Show Job Controls
Bid Cobra

SMITH SL 323 (1790-02-048)

Items: 66

County: SMITH
Length: 0.0000 MILES
Highway: SL 323
District: TYLER
Control Number: 1790-02-048
DBE Goal: 0.0%
Project: F 2026(531)
Guaranty: $34,000.00
Time: 130 WORKING DAYS
Engineer's Estimate: $1,629,505.50
Date: 04/08/2026 (2 months ago) Changed
Contract Number: 4263021
Type: CONSTRUCT BRIDGE
Project ID: A00212486
Contract Type: Federal
Project Description: REPLACE EXISTING CULVERT WITH NEW BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$1,629,505.50
$1,516,226.34
Over/Under Est: -6.95% -$113,279.16
$1,528,969.65
Over/Under Est: -6.17% -$100,535.85
Amt Left: 0.84% $12,743.31
Over/Under Est: -5.96% -$97,130.20
Amt Left: 1.07% $16,148.96
Delta: -0.22% -$3,405.65
Over/Under Est: -3.48% -$56,665.60
Amt Left: 3.73% $56,613.56
Delta: -2.64% -$40,464.60
$1,623,970.51
Over/Under Est: -0.34% -$5,534.99
Amt Left: 7.11% $107,744.17
Delta: -3.25% -$51,130.61
Over/Under Est: 1.7% $27,769.55
Amt Left: 9.3% $141,048.71
Delta: -2.05% -$33,304.54
Over/Under Est: 6.2% $100,973.00
Amt Left: 14.13% $214,252.16
Delta: -4.42% -$73,203.45
Over/Under Est: 13.02% $212,230.50
Amt Left: 21.47% $325,509.66
Delta: -6.43% -$111,257.50
Over/Under Est: 43.72% $712,447.75
Amt Left: 54.46% $825,726.91
Delta: -27.16% -$500,217.25

