STONEWALL FM 1835 (1747-02-017)
Items: 61
County: STONEWALL
Length: 0.0000 MILES
Highway: FM 1835
District: ABILENE
Control Number: 1747-02-017
DBE Goal: 500.0%
Project: BR 2B25(017)
Guaranty: $100,000.00
Time: 107 WORKING DAYS
Engineer's Estimate: $8,261,189.51
Date: 09/05/2025 (9 months ago)
Contract Number: 9253210
Type: BRIDGE REPLACEMENT
Project ID: A00205768
Contract Type: Federal
Project Description: REPLACE BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ANTHONY BOUCHER
JOSE CABRERA
STONEWALL FM 1835 (1747-02-017)
Project Name: N/A
Project: BR 2B25(017)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: FM 1835
Limits To: @ DOUBLE MOUNTAIN FORK BRAZOS RIVER
Project Description: REPLACE BRIDGE
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$8,261,189.51 | |||
| $3,884,350.00 |
-52.98%
-$4,376,839.51
|
|||
| $3,981,565.74 |
-51.8%
-$4,279,623.77
|
2.5%
$97,215.74
|
||
| $4,267,208.80 |
-48.35%
-$3,993,980.71
|
9.86%
$382,858.80
|
-7.17%
-$285,643.06
|
|
| $4,626,000.00 |
-44%
-$3,635,189.51
|
19.09%
$741,650.00
|
-8.41%
-$358,791.20
|
|
| $5,402,560.88 |
-34.6%
-$2,858,628.63
|
39.09%
$1,518,210.88
|
-16.79%
-$776,560.88
|
|
| $6,183,843.20 |
-25.15%
-$2,077,346.31
|
59.2%
$2,299,493.20
|
-14.46%
-$781,282.32
|
|
| $7,085,132.00 |
-14.24%
-$1,176,057.51
|
82.4%
$3,200,782.00
|
-14.57%
-$901,288.80
|
|
| $7,280,123.45 |
-11.88%
-$981,066.06
|
87.42%
$3,395,773.45
|
-2.75%
-$194,991.45
|
|
| $7,449,534.71 |
-9.82%
-$811,654.80
|
91.78%
$3,565,184.71
|
-2.33%
-$169,411.26
|
|
| $7,624,494.88 |
-7.71%
-$636,694.63
|
96.29%
$3,740,144.88
|
-2.35%
-$174,960.17
|
E
Engineer's Estimate
$8,261,189.51
$3,884,350.00
Over/Under Est:
-52.98%
-$4,376,839.51
$3,981,565.74
Over/Under Est:
-51.8%
-$4,279,623.77
Amt Left:
2.5%
$97,215.74
$4,267,208.80
Over/Under Est:
-48.35%
-$3,993,980.71
Amt Left:
9.86%
$382,858.80
Delta:
-7.17%
-$285,643.06
$4,626,000.00
Over/Under Est:
-44%
-$3,635,189.51
Amt Left:
19.09%
$741,650.00
Delta:
-8.41%
-$358,791.20
$5,402,560.88
Over/Under Est:
-34.6%
-$2,858,628.63
Amt Left:
39.09%
$1,518,210.88
Delta:
-16.79%
-$776,560.88
$6,183,843.20
Over/Under Est:
-25.15%
-$2,077,346.31
Amt Left:
59.2%
$2,299,493.20
Delta:
-14.46%
-$781,282.32
$7,085,132.00
Over/Under Est:
-14.24%
-$1,176,057.51
Amt Left:
82.4%
$3,200,782.00
Delta:
-14.57%
-$901,288.80
$7,280,123.45
Over/Under Est:
-11.88%
-$981,066.06
Amt Left:
87.42%
$3,395,773.45
Delta:
-2.75%
-$194,991.45
$7,449,534.71
Over/Under Est:
-9.82%
-$811,654.80
Amt Left:
91.78%
$3,565,184.71
Delta:
-2.33%
-$169,411.26
$7,624,494.88
Over/Under Est:
-7.71%
-$636,694.63
Amt Left:
96.29%
$3,740,144.88
Delta:
-2.35%
-$174,960.17
| Subcontractor | Percentage | Amount |
|---|---|---|
| PEACHTREE CONSTRUCTION, LTD. | 3.27% | $127,773.62 |
| S & S BRIDGE PAINTING, INC. | 0.83% | $32,431.84 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 0.80% | $31,259.60 |
| TRP CONSTRUCTION GROUP, LLC | 0.79% | $30,868.86 |
| HOUSTON SAWING & DRILLING | 0.37% | $14,457.57 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 0.26% | $10,159.37 |
| FC TRAFFIC CONTROL, INC. | 0.26% | $10,159.37 |
| MAVERICK SAW CUTTING & CORE DRILLING, LP | 0.16% | $6,251.92 |
| TORO BRAVO CONSTRUCTION, LLC | 0.16% | $6,251.92 |
| Total: | 6.90% | $269,614.07 |
Bid Items & Bid Tabulations
61
Total
0 of 61
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| Total: | $15,000.00 |