A
Highway: IH 820
District: FORT WORTH
Control Number: 0008-14-124
DBE Goal: N/A
Project: BR 2023(973)
Guaranty: N/A
Time: 171 WORKING DAYS
Engineer's Estimate: $1,760,035.00
Date: 06/27/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,760,035.00
1
Awarded
$1,932,277.50
Over/Under Est: 9.79% $172,242.50
$2,006,828.00
Over/Under Est: 14.02% $246,793.00
Amt Left: 3.86% $74,550.50
Over/Under Est: 56.69% $997,787.00
Amt Left: 42.72% $825,544.50
Delta: -37.42% -$750,994.00
Over/Under Est: 56.96% $1,002,507.59
Amt Left: 42.97% $830,265.09
Delta: -0.17% -$4,720.59
Subcontractor Percentage Amount
SYNERGY SIGNS & SERVICES LLC 5.58% $107,821.08
DALLAS LITE AND BARRICADE, INC. 4.39% $84,826.98
HDZ CONSTRUCTION 0.17% $3,284.87
Total: 10.14% $195,932.93

Bid Items & Bid Tabulations

29 Total 0 of 29
TARRANT  |  IH 820  |  FORT WORTH  |  0008-14-124  |  06/27/2023  |  $1,760,035.00  |  BR 2023(973)  |  BRIDGE MAINT  |  171 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
IBCTX, LLC
FNH CONSTRUCTION, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
RAGLE CONSTRUCTION, INC.
ANCHOR BOLTS
EA 36.000 $15.000 $500.000 $1,500.000 $500.000 $55.000
RETROFIT RAIL (TY SSTR)(HPC)
LF 3,283.600 $260.000 $315.000 $200.000 $400.000 $498.150
MOBILIZATION
LS 1.000 $143,292.000 $193,000.000 $200,000.000 $275,000.000 $275,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $17,000.000 $40,000.000 $8,500.000 $10,000.000 $37,500.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 150.000 $15.000 $20.000 $18.000 $35.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 150.000 $3.000 $10.000 $9.000 $5.000 $2.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,600.000 $70.000 $30.000 $125.000 $100.000 $83.500
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 15,800.000 $15.000 $5.000 $31.000 $35.000 $9.750
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,600.000 $35.000 $15.000 $40.000 $35.000 $11.000
MTL W-BEAM GD FEN (TIM POST)
LF 12.500 $60.000 $80.000 $100.000 $100.000 $31.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 13.000 $2,250.000 $2,400.000 $2,000.000 $3,000.000 $1,900.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 412.500 $65.000 $60.000 $50.000 $50.000 $12.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,900.000 $2,400.000 $2,000.000 $2,500.000 $1,400.000
REMOVE METAL BEAM GUARD FENCE
LF 636.000 $5.000 $6.000 $3.000 $7.000 $2.500
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $180.000 $500.000 $500.000 $1,000.000 $250.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 18.000 $50.000 $55.000 $50.000 $100.000 $30.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 261.500 $55.000 $45.000 $50.000 $100.000 $35.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 5.000 $3,000.000 $3,000.000 $3,500.000 $2,750.000 $5,000.000
REMOVE BRDG MNT CLEARANCE SIGN ASSM
EA 3.000 $1,500.000 $900.000 $1,500.000 $1,000.000 $2,500.000
INSTALL LRSS (STRUCT STEEL)
LB 1,100.000 $10.000 $8.000 $30.000 $10.000 $8.000
REMOVE LRSA
EA 3.000 $500.000 $3,600.000 $2,500.000 $4,000.000 $3,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 18.000 $25.000 $20.000 $100.000 $20.000 $30.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 18.000 $21.000 $20.000 $100.000 $20.000 $22.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)SRF
EA 16.000 $100.000 $250.000 $100.000 $200.000 $110.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)SRF
EA 10.000 $100.000 $250.000 $100.000 $200.000 $110.000
D-GR HMA TY-D PG64-22
TON 15.800 $380.000 $2,500.000 $1,000.000 $75.000 $1,375.000
TACK COAT
GAL 30.000 $16.000 $150.000 $100.000 $75.000 $102.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 210.000 $150.000 $100.000 $150.000 $150.000 $81.000
TMA (STATIONARY)
DAY 340.000 $200.000 $75.000 $250.000 $350.000 $303.000
Totals: $1,760,035.000 $1,932,277.500 $2,006,828.000 $2,757,822.000 $2,762,542.590