Bid Items & Bid Tabulations

66 Total 0 of 66
SMITH  |  SL 323  |  TYLER  |  1790-02-048  |  04/08/2026  |  $1,629,505.50  |  F 2026(531)  |  CONSTRUCT BRIDGE  |  130 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DRAKE COMPANIES LLC
SKYLINE BRIDGE LLC
GARRET SHIELDS INFRASTRUCTURE
R CONSTRUCTION CIVIL, LLC
THK CONSTRUCTION LLC
LONGVIEW BRIDGE AND ROAD, LTD.
HODGES AND SON CONSTRUCTION COMPANY, INC.
BAKER & COMPANY CONSTRUCTION, LLC
RED BARON BUILDING COMPANY, LLC
PREPARING ROW
STA 7.250 $3,000.000 $1,511.000 $850.000 $1,000.000 $2,400.000 $1,200.000 $2,150.000 $2,200.000 $5,560.000 $2,500.000
REMOV CONC (DRIVEWAYS)
SY 364.000 $25.000 $8.500 $12.500 $20.000 $8.000 $10.000 $9.000 $15.000 $11.000 $40.000
RMV (0"-6") TRT/UNTRT BASE & ASPH PAV
SY 535.000 $8.000 $11.900 $10.100 $20.000 $9.000 $20.000 $9.000 $12.000 $8.000 $8.000
RMV (6"-12") TRT/UNTRT BASE & ASPH PAV
SY 531.000 $10.000 $12.000 $10.180 $20.000 $9.000 $20.000 $9.000 $15.000 $8.000 $11.000
EXCAV (ROADWAY)
CY 453.000 $10.000 $12.850 $9.750 $30.000 $27.000 $15.000 $10.250 $20.000 $20.000 $30.000
EMBANK (FNL)(OC)(TY C)
CY 327.000 $17.000 $15.500 $31.000 $30.000 $27.000 $15.000 $20.000 $30.000 $20.000 $65.000
FURN & PLACE TOPSOIL (4")
SY 3,573.000 $2.000 $2.650 $4.000 $4.000 $4.500 $3.500 $2.000 $3.000 $1.500 $6.500
BROADCAST SEED (PERM_RURAL_SAND)
SY 3,573.000 $0.300 $0.440 $0.480 $0.200 $0.400 $0.420 $0.400 $1.500 $0.500 $2.500
BROADCAST SEED (TEMP_WARM)
SY 893.000 $2.500 $0.440 $0.480 $0.200 $0.400 $0.420 $0.400 $1.000 $0.500 $2.500
BROADCAST SEED (TEMP_COOL)
SY 893.000 $2.500 $0.440 $0.480 $0.200 $0.400 $0.420 $0.400 $1.000 $0.500 $2.500
VEGETATIVE WATERING
TGL 40.000 $8.000 $13.300 $1.000 $10.000 $250.000 $1.000 $40.000 $1.000 $10.000 $150.000
CEMENT
TON 73.000 $250.000 $280.000 $280.000 $300.000 $295.000 $350.000 $290.000 $350.000 $275.000 $300.000
CEMENT TRT (EXIST MATL)(12")
SY 2,715.000 $10.000 $3.500 $6.500 $5.000 $9.000 $8.000 $2.600 $8.000 $5.000 $9.000
PRIME COAT & BLOTTER (MC-30)
GAL 815.000 $6.000 $8.000 $6.900 $5.000 $9.000 $8.400 $5.800 $10.000 $6.000 $12.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 1,200.000 $4.000 $8.000 $6.250 $6.000 $13.000 $8.400 $6.200 $12.000 $10.000 $10.000
AGGR (TY-PD OR PL, GR-3)
CY 29.000 $150.000 $217.000 $546.000 $375.000 $605.000 $227.850 $325.000 $650.000 $240.000 $250.000
SP MIXES SP-B PG64-22
TON 636.000 $165.000 $162.960 $197.750 $180.000 $178.000 $181.020 $170.000 $200.000 $158.000 $200.000
SP MIXES SP-C SAC-A PG70-22
TON 313.000 $188.000 $189.630 $213.000 $180.000 $220.000 $219.240 $180.000 $200.000 $191.000 $200.000
TACK COAT
GAL 286.000 $3.000 $8.000 $5.000 $12.000 $1.100 $8.400 $4.500 $8.000 $7.000 $10.000
CEM STABIL BKFL
CY 205.000 $225.000 $228.000 $240.000 $180.000 $90.000 $225.000 $225.000 $250.000 $208.000 $400.000
DRILL SHAFT (18 IN)
LF 212.000 $130.000 $74.000 $95.000 $300.000 $125.000 $144.630 $130.000 $110.000 $184.000 $480.000
DRILL SHAFT (36 IN)
LF 530.000 $290.000 $273.000 $225.000 $300.000 $295.000 $281.720 $320.000 $220.000 $318.000 $632.000
CL C CONC (ABUT)
CY 66.000 $1,200.000 $910.000 $950.000 $1,000.000 $650.000 $1,050.000 $1,000.000 $1,000.000 $1,470.000 $750.000
REINF CONC SLAB
SF 4,600.000 $24.000 $25.864 $22.500 $25.000 $26.000 $22.000 $30.000 $28.000 $46.000 $22.000
APPROACH SLAB
CY 70.600 $800.000 $755.000 $620.000 $800.000 $895.000 $800.000 $950.000 $900.000 $1,260.000 $800.000
PRESTR CONC GIRDER (TX46)
LF 597.000 $250.000 $236.440 $270.400 $250.000 $242.000 $274.870 $335.000 $320.000 $247.000 $352.000
RIPRAP (MOW STRIP)(4 IN)
CY 14.000 $700.000 $585.000 $775.000 $600.000 $825.000 $700.000 $692.000 $700.000 $788.000 $650.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 300.000 $220.000 $192.000 $172.000 $125.000 $210.000 $160.000 $195.000 $185.000 $101.000 $245.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 1,457.000 $190.000 $191.000 $165.000 $120.000 $210.000 $160.000 $175.000 $200.000 $131.000 $265.000
RAIL (TY SSTR)
LF 264.000 $70.000 $105.000 $121.000 $80.000 $150.000 $180.000 $155.000 $90.000 $327.000 $150.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 90.000 $225.000 $228.000 $220.000 $200.000 $200.000 $175.000 $290.000 $150.000 $275.000 $250.000
REMOV STR (BOX CULVERT)
LF 95.000 $90.000 $120.000 $75.000 $30.000 $75.000 $105.000 $125.000 $500.000 $100.000 $1,000.000
REMOVE STR (DRAINAGE FLUME)
EA 1.000 $2,000.000 $535.000 $900.000 $2,000.000 $2,400.000 $2,000.000 $2,000.000 $5,000.000 $1,580.000 $5,000.000
REMOV STR (PIPE)
