Show Job Controls
Bid Cobra

TARRANT IH 20 (0008-13-249)

Items: 67

County: TARRANT
Length: N/A
Highway: IH 20
District: FORT WORTH
Control Number: 0008-13-249
DBE Goal: N/A
Project: BR 2023(695)
Guaranty: N/A
Time: 363 WORKING DAYS
Engineer's Estimate: $3,549,256.61
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: REHABILITATE BRIDGE
Mail/Deliver Bids To: N/A
DAVID NEELEY
JEREMY ARREGUIN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$3,549,256.61
$4,830,945.89
Over/Under Est: 36.11% $1,281,689.28
$5,376,939.00
Over/Under Est: 51.49% $1,827,682.39
Amt Left: 11.3% $545,993.11
Subcontractor Percentage Amount
UNIFIED SPECIALTIES LLC 8.55% $413,212.35
GIBSON & ASSOCIATES, INC. 5.62% $271,608.58
HERMANOS STEEL, LLC 4.57% $220,863.21
PEACHTREE CONSTRUCTION, LTD. 2.11% $101,974.04
A-CORE CONCRETE CUTTING OF TEXAS, INC. 1.59% $76,843.00
JE CASEY, LLC 1.59% $76,843.00
RGJ SERVICES, LLC 1.13% $54,611.69
J MUNOZ TRUCKING LLC 0.71% $34,313.54
MOBILE ENTERPRISES, INC. 0.70% $33,830.25
HOUSTON SAWING & DRILLING 0.66% $31,897.09
REPUBLIC COMPOSITE STUD WELDING 0.48% $23,197.89
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 0.35% $16,915.13
TEXOP CONSTRUCTION 0.33% $15,948.55
KING GEORGE TRAFFIC SOLUTIONS LLC 0.21% $10,149.08
ELITE STRIPING, LLC 0.20% $9,665.79
SCOTT DERR PAINTING CO, LLC 0.16% $7,732.63
Total: 28.96% $1,399,605.82

Bid Items & Bid Tabulations

67 Total 0 of 67
TARRANT  |  IH 20  |  FORT WORTH  |  0008-13-249  |  05/04/2023  |  $3,549,256.61  |  BR 2023(695)  |  REHAB BRIDGE  |  363 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
IBCTX, LLC
REMOVING CONC (CURB)
LF 202.000 $15.000 $14.000 $50.000
REMOVING CONC (MISC)
SY 45.000 $75.000 $24.000 $100.000
CEMENT
TON 1.000 $225.000 $1,000.000 $400.000
CEMENT TREAT (SUBGRADE) (8")
SY 50.000 $3.400 $66.000 $185.000
PRIME COAT (MC-30)
GAL 10.000 $5.950 $235.000 $500.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,080.000 $20.000 $7.300 $15.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,377.000 $5.000 $14.000 $15.000
PLANE CONC PAV(0" TO 1")
SY 189.000 $15.000 $10.500 $15.000
PLANE CONC PAV(0" TO 2")
SY 1,070.000 $10.000 $9.600 $15.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 49.000 $85.000 $183.000 $220.000
FLOWABLE BACKFILL
CY 4.000 $450.000 $765.000 $1,000.000
REINF CONC SLAB (HPC)
SF 31,879.000 $25.000 $30.400 $44.000
APPROACH SLAB (HPC)
CY 41.000 $650.000 $712.000 $1,400.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 1,122.000 $28.000 $7.100 $18.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 113.000 $200.000 $110.000 $210.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 97.000 $240.000 $150.000 $294.000
CONC STR REPAIR (STANDARD)
SF 28.000 $600.000 $150.000 $258.000
RIPRAP (CONC)(5 IN)
CY 2.000 $630.000 $2,000.000 $2,000.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 130.000 $50.000 $42.000 $50.000
CLEANING AND SEALING JOINTS (CL 7)
LF 265.000 $40.000 $26.000 $31.000
RESIZING AND SEALING JOINTS
LF 282.000 $75.000 $46.000 $55.000
STR STEEL (SHEAR CONNECTOR)
LB 14,426.000 $12.000 $6.500 $7.000
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 1.000 $575,000.000 $449,000.000 $940,000.000
RAIL (TY SSTR)(HPC)
LF 1,711.000 $85.000 $67.000 $186.000
ARMOR JOINT (SEALED)
LF 91.000 $175.000 $71.000 $170.000
HEADER TYPE EXPANSION JOINT
CF 16.000 $550.000 $545.000 $654.000
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 199.000 $150.000 $121.000 $210.000
REMOV STR (BRIDGE SLAB)
EA 2.000 $240,000.000 $600,000.000 $225,000.000
REMOVE STR (RAIL)
LF 1,711.000 $25.000 $28.000 $50.000
MOBILIZATION
LS 1.000 $308,155.610 $480,000.000 $537,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $9,385.000 $42,000.000 $25,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 150.000 $45.000 $26.000 $32.000
ROCK FILTER DAMS (REMOVE)
LF 150.000 $15.000 $12.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,030.000 $3.000 $3.250 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,030.000 $0.800 $1.000 $3.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 700.000 $4.000 $3.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 700.000 $1.750 $0.850 $3.000
CONC CURB (TY II)
LF 110.000 $25.000 $22.000 $45.000
CONC CURB & GUTTER (TY II)
LF 30.000 $64.000 $67.000 $55.000
MTL W-BEAM GD FEN (TIM POST)
LF 160.000 $29.000 $35.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $2,800.000 $1,000.000 $2,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,350.000 $1,500.000 $1,900.000
REMOVE METAL BEAM GUARD FENCE
LF 384.000 $2.500 $5.000 $8.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $300.000 $250.000 $400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,200.000 $3,000.000 $3,500.000
REM & RELOCATE OVHD SIGN & SUP
EA 1.000 $6,500.000 $40,000.000 $50,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 22.000 $25.000 $30.000 $30.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 14.000 $22.000 $30.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 15.000 $40.000 $40.000 $50.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 3.000 $45.000 $45.000 $50.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 23.000 $9.000 $6.000 $8.000
PAVEMENT SEALER 6"
LF 2,424.000 $0.500 $0.500 $1.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 220.000 $1.000 $1.090 $1.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 2,574.000 $0.750 $1.090 $1.500
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 2,582.000 $0.700 $1.090 $1.500
REFL PAV MRKR TY II-A-A
EA 12.000 $5.000 $5.000 $7.000
REFL PAV MRKR TY II-C-R
EA 11.000 $5.000 $5.000 $7.000
PAV SURF PREP FOR MRK (6")
LF 5,376.000 $0.100 $0.500 $1.000
PAV SURF PREP FOR MRK (24")
LF 23.000 $1.500 $1.250 $2.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 695.000 $120.000 $37.000 $142.000
D-GR HMA TY-D SAC-B PG70-28
TON 12.000 $150.000 $1,300.000 $1,600.000
SP MIXES SP-C SAC-A PG70-28
TON 273.000 $250.000 $265.000 $335.000
TACK COAT
GAL 475.000 $4.500 $3.500 $4.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 1,377.000 $120.000 $165.000 $188.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 483.000 $100.000 $60.000 $100.000
TMA (STATIONARY)
DAY 483.000 $200.000 $125.000 $225.000
TMA (MOBILE OPERATION)
DAY 267.000 $220.000 $125.000 $25.000
Totals: $3,549,256.610 $4,830,945.890 $5,376,939.000