SMITH FM 2015 (1934-02-006)
Items: 109
County: SMITH
Length: N/A
Highway: FM 2015
District: TYLER
Control Number: 1934-02-006
DBE Goal: N/A
Project: STP 2019(017)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $3,042,382.25
Date: 09/07/2018 (7 years ago)
Contract Number: N/A
Type: GR,CMT TRT SBGRD,ACP,OCST,STRS,MBGF,PV MK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,042,382.25 | |||
| $3,017,503.37 |
-0.82%
-$24,878.88
|
|||
| $3,227,343.59 |
6.08%
$184,961.34
|
6.95%
$209,840.22
|
||
| $3,249,487.55 |
6.81%
$207,105.30
|
7.69%
$231,984.18
|
-0.69%
-$22,143.96
|
|
| $3,291,175.59 |
8.18%
$248,793.34
|
9.07%
$273,672.22
|
-1.28%
-$41,688.04
|
|
| $3,325,267.25 |
9.3%
$282,885.00
|
10.2%
$307,763.88
|
-1.04%
-$34,091.66
|
|
| $3,338,814.24 |
9.74%
$296,431.99
|
10.65%
$321,310.87
|
-0.41%
-$13,546.99
|
|
| $3,528,208.60 |
15.97%
$485,826.35
|
16.92%
$510,705.23
|
-5.67%
-$189,394.36
|
|
| $3,593,264.70 |
18.11%
$550,882.45
|
19.08%
$575,761.33
|
-1.84%
-$65,056.10
|
|
| $3,630,610.73 |
19.33%
$588,228.48
|
20.32%
$613,107.36
|
-1.04%
-$37,346.03
|
E
Engineer's Estimate
$3,042,382.25
1
Awarded
$3,017,503.37
Over/Under Est:
-0.82%
-$24,878.88
$3,227,343.59
Over/Under Est:
6.08%
$184,961.34
Amt Left:
6.95%
$209,840.22
$3,249,487.55
Over/Under Est:
6.81%
$207,105.30
Amt Left:
7.69%
$231,984.18
Delta:
-0.69%
-$22,143.96
$3,291,175.59
Over/Under Est:
8.18%
$248,793.34
Amt Left:
9.07%
$273,672.22
Delta:
-1.28%
-$41,688.04
$3,325,267.25
Over/Under Est:
9.3%
$282,885.00
Amt Left:
10.2%
$307,763.88
Delta:
-1.04%
-$34,091.66
$3,338,814.24
Over/Under Est:
9.74%
$296,431.99
Amt Left:
10.65%
$321,310.87
Delta:
-0.41%
-$13,546.99
$3,528,208.60
Over/Under Est:
15.97%
$485,826.35
Amt Left:
16.92%
$510,705.23
Delta:
-5.67%
-$189,394.36
$3,593,264.70
Over/Under Est:
18.11%
$550,882.45
Amt Left:
19.08%
$575,761.33
Delta:
-1.84%
-$65,056.10
$3,630,610.73
Over/Under Est:
19.33%
$588,228.48
Amt Left:
20.32%
$613,107.36
Delta:
-1.04%
-$37,346.03
Bid Items & Bid Tabulations
109
Total
0 of 109