SWISHER IH 27 (0067-02-071)

Items: 64

County: SWISHER
Length: N/A
Highway: IH 27
District: LUBBOCK
Control Number: 0067-02-071
DBE Goal: N/A
Project: BR 2021(558)
Guaranty: N/A
Time: 354 WORKING DAYS
Engineer's Estimate: $3,360,094.14
Date: 05/06/2021 (5 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$3,360,094.14
$3,742,465.57
Over/Under Est: 11.38% $382,371.43
$5,383,919.00
Over/Under Est: 60.23% $2,023,824.86
Amt Left: 43.86% $1,641,453.43
Over/Under Est: 69.88% $2,348,151.05
Amt Left: 52.53% $1,965,779.62
Delta: -6.02% -$324,326.19
Subcontractor Percentage Amount
GIBSON & ASSOCIATES, INC. 15.30% $596,497.20
STRUCTURAL INTEGRITY GROUP LLC 11.99% $467,451.07
TRP CONSTRUCTION GROUP, LLC 4.24% $165,303.80
ALAMO BROTHERS CONCRETE INC 0.00% $0.00
TEXOP CONSTRUCTION 0.00% $0.00
S&S BRIDGE PAINTING 0.00% $0.00
BARRICADES UNLIMITED 0.00% $0.00
DUSTROL, INC. 0.00% $0.00
Total: 31.53% $1,229,252.07

Bid Items & Bid Tabulations

64 Total 0 of 64
SWISHER  |  IH 27  |  LUBBOCK  |  0067-02-071  |  05/06/2021  |  $3,360,094.14  |  BR 2021(558)  |  BRIDGE MAINT  |  354 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GILVIN-TERRILL, LTD.
CEKRA INC.
GIBSON & ASSOCIATES, INC.
REMOVE CONC (RAIL)
LF 1,861.000 $15.000 $70.000 $15.000 $100.000
REMOVING CONC (FLUME)
SY 12.000 $13.000 $415.000 $15.000 $200.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 714.000 $6.000 $25.000 $10.000 $55.000
BACKFILL (TY B)
STA 41.000 $300.000 $195.000 $200.000 $365.000
PROOF ROLLING
HR 20.000 $90.000 $100.000 $150.000 $105.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 734.000 $3.250 $7.000 $5.000 $9.350
FOG SEAL (CSS-1H)
GAL 2,649.000 $4.000 $5.000 $5.000 $6.820
D-GR HMA(SQ) TY-C SAC-A PG70-28
TON 1,723.000 $125.000 $140.000 $100.000 $191.070
PLANE ASPH CONC PAV (4")
SY 4,724.000 $3.400 $5.000 $2.000 $4.950
FLOWABLE BACKFILL
CY 120.000 $235.000 $400.000 $150.000 $1,000.000
DRILL SHAFT (18 IN)
LF 72.000 $3.070 $255.000 $100.000 $310.000
CL B CONC (FLUME)
CY 80.000 $470.000 $650.000 $1,000.000 $1,000.000
OPAQUE SEALER FINISH
SF 48,476.000 $8.000 $0.320 $1.000 $0.460
BLAST FINISH
SF 800.000 $7.000 $1.500 $5.000 $1.650
PENETRATING CONCRETE SURFACE TREATMENT
SY 88.000 $14.000 $18.000 $15.000 $19.800
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 352.000 $213.000 $110.000 $300.000 $122.100
CONC STR REPAIR (EPOXY MORTAR)
SF 422.000 $153.000 $110.000 $500.000 $163.900
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 800.000 $60.000 $100.000 $400.000 $60.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 3,557.000 $60.000 $100.000 $150.000 $223.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 502.000 $210.000 $110.000 $800.000 $168.300
RIPRAP (CONC)(4 IN)
CY 136.000 $500.000 $560.000 $400.000 $1,025.000
RAIL (TY T551)(HPC)
LF 1,220.000 $60.000 $77.000 $500.000 $237.000
RAIL (TY T80PP-TS)(HPC)
LF 672.000 $175.000 $230.000 $500.000 $1,185.000
RETROFIT RAIL (TY T551)
LF 48.000 $150.000 $200.000 $500.000 $182.000
MOBILIZATION
LS 1.000 $404,000.000 $350,000.000 $400,000.000 $570,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $10,000.000 $11,000.000 $12,000.000 $11,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,200.000 $9.500 $6.000 $4.000 $5.780
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,200.000 $8.000 $2.000 $4.000 $2.370
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 210.000 $45.000 $75.000 $80.000 $58.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 210.000 $20.000 $15.000 $5.000 $52.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 210.000 $20.000 $10.000 $25.000 $47.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,440.000 $25.000 $37.000 $30.000 $29.150
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,800.000 $2,375.000 $2,500.000 $1,980.000
REMOVE METAL BEAM GUARD FENCE
LF 1,200.000 $2.250 $3.000 $10.000 $3.300
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,800.000 $3,175.000 $2,500.000 $3,080.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,000.000 $2,500.000 $2,500.000 $5,500.000
CRASH CUSH ATTEN (REMOVE)
EA 14.000 $1,000.000 $1,000.000 $2,500.000 $1,100.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 12.000 $2,000.000 $25,167.000 $20,000.000 $23,540.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $2,000.000 $7,500.000 $20,000.000 $11,187.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 144.000 $35.000 $36.500 $25.000 $27.500
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 25.000 $50.000 $12.350 $25.000 $22.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 800.000 $0.800 $0.250 $3.000 $0.280
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 96.000 $0.750 $1.250 $15.000 $1.380
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 400.000 $2.000 $0.250 $2.000 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 8,000.000 $3.000 $0.250 $1.500 $0.280
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 200.000 $3.000 $8.000 $20.000 $8.800
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 200.000 $2.000 $1.000 $20.000 $3.300
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 10,500.000 $0.320 $0.550 $2.000 $0.610
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,570.000 $0.320 $0.550 $2.000 $0.610
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 7,260.000 $0.320 $0.550 $2.000 $0.610
REFL PAV MRKR TY II-A-A
EA 134.000 $3.000 $6.000 $15.000 $6.600
ELIM EXT PAV MRK & MRKS (4")
LF 21,400.000 $0.500 $1.750 $1.000 $1.930
PAV SURF PREP FOR MRK (6")
LF 8,000.000 $0.070 $0.500 $5.000 $0.550
FULL - WIDTH MOWING
AC 28.000 $200.000 $375.000 $175.000 $1,000.000
LITTER REMOVAL
CYC 4.000 $2,000.000 $2,475.000 $1,000.000 $2,500.000
CONC RAIL REPAIR(REMOVE AND REPL RAIL)
LF 56.000 $150.000 $1,400.000 $1,000.000 $1,200.000
BRIDGE JOINT REPAIR (FULL DEPTH)
LF 222.000 $167.000 $375.000 $500.000 $590.000
BRIDGE JOINT REPLACEMENT (SEJ)
LF 180.000 $340.000 $500.000 $250.000 $765.000
CARBON FIBER REINF POLYMER PROTECTION
SF 816.000 $152.000 $90.000 $100.000 $80.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 4,724.000 $108.000 $140.000 $100.000 $107.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $15,000.000 $15,000.000 $36,000.000
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 772.000 $0.700 $14.750 $20.000 $16.230
TMA (STATIONARY)
DAY 750.000 $250.000 $50.000 $350.000 $125.000
CLEANING SUBSTRUCTURE (BENT)
EA 12.000 $1,000.000 $815.000 $2,000.000 $1,600.000
Totals: $3,360,094.140 $3,742,465.570 $5,383,919.000 $5,708,245.190