Bid Cobra

SMITH VARIOUS (0910-16-185)

Items: 33

County: SMITH
Length: 0.0000 MILES
Highway: VARIOUS
District: TYLER
Control Number: 0910-16-185
DBE Goal: 0.0%
Project: F 2B24(309)
Guaranty: $31,000.00
Time: 144 WORKING DAYS
Engineer's Estimate: $1,555,500.00
Date: 11/06/2024 (1 year ago)
Contract Number: 11243024
Type: TRAFFIC SIGNAL IMPROVEMENTS
Project ID: A00198663
Project Description: FY 25 TRF SIGNAL UPGRADES. CONSTRUCT TRAFFIC SIGNAL UPGRADES TO OPTIMIZE COORDINATION AT VARIOUS INTERSECTIONS INSIDE THE CITY OF TYLER. (SEE ROADWAY LIST IN PROJECT COMMENTS)
Mail/Deliver Bids To: N/A
JUANITA DANIELSWEST
STEVEN SWINDELL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,555,500.00
1
$1,685,437.84
Over/Under Est: 8.35% $129,937.84
Over/Under Est: 16.84% $261,950.00
Amt Left: 7.83% $132,012.16
Over/Under Est: 17.37% $270,263.30
Amt Left: 8.33% $140,325.46
Delta: -0.46% -$8,313.30
Over/Under Est: 24.81% $385,892.50
Amt Left: 15.19% $255,954.66
Delta: -6.33% -$115,629.20
Over/Under Est: 60.99% $948,685.00
Amt Left: 48.58% $818,747.16
Delta: -28.99% -$562,792.50
$2,820,840.00
Over/Under Est: 81.35% $1,265,340.00
Amt Left: 67.37% $1,135,402.16
Delta: -12.65% -$316,655.00
Subcontractor Percentage Amount
VACA UNDERGROUND UTILITIES INC 28.72% $484,057.75
DIAMOND ELITE BARRICADES, LLC 0.75% $12,640.78
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.50% $8,427.19
TEX-SAFE SOLUTIONS 0.14% $2,359.61
Total: 30.11% $507,485.33

Bid Items & Bid Tabulations

33 Total 0 of 33
SMITH  |  VARIOUS  |  TYLER  |  0910-16-185  |  11/06/2024  |  $1,555,500.00  |  F 2B24(309)  |  TRAF SIGNAL IMPRVS  |  144 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
FLORIDA TRAFFIC CONTROL DEVICES, INC.
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SELECT MAINTENANCE, L.L.C.
STRIPING TECHNOLOGY, L.P.
FNH CONSTRUCTION, LLC
REMOVING CONC (MEDIANS)
SY 15.000 $50.000 $85.000 $240.000 $300.000 $30.000 $250.000 $100.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 9.000 $40.000 $85.000 $360.000 $300.000 $50.000 $250.000 $100.000
MOBILIZATION
LS 1.000 $140,000.000 $162,764.000 $180,000.000 $100,000.000 $190,000.000 $30,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $4,000.000 $13,688.880 $6,555.000 $5,000.000 $33,500.000 $1,800.000 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,470.000 $7.000 $0.010 $9.500 $10.000 $8.000 $100.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,470.000 $3.000 $0.010 $2.500 $10.000 $1.000 $10.000 $9.000
CONC SIDEWALKS (4")
SY 15.000 $120.000 $165.000 $275.000 $100.000 $125.000 $350.000 $100.000
CURB RAMPS (TY 22)
EA 3.000 $2,800.000 $3,500.000 $13,255.000 $4,500.000 $6,500.000 $5,000.000 $3,250.000
CONC DIRECTIONAL ISLAND
SY 55.000 $250.000 $250.000 $480.000 $400.000 $125.000 $380.000 $500.000
CONDT (PVC) (SCH 80) (3")
LF 2,590.000 $20.000 $16.800 $21.500 $20.000 $22.000 $30.000 $30.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 13,040.000 $35.000 $21.600 $27.250 $34.000 $23.000 $63.500 $60.000
ELEC CONDR (NO.6) BARE
LF 7,820.000 $3.000 $3.000 $1.750 $2.000 $2.000 $6.000 $3.000
GROUND BOX TY D (162922)W/APRON
EA 44.000 $1,300.000 $1,800.000 $1,925.000 $1,100.000 $1,500.000 $2,250.000 $1,500.000
REMOVE GROUND BOX
EA 1.000 $500.000 $510.000 $300.000 $500.000 $450.000 $600.000 $250.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 40.000 $3.000 $18.000 $18.000 $18.750 $15.000 $20.000 $6.000
PAVEMENT SEALER 6"
LF 120.000 $1.000 $6.000 $6.000 $6.250 $5.000 $5.000 $3.000
PAVEMENT SEALER 8"
LF 40.000 $1.000 $12.000 $12.000 $12.500 $10.000 $10.000 $6.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 120.000 $2.000 $30.000 $30.000 $31.250 $25.000 $10.000 $3.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 65.000 $15.000 $39.000 $38.500 $40.500 $32.500 $25.000 $20.000
REFL PAV MRKR TY I-C
EA 10.000 $10.000 $27.600 $27.750 $28.750 $23.000 $10.000 $6.000
ELIM EXT PAV MRK & MRKS (8")
LF 120.000 $1.000 $3.600 $3.500 $3.750 $3.000 $10.000 $6.000
ELIM EXT PAV MRK & MRKS (24")
LF 55.000 $5.000 $12.000 $12.000 $12.500 $10.000 $5.000 $20.000
PAV SURF PREP FOR MRK (6")
LF 120.000 $1.000 $3.600 $3.500 $3.750 $3.000 $5.000 $3.000
PAV SURF PREP FOR MRK (8")
LF 40.000 $1.500 $6.000 $6.000 $6.250 $5.000 $5.000 $6.000
PAV SURF PREP FOR MRK (RPM)
EA 10.000 $5.000 $4.200 $4.000 $4.380 $3.500 $5.000 $150.000
INSTALL HWY TRF SIG (UPGRADE)
EA 22.000 $1,000.000 $3,790.880 $1,515.000 $10,000.000 $15,000.000 $8,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 54.000 $150.000 $325.000 $195.000 $200.000 $75.000 $125.000 $150.000
GROUND BOX (PREPARE)
EA 41.000 $300.000 $510.000 $1,720.000 $500.000 $450.000 $575.000 $500.000
TMA (STATIONARY)
DAY 27.000 $200.000 $325.000 $200.000 $200.000 $165.000 $1,000.000 $250.000
VIVDS PROSR SYS
EA 22.000 $10,500.000 $13,472.760 $17,650.000 $12,500.000 $13,500.000 $17,400.000 $10,000.000
VIVDS CAM ASSY FXD LNS
EA 90.000 $4,500.000 $4,781.540 $4,550.000 $4,500.000 $3,500.000 $4,790.000 $10,000.000
VIVDS CNTRL SOFTWARE
EA 22.000 $500.000 $1,250.860 $665.000 $350.000 $250.000 $480.000 $1,500.000
VIVDS CABLING
LF 19,120.000 $3.000 $3.190 $2.000 $5.100 $1.000 $7.000 $3.000
Totals: $1,555,500.000 $1,685,437.840 $1,817,450.000 $1,825,763.300 $1,941,392.500 $2,504,185.000 $2,820,840.000