EA 1.000 $800.000 $650.000 $1,500.000 $1,000.000 $1,200.000 $500.000 $2,500.000 $2,000.000 $1,580.000 $3,000.000
MOBILIZATION
LS 1.000 $120,705.000 $100,000.000 $125,000.000 $130,000.000 $22,000.000 $160,000.000 $90,000.000 $145,000.000 $134,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $1,550.000 $1,600.000 $4,000.000 $6,600.000 $912.150 $1,120.000 $2,000.000 $840.000 $4,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $100.000 $100.000 $60.000 $100.000 $82.000 $100.000 $265.000 $100.000 $240.000 $150.000
TMA (STATIONARY)
DAY 14.000 $200.000 $180.000 $300.000 $300.000 $180.000 $200.000 $265.000 $300.000 $350.000 $500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 238.000 $44.000 $49.500 $40.000 $20.000 $42.000 $47.250 $46.250 $1.000 $55.500 $45.000
ROCK FILTER DAMS (REMOVE)
LF 238.000 $11.000 $14.500 $10.000 $5.000 $13.000 $13.650 $14.300 $1.000 $16.000 $45.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 198.000 $80.000 $45.000 $50.000 $80.000 $28.000 $15.000 $50.000 $1.000 $89.000 $65.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 982.000 $4.000 $4.650 $3.950 $5.000 $4.500 $4.410 $4.950 $1.000 $6.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 982.000 $1.200 $1.350 $1.450 $1.000 $1.100 $1.260 $1.150 $1.000 $2.500 $3.000
DRIVEWAYS (CONC)
SY 319.000 $100.000 $78.000 $82.250 $120.000 $80.000 $95.000 $118.000 $90.000 $290.000 $133.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 1,544.000 $0.250 $2.200 $2.250 $1.250 $3.250 $3.070 $3.850 $1.500 $4.500 $10.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 772.000 $0.250 $4.000 $4.000 $2.500 $5.250 $5.610 $3.850 $1.500 $4.500 $10.000
MTL W-BEAM GD FEN (STEEL POST)
LF 100.000 $30.000 $33.000 $32.000 $40.000 $53.000 $31.500 $32.500 $30.000 $32.500 $50.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,400.000 $2,475.000 $2,400.000 $2,500.000 $3,800.000 $2,362.500 $2,570.000 $2,300.000 $2,420.000 $3,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,200.000 $3,605.000 $3,475.000 $3,500.000 $5,000.000 $3,438.750 $3,250.000 $3,300.000 $3,245.000 $4,000.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 2.000 $27,000.000 $28,050.000 $27,000.000 $24,000.000 $17,000.000 $26,775.000 $24,200.000 $26,000.000 $29,600.000 $20,000.000
CHAIN LINK FENCE (INSTALL) (8')
LF 152.000 $72.000 $22.000 $35.000 $30.000 $44.000 $50.000 $55.000 $25.000 $66.000 $100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $700.000 $720.000 $1,500.000 $800.000 $1,900.000 $1,358.700 $1,425.000 $800.000 $1,425.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 2.000 $103.000 $110.000 $150.000 $100.000 $150.000 $199.500 $210.000 $50.000 $209.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 6.000 $35.000 $22.000 $26.500 $5.000 $33.000 $18.900 $22.000 $20.000 $22.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1 (BI)
EA 5.000 $32.000 $39.000 $26.500 $6.000 $33.000 $26.250 $22.000 $25.000 $22.000 $50.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 24.000 $6.000 $11.000 $10.750 $175.000 $10.000 $10.500 $11.000 $20.000 $11.000 $19.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 1.000 $750.000 $1,320.000 $1,275.000 $625.000 $1,200.000 $1,260.000 $1,320.000 $500.000 $1,320.000 $600.000
RE PM TY II (W) 6" (SLD)
LF 280.000 $0.200 $2.200 $2.150 $1.250 $2.000 $2.100 $2.200 $5.000 $2.200 $1.250
RE PM TY II (Y) 6" (SLD)
LF 280.000 $0.200 $2.200 $2.150 $1.250 $2.000 $2.100 $2.200 $5.000 $2.200 $1.250
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 1,264.000 $0.600 $2.200 $2.150 $1.250 $2.000 $2.100 $2.200 $5.000 $2.200 $1.250
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 1,263.000 $0.600 $2.200 $2.150 $1.250 $2.000 $2.100 $2.200 $5.000 $2.200 $1.250
REFL PAV MRKR TY II-A-A
EA 41.000 $4.000 $8.800 $8.500 $8.750 $8.000 $8.400 $8.800 $15.000 $8.800 $8.500
ELIM EXT PM & MRKS (6")
LF 184.000 $0.500 $2.200 $2.150 $2.500 $2.000 $2.100 $2.200 $1.000 $2.200 $2.500
PAV SURF PREP FOR MRK (6")
LF 560.000 $0.800 $1.100 $1.150 $2.500 $1.000 $1.050 $1.100 $1.000 $1.100 $2.500
FULL - WIDTH MOWING
CYC 1.000 $5,500.000 $550.000 $1,000.000 $1,000.000 $600.000 $500.000 $1,980.000 $100.000 $1,650.000 $2,500.000
LITTER REMOVAL
CYC 1.000 $4,500.000 $500.000 $1,500.000 $1,000.000 $1,100.000 $500.000 $945.000 $100.000 $550.000 $2,500.000
Totals: $1,629,505.500 $1,516,226.340 $1,528,969.650 $1,532,375.300 $1,572,839.900 $1,623,970.510 $1,657,275.050 $1,730,478.500 $1,841,736.000 $2,341,953.250
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $55,000.00