STONEWALL US 83 (0033-01-040)
Items: 80
County: STONEWALL
Length: N/A
Highway: US 83
District: ABILENE
Control Number: 0033-01-040
DBE Goal: N/A
Project: BR 1802(318)
Guaranty: N/A
Time: 358 WORKING DAYS
Engineer's Estimate: $4,519,026.56
Date: 11/05/2020 (5 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT & APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,519,026.56 | |||
| $4,007,232.00 |
-11.33%
-$511,794.56
|
|||
| $4,334,790.50 |
-4.08%
-$184,236.06
|
8.17%
$327,558.50
|
||
| $4,534,985.60 |
0.35%
$15,959.04
|
13.17%
$527,753.60
|
-4.62%
-$200,195.10
|
|
| $4,672,631.48 |
3.4%
$153,604.92
|
16.6%
$665,399.48
|
-3.04%
-$137,645.88
|
|
| $5,574,018.00 |
23.35%
$1,054,991.44
|
39.1%
$1,566,786.00
|
-19.29%
-$901,386.52
|
|
| $6,101,096.13 |
35.01%
$1,582,069.57
|
52.25%
$2,093,864.13
|
-9.46%
-$527,078.13
|
|
| $7,552,619.05 |
67.13%
$3,033,592.49
|
88.47%
$3,545,387.05
|
-23.79%
-$1,451,522.92
|
|
| $8,492,666.20 |
87.93%
$3,973,639.64
|
111.93%
$4,485,434.20
|
-12.45%
-$940,047.15
|
E
Engineer's Estimate
$4,519,026.56
1
Awarded
$4,007,232.00
Over/Under Est:
-11.33%
-$511,794.56
$4,334,790.50
Over/Under Est:
-4.08%
-$184,236.06
Amt Left:
8.17%
$327,558.50
$4,534,985.60
Over/Under Est:
0.35%
$15,959.04
Amt Left:
13.17%
$527,753.60
Delta:
-4.62%
-$200,195.10
$4,672,631.48
Over/Under Est:
3.4%
$153,604.92
Amt Left:
16.6%
$665,399.48
Delta:
-3.04%
-$137,645.88
$5,574,018.00
Over/Under Est:
23.35%
$1,054,991.44
Amt Left:
39.1%
$1,566,786.00
Delta:
-19.29%
-$901,386.52
$6,101,096.13
Over/Under Est:
35.01%
$1,582,069.57
Amt Left:
52.25%
$2,093,864.13
Delta:
-9.46%
-$527,078.13
$7,552,619.05
Over/Under Est:
67.13%
$3,033,592.49
Amt Left:
88.47%
$3,545,387.05
Delta:
-23.79%
-$1,451,522.92
$8,492,666.20
Over/Under Est:
87.93%
$3,973,639.64
Amt Left:
111.93%
$4,485,434.20
Delta:
-12.45%
-$940,047.15
Bid Items & Bid Tabulations
80
Total
0 of 80