STEPHENS PR 33 (0714-02-018)

Items: 59

County: STEPHENS
Length: N/A
Highway: PR 33
District: BROWNWOOD
Control Number: 0714-02-018
DBE Goal: N/A
Project: BR 2022(605)
Guaranty: N/A
Time: 134 WORKING DAYS
Engineer's Estimate: $1,007,627.40
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JORDAN PERRY
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,007,627.40
$960,397.90
Over/Under Est: -4.69% -$47,229.50
$982,874.23
Over/Under Est: -2.46% -$24,753.17
Amt Left: 2.34% $22,476.33
Over/Under Est: -1.59% -$16,004.56
Amt Left: 3.25% $31,224.94
Delta: -0.89% -$8,748.61
$1,159,001.80
Over/Under Est: 15.02% $151,374.40
Amt Left: 20.68% $198,603.90
Delta: -16.88% -$167,378.96

Bid Items & Bid Tabulations

59 Total 0 of 59
STEPHENS  |  PR 33  |  BROWNWOOD  |  0714-02-018  |  06/01/2022  |  $1,007,627.40  |  BR 2022(605)  |  BRIDGE REPL  |  134 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
PIERCE R & B LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
EARTH BUILDERS, L.P.
PREPARING ROW
STA 6.600 $2,500.000 $2,500.000 $2,500.000 $4,000.000 $12,500.000
EXCAVATION (ROADWAY)
CY 383.000 $25.000 $25.000 $20.000 $15.000 $20.000
EXCAVATION (CHANNEL)
CY 99.000 $30.000 $25.000 $35.000 $20.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 338.000 $25.000 $25.000 $22.000 $20.000 $20.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,460.000 $3.000 $3.000 $2.150 $3.000 $2.500
BROADCAST SEED (TEMP) (WARM)
SY 730.000 $2.000 $3.000 $2.200 $1.000 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 730.000 $2.000 $3.000 $2.200 $1.000 $1.000
SOIL RETENTION BLANKETS (CL 2) (TY G)
SY 900.000 $6.000 $5.000 $4.300 $4.000 $4.000
PROOF ROLLING
HR 2.000 $100.000 $100.000 $150.000 $100.000 $100.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 257.000 $95.000 $180.000 $75.000 $60.000 $100.000
PRIME COAT (RC-250)
GAL 530.000 $20.000 $25.000 $19.500 $15.000 $12.500
ASPH (AC-20-5TR)
GAL 1,607.000 $20.000 $12.870 $14.850 $15.000 $20.000
AGGR(TY-B GR-5 SAC-B)
CY 17.000 $1,000.000 $792.650 $700.000 $700.000 $500.000
AGGR(TY-PB GR-3 SAC-B)
CY 25.000 $900.000 $612.000 $545.000 $700.000 $500.000
AGGR(TY-PB GR-4 SAC-B)
CY 19.000 $900.000 $768.430 $685.000 $700.000 $500.000
CEM STABIL BKFL
CY 92.000 $300.000 $300.000 $210.000 $225.000 $400.000
TRENCH EXCAVATION PROTECTION
LF 44.000 $15.000 $40.000 $18.000 $1.000 $10.000
DRILL SHAFT (36 IN)
LF 184.000 $300.000 $290.000 $335.000 $250.000 $375.000
CORE HOLE
EA 2.000 $225.000 $200.000 $200.000 $500.000 $500.000
CL C CONC (ABUT)
CY 43.900 $1,400.000 $1,200.000 $1,300.000 $1,200.000 $1,500.000
CL C CONC (CULV)
CY 71.400 $1,000.000 $750.000 $1,400.000 $1,400.000 $1,000.000
REINF CONC SLAB
SF 3,907.280 $30.000 $25.000 $26.000 $28.000 $35.000
PRESTR CONC GIRDER (TX34)
LF 318.000 $320.000 $305.000 $280.000 $360.000 $300.000
RIPRAP (CONC)(5 IN)
CY 11.900 $600.000 $550.000 $600.000 $600.000 $750.000
RAIL (TY T631)
LF 196.000 $100.000 $116.300 $117.000 $120.000 $150.000
ARMOR JOINT (SEALED)
LF 60.000 $110.000 $150.000 $100.000 $130.000 $100.000
GABIONS (3' X 3')(GALV)
CY 155.000 $325.000 $175.000 $300.000 $250.000 $350.000
GABION (1.5' X 3')(GALV)
CY 6.000 $350.000 $175.000 $800.000 $300.000 $350.000
RC PIPE (CL III)(18 IN)
LF 28.000 $150.000 $150.000 $100.000 $80.000 $100.000
RC PIPE (CL III)(24 IN)
LF 45.000 $150.000 $170.000 $110.000 $95.000 $125.000
SET (TY I)(S= 8 FT)(HW= 4 FT)(3:1) (C)
EA 8.000 $11,000.000 $6,600.000 $13,500.000 $4,500.000 $15,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $3,500.000 $1,250.000 $1,500.000 $2,000.000 $2,500.000
SET (TY II) (24 IN) (RCP) (3: 1) (P)
EA 1.000 $3,500.000 $1,500.000 $1,500.000 $3,500.000 $2,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $4,000.000 $1,500.000 $1,600.000 $3,500.000 $3,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $15,000.000 $20,000.000 $45,000.000 $30,000.000
REMOV STR (PIPE)
EA 3.000 $600.000 $500.000 $1,200.000 $500.000 $2,500.000
MOBILIZATION
LS 1.000 $92,000.000 $100,000.000 $98,000.000 $80,000.000 $110,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $2,500.000 $10,000.000 $3,000.000 $8,000.000 $2,500.000
ROCK FILTER DAMS (REMOVE)
LF 30.000 $15.000 $10.000 $10.000 $1.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 260.000 $5.000 $5.000 $4.000 $1.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 260.000 $2.000 $5.000 $1.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 165.000 $6.000 $4.000 $5.000 $5.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 165.000 $2.000 $4.000 $1.000 $1.000 $1.000
ROCK FILTER DAMS (INSTALL) (TY 2) (6:1)
LF 30.000 $60.000 $50.000 $50.000 $1.000 $40.000
DRIVEWAYS (SURF TREAT)
SY 62.000 $100.000 $123.390 $95.000 $70.000 $100.000
MTL W-BEAM GD FEN (STEEL POST)
LF 75.000 $40.000 $36.250 $35.000 $35.000 $50.000
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $4.000 $2.500 $2.600 $2.000 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,600.000 $3,150.000 $3,535.000 $3,400.000 $3,250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $800.000 $2,500.000 $750.000 $1,000.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $850.000 $2,500.000 $800.000 $1,000.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 5.000 $110.000 $250.000 $100.000 $500.000 $100.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 19.000 $20.000 $20.000 $1.000 $1.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $50.000 $27.500 $33.000 $30.000 $50.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 4.000 $60.000 $66.000 $81.000 $60.000 $75.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 66.000 $3.000 $5.000 $2.000 $5.000 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,304.000 $2.000 $2.020 $1.800 $2.000 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,304.000 $2.000 $2.020 $1.800 $2.000 $2.000
REFL PAV MRKR TY II-A-A
EA 34.000 $10.000 $45.300 $8.400 $10.000 $10.000
TMA (STATIONARY)
DAY 10.000 $300.000 $300.000 $300.000 $200.000 $100.000
Totals: $1,007,627.400 $960,397.900 $982,874.230 $991,622.840 $1,159,001